PCR2005131RESOLUTION #P.C.131-2005
APPROVAL OF A BUILDING SITE AND OPERATION PLAN
FOR TWO (2), TWO-FAMILY RESIDENTAIL STRUCTURES
LOCATED IN THE SE ¼ OF SECTION 3
(LOTS 3 & 8 OF NORTHFIELD GREEN / TAX KEY NOS. 2172.013 & 2172.018)
WHEREAS, On October 28, 2005 plans were submitted by RJM Builders for a Building,
Site and Operation Plan for two (2), two-family residential structures located in the SE ¼
of Section 3, and
WHEREAS, Said property is currently zoned RSA Attached Single Family Residence
District and said use is a permitted use, and
WHEREAS, Said parcel will be serviced by public sewer and water facilities, and
WHEREAS, Said property is subject to the design standards outlined in the City of
Muskego’s General Design Guide and the Moorland South Design Guide, and
WHEREAS, The petitioner requests approval for two (2), two-family ranch dwellings on
Lots 3 & 8 of the Northfield Green Subdivision, and said structures appears to meet the
requirements of the zoning ordinance in accordance to the setbacks and offsets of the
site, and
WHEREAS, The Moorland South Design Guide promotes structures to utilize Craftsman
or Prairie Style influences, and
WHEREAS, Said structure is proposed to be constructed with exterior materials which
include Irish Cream colored brick, a brick ledge, Navajo Beige colored hardiplank siding
with Khaki Brown trim, Sandstone Beige hardiplank Shake, and dimensional asphalt
shingles, and
WHEREAS, Said structure includes architectural elements including lower pitched roofs,
tapered columns, shake material in the gables, decorative paneling with louvers within
the front gable, and prairie style windows, and the elements appear to meet the intent of
the Moorland South Design Guide for craftsman style architecture, and
WHEREAS, The parking will be handled by two-car attached garages and
concrete/asphalt driveways with room for at least two (2) additional guests, and
WHEREAS, A landscaping plan has been submitted and needs a few minor
adjustments.
THEREFORE BE IT RESOLVED, That the Plan Commission approves of the Building,
Site and Operation Plan submitted by RJM Builders for two (2), two-family residential
structures located in the SE ¼ of Section 3.
BE IT FURTHER RESOLVED, That a revised landscape plan must be submitted and
approved by the City Forester before building permits are released.
BE IT FURTHER RESOLVED, That the approval is subject to any architectural or
material additions that the Planning Commission may require and those would have to
be reviewed and approved by the Planning Department before the issuance of building
permits.
BE IT FURTHER RESOLVED, That there needs to be a greater degree of color
difference than proposed, between any structures that are next to each other and these
will have to be reviewed and approved by the Planning Department before the issuance
of building permits.
BE IT FURTHER RESOLVED, That a copy of said plans be kept on file in the Building
Department and that all aspect of this plan shall be maintained in perpetuity unless
otherwise authorized by the Plan Commission.
BE IT FURTHER RESOLVED, That if occupancy is requested prior to the completion of
landscaping and/or asphalting, a bond, or cashiers check equal to twice the value of said
costs must be submitted to the Planning Department.
BE IT FURTHER RESOLVED, That failure to comply with the approval contained in this
resolution shall result in the imposition of fines of $100 per day, the initiation of legal
action, or both.
Plan Commission
City of Muskego
Adopted:
Defeated:
Deferred: November 15, 2005
Introduced: November 15, 2005
ATTEST: Sandi Asti, Recording Secretary