PCR2015040
RESOLUTION #P.C. 040-2015
APPROVAL OF A BUILDING SITE AND OPERATION PLAN AMENDMENT FOR
AMERICAN HYDRAULICS LOCATED IN THE SW ¼ OF SECTION 16
(TAX KEY 2223.006/ S83 W18666 SATURN DRIVE)
WHEREAS, On June 29, 2015 a submittal was received from Jim Hurst for American Hydraulics
located at S83 W18666 Saturn Drive (Tax Key No. 2223.006), and
WHEREAS, An addition of 2,244 SF is proposed to add on more warehousing/manufacturing
space to the existing building on site, and
WHEREAS, The new addition is proposed to be clad with steel wall panels and a steel roof and
all materials and colors proposed will match the existing building materials and colors found on
the existing structure, and
WHEREAS, The General Design Guide calls for commercial/industrial structures to be 50%
masonry at Planning Commission discretion and the addition proposed matches the material
usage found along the other facades of the structure, and
WHEREAS, The addition will extend off the northern portion of the existing building and the
existing parking/access will remain the same as today, and
WHEREAS, No new landscaping and no new lighting is proposed at this time, and
WHEREAS, There are some existing unscreened dumpsters and outdoor storage on site.
THEREFORE BE IT RESOLVED, That the Plan Commission approves of an amended Building,
Site and Operation Plan for Merit Asphalt located at S83 W18666 Saturn Drive (Tax Key No.
2223.006).
BE IT FURTHER RESOLVED, As part of the building permit process a Plat of Survey needs to be
submitted for the site including the proposed addition to ensure compliance with all
setbacks/offsets.
BE IT FURTHER RESOLVED, A material cost list for the addition must be provided as part of the
building permit to make sure it does not exceed 50% of the current FMV of the current building
value due to the existing non-conforming building location.
BE IT FURTHER RESOLVED, That a grading plan will need to be submitted as part of the
building permit to show how the addition will work with the existing grades and/or how t he grades
will be modified to accommodate the addition.
BE IT FURTHER RESOLVED, That a dumpster enclosure is required and a plan showing such
must be submitted to screen the dumpster as part of the building permit process.
BE IT FURTHER RESOLVED, That all other outdoor storage must be stored within the building
or removed from the site before occupancy for the addition would be granted.
BE IT FURTHER RESOLVED, That a copy of said plans be kept on file and that all aspects of
this plan shall be maintained in perpetuity unless otherwise authorized by the Plan Commission.
BE IT FURTHER RESOLVED, That failure to comply with the approval contained in this
resolution shall result in the imposition of fines of $100 per day, the initi ation of legal action, or
both.
Plan Commission
City of Muskego
Adopted: July 7, 2015
Denied:
Deferred:
Introduced: July 7, 2015
ATTEST: Kellie McMullen, Recording Secretary