PCR2019054 Chase BSO Amend
RESOLUTION #P.C. 054-2019
APPROVAL OF A BUILDING, SITE AND OPERATION PLAN AMENDMENT FOR
CHASE BANK LOCATED IN THE SE ¼ OF SECTION 3
(TAX KEY NO. 2172.998 / S69 W15612 JANESVILLE ROAD)
WHEREAS, A submittal was received for a Building, Site and Operation (BSO) Plan amendment
for Chase Bank located at S69 W15612 Janesville Road / Tax Key No. 2172.998, and
WHEREAS, The petitioner is proposing to remove and replace the existing parking lot asphalt
and replace the garbage enclosure, and
WHEREAS, The slope of the existing ADA parking stalls will be modified to comply with current
ADA requirements in addition to the replacement of the concrete walk leading from the ADA
parking stalls to the bank entrance, and
WHEREAS, Typically commercial parking areas are required to be set back from the right-of-way
three (3) feet. However, along Janesville Road the Plan Commission has generally allowed
businesses to have their parking area up to the property line, if there are stiuations where former
paving was in or up to the right-of-way line, and
WHEREAS, The petitioner is proposing to remove the asphalt that extends into the right-of-way
and return the areas back to lawn, and
WHEREAS, None of the site currently contains curbing, and
WHEREAS, A new handicap sign is proposed near the entrance to the bank with a concrete
bollard extending from the ground four (4) feet in height, and
WHEREAS, A dumpster enclosure is proposed in the northeast corner of the site and the
enclosure is to be screened with a cedar plank fence, and
WHEREAS, No new site bollards, lighting or signage have been proposed at this time, and
WHEREAS, The existing light fixtures that have been mounted to the roof of the building do not
meet the city standards that all lighting must be full cut-off with zero degree tilt, as the lights shine
onto Janesville Road and the light source is directly visible.
THEREFORE BE IT RESOLVED, The Plan Commission approves of an amended Building, Site
and Operation Plan for Chase Bank at S69 W15612 Janesville Road / Tax Key No. 2172.998.
BE IT FURTHER RESOLVED, For the proposed work, proper permits are required to be issued
prior to any work commencing, including a Zoning Permit, Building Permit, Electrical Permit
and/or possible Land Disturbance Permit.
BE IT FURTHER RESOLVED, An exterior lighting plan, for all existing and proposed lighting, is
required and will need approvals, before any site work can occur, from the Planning Division to
ensure that all exterior lighting meets the code requirements.
BE IT FURTHER RESOLVED, Since the entire site is being repaved, the exterior perimeter of the
site will need to contain concrete curb and gutter and said plans must be submitted before any
permits can be issued.
BE IT FURTHER RESOLVED, Any handicap signs, no parking signs or other information signage
must be mounted in the ground or on the building and cannot be on a moveable base.
BE IT FURTHER RESOLVED, Any bollards protecting the building, parking signs or other site
features must be painted a color to match the building.
BE IT FURTHER RESOLVED, All driveway and parking surfaces must be located within the lot
lines and the owner is responsible for knowing where the lot lines are.
BE IT FURTHER RESOLVED, The gate of the dumpster enclosure must be constructed out of
the same material as the fencing, which must compliment the color of the building.
BE IT FURTHER RESOLVED, A copy of said plans must be kept on file and that all aspects of
this plan shall be maintained in perpetuity unless otherwise authorized by the Plan Commission.
BE IT FURTHER RESOLVED, Failure to comply with the approval contained in this resolution
shall result in the imposition of fines of $100 per day, the initiation of legal action, or both.
Plan Commission
City of Muskego
Adopted: September 3, 2019
Denied:
Deferred:
Introduced: September 3, 2019
ATTEST: Adam Trzebiatowski, Planning Manager