PCR2002064RESOLUTION #P.C. 064-2002
HARRY'S CONCRETE BREAKING AND SAWING AT THE PROPERTY LOCATED AT W146
APPROVAL OF AN AMENDMENT TO THE BUILDING SITE AND OPERATION PLAN FOR
S6420 TESS CORNERS DRIVE I TAX KEY NO. 2165.998.003)
WHEREAS, On April 6, 2002 plans were submitted by Mark Gerls d/b/a Harry's Concrete Breaking and
Sawing for a Building, Site and Operation Plan amendment for the property located at W146 S6420 Tess
Corners Drive I Tax Key No. 2165.998.003, and
WHEREAS, The property is zoned 1-1. Industrial Park District, and the proposed use is permitted within
the District, and I WHEREAS, An additional 10,600 square feet of asphalt is proposed to be installed along the north and
west of the existing building, and the existing paved area is proposed to be refinished, and said
installation meets the Code requirements as illustrated, and
WHEREAS, The petitioner is proposing to install an overhead door along the east elevation where none
I
! currently exists, and details of the overhead door have not been provided at this time, and
WHEREAS, Stormwater management plans have been submitted, and are currently undergoing in-
house, engineering review, and
existing building, and a detailed plan illustrating planting materials and sizes is required to be provided for
WHEREAS, The petitioner is proposing to extend the landscape area across the west elevation of the
review, and to date none has been provided, and
THEREFORE BE IT RESOLVED, That the Plan Commission approves of a Building, Site and Operation
Plan amendment for the Harrv's Concrete Breakino and Sawino located on the orooertv at W146 S6420 e Tess Corners Drive.
BE IT FURTHER RESOLVED, That Planning Staff believes the addition of the overhead will have a
detail shall be provided to the Planning Department for review prior to the release of building permits.
negligible aesthetic effect for the surrounding properties, and an elevation drawing and overhead door
BE IT FURTHER RESOLVED, That a detailed plan illustrating planting materials and sizes is required to
be provided to the Planning Department prior to the release of building permits.
BE IT FURTHER RESOLVED, That stormwater management plans be approved by the Building and
Engineering Department prior to the release of permits.
BE IT FURTHER RESOLVED, That a copy of said plans be kept on file in the Building Department and
that all aspects of this plan as they relate to landscape areas and drainage shall be maintained in
perpetuity unless otherwise authorized by the Plan Commission.
BE IT FURTHER RESOLVED, That if occupancy is requested prior to the completion of landscaping
andlor asphalting, a bond, letter of credit or cashiers check equal to twice the value of said costs must be
submitted to the Planning Department.
BE IT FURTHER RESOLVED, That failure to comply with the approval contained in this resolution shall
result in the imposition of fines of $100 per day, the initiation of legal action, or both.
City of Muskego
Plan Department
Adopted: May 7,2002
Deferred:
Defeated: _-
ATTEST.
Introduced: May 7, 2002
Sandi Asti, Recording Secretary
d. LhL