PCR2018065 Heinrich 4 Lot CSM
RESOLUTION #P.C. 065-2018
APPROVAL OF A FOUR LOT CERTIFIED SURVEY MAP FOR THE HEINRICH
PROPERTY LOCATED AT S102 W16204 HEINRICH DRIVE / TAX KEY NO. 2268.996
WHEREAS, A Certified Survey Map (CSM) was submitted by Frank Heinrich for a four (4) lot land division
located at S102 W16204 Heinrich Drive / Tax Key No. 2268.996, and
WHEREAS, The proposed lots range in size from 134,886 SF (3.09 acres) to 1,241,128 SF (28.49 acres) in
size, and
WHEREAS, The property is zoned A-1 Agricultural District, which requires a minimum lot size of 120,000
square feet and average lot width of 300 feet, and
WHEREAS, The 2020 Plan depicts the area for rural density residential use and the proposal is consistent
with the plan, and
WHEREAS, All lots will be serviced by private on-site septic/mound systems and private water wells, and
WHEREAS, Lots 3 and 4 are vacant, Lot 1 contains an outbuilding, and Lot 2 contains an existing home
along with numerous farm buildings, and
WHEREAS, It was determined by the Public Works Committee that actual Heinrich Drive roadway does not
need to be extended since only one additional home will front on the extended right-of-way and since there
is an existing driveway leading to the home, and
WHEREAS, Heinrich Drive also currently has a turn-around easement and a paved cul-du-sac that will
continue to be utilized.
THEREFORE BE IT RESOLVED, That the Plan Commission approves of a Certified Survey Map submitted
by Frank Heinrich for a four (4) lot land division located at S102 W16204 Heinrich Drive / Tax Key No.
2268.996 subject to resolution of technical discrepancies as identified by the City Engineers, and payment
of all applicable fees and outstanding assessments if applicable.
BE IT FURTHER RESOLVED, A soil boring/test must be conducted to determine the highest anticipated
seasonal ground water level and to see were/if the lots can have a mound/septic system and reports of the
findings of those items must be provided to the City for review.
BE IT FURTHER RESOLVED, The square footage of all outbuildings must be shown on the CSM to ensure
that the lot is large enough to support the total outbuilding size.
BE IT FURTHER RESOLVED, The outbuilding on Lot 1 will need to be removed within one (1) year of
recording of the CSM unless a home is built on the property by that time.
BE IT FURTHER RESOLVED, The existing turn-around easement document needs to be provided to the
City and reviewed to ensure that it is still valid and adequate.
BE IT FURTHER RESOLVED, All technical corrections from the City will need to be addressed before the
Certified Survey Map can be signed and recorded.
BE IT FURTHER RESOLVED, A digital file of this CSM shall be submitted to the City in accordance with
Common Council Ordinance No. 1118 and Resolution 196-2002.
Plan Commission
City of Muskego
Adopted: December 4, 2018
Defeated:
Deferred:
Introduced: December 4, 2018
Page 2
ATTEST: Adam Trzebiatowski, Planning Manager