PCR1996019AMENDED RESOLUTION #P.C. 19-96
APPROVAL OF CERTIFIED SURVEY MAP CREATING THREE LOTS
OF THE FERRITO PROPERTY LOCATED IN
THE SE 1/4 OF SECTION 23
(BOXHORN DRIVE)
WHEREAS, A Certified Survey Map was submitted on January 25,
1996, to create a three (3) lot land division located in the SE
1/4 of Section 23, and
WHEREAS, A sketch was approved for a three (3) lot land
division, and
RS-2 (20,000 square foot lots) when the sewer project is
completed and said proposal appears to meet the requirements of
said Zoning District, and
WHEREAS, The property is zoned R-2 and will be rezoned to
WHEREAS, The proposed parcels are intended to be serviced by
municipal sewer, and
WHEREAS, The proposed parcels will have access from Boxhorn
Drive.
THEREFORE BE IT RESOLVED, That the Plan Commission, in
consideration of unique configuration and physical
attributes/limitations, approve the Certified Survey Map for a
three (3) lot land division in the SE 1/4 of Section 23 of the
Ferrito Property and recommend approval to the Common Council
by the City Engineers, City Staff and the Plan Commission and
subject to resolution of technical discrepancies as identified
payment of all applicable fees in Section 18.14(3) of the Land
Division Ordinance.
BE IT FURTHER RESOLVED, That a note on the Certified Survey
Map state that no further land division shall be allowed on
Parcels 1, 2, and 3.
BE IT FURTHER RESOLVED, That a drainage plan must be
submitted prior to the issuance of any building and zoning
permits for all three parcels.
BE IT FURTHER RESOLVED, That access to parcel 3 must be
approved by the Fire Department.
BE IT FURTHER RESOLVED, That after six (6) months of
approval, the 491 square foot garage structure must be moved
from parcel 2 to parcel 3.
on Parcel 1.
BE IT FURTHER RESOLVED, That a sewer easement must be shown
Plan Commission
City of Muskego
Adopted 02/06/96
0 Defeated
Deferred
01-29-96