PCR2017030 High School
RESOLUTION #P.C. 030-2017
APPROVAL OF A BUILDING SITE AND OPERATION PLAN AMENDMENT FOR
MUSKEGO HIGH SCHOOL LOCATED IN THE NW ¼ OF SECTION 21
(TAX KEY 2242.999 / W185 S8750 RACINE AVE.)
WHEREAS, A submittal was received from Bray Architects on behalf of Muskego High School for
a property located at W185 S8750 Racine Ave. (Tax Key No. 2242.999), and
WHEREAS, The petitioner is proposing to add three new structures at the south end of the
existing football field, and
WHEREAS, The structures will frame a new entry to the football stadium and be used for
concession sales, restrooms, storage, and ticket sales, and
WHEREAS, There are also site improvements proposed that include patio areas, outdoor
seating, new sidewalks, and replaced fencing, and
WHEREAS, The proposed structures are similar in design, material usage, and colors to the
newer portions of main high school building and contain materials such as matching brick and
metal wall panels, and
WHEREAS, Landscaping is proposed around the base of the new structures, and
WHEREAS, Various signage elements are proposed on the new structures, and
WHEREAS, Downcast lighting is proposed on the building walls and under the overhang/canopy
areas.
THEREFORE BE IT RESOLVED, That the Plan Commission approves of an amended Building,
Site and Operation Plan from Bray Architects on behalf of Muskego High School located at W185
S8750 Racine Ave. (Tax Key No. 2242.999).
BE IT FURTHER RESOLVED, A formal landscape plan must be reviewed by the City Forester
before permits can be issued.
BE IT FURTHER RESOLVED, The plans for this use and layout may require review by the Fire
Department for proper fire protection and access prior to the issuance of building permits.
BE IT FURTHER RESOLVED, Any exterior (ground or roof mounted) mechanicals (HVAC units,
transformers, exhaust features, etc.) must be screened from surrounding view and details relating
to the location and size of these features must be provided at Building Permit time.
BE IT FURTHER RESOLVED, No outdoor storage or display is allowed on site unless specific
Plan Commission approvals are granted in the future for any storage and all dumpsters/recycle
bins must be located within the existing trash enclosures on site and/or within the newly approved
buildings.
BE IT FURTHER RESOLVED, Any bollards must be painted to match the color of the buildings.
BE IT FURTHER RESOLVED, Any signage (temporary or permanent) will require staff level
reviews to see if sign permitting is required.
BE IT FURTHER RESOLVED, A copy of said plans must be kept on file and that all aspects of
this plan shall be maintained in perpetuity unless otherwise authorized by the Plan Commission.
BE IT FURTHER RESOLVED, Failure to comply with the approval contained in this resolution
shall result in the imposition of fines of $100 per day, the initiation of legal action, or both.
Plan Commission
City of Muskego
Adopted: April 4, 2017
Denied:
Deferred:
Introduced: April 4, 2017