PCR1994170AMENDED
RESOLUTION #P.C. 170-94
APPROVAL OF EXPANSION OF CONDITIONAL USE GRANT
A LANDSCAPE BUSINESS BY JOHN GLOCKNER AT THE PROPERTY
& AMENDED BUILDING, SITE AND OPERATION PLAN TO ALLOW
LOCATED AT 571 W13219 TESS CORNERS DRIVE
~
WHEREAS, The Plan Commission of the City Of Muskego has
use Grant #lo2 which currently allows a for sand and gravel
received a petition for the expansion of the current Conditional
extraction at S71 W13219 Tess Corners Drive to include a
landscape business also at said location, and
WHEREAS, It is intended to store four (4) trucks and one (1)
trailer and mulch at any one time and for them to be parked east
of the existing driveway, and it is possible that nursery stock
limited to that which is needed for contracted jobs may be
stored at this location, and
behind the existing gate and the area is proposed to be 220' x
30' in area along the east side of the existing driveway, and
WHEREAS, The area is 270' from the edge of the property and
WHEREAS, The owners of property within 300 feet of this
property have been notified of the Public Hearing, and a Public
Hearing has been held in conformance with Section 17:3.07 of the
City's Code of Ordinances.
THEREFORE BE IT RESOLVED, That the Plan Commission of the
City of Muskego does hereby recommend approval of the expansion
of Conditional Use Grant #lo2 at S71 W13219 Tess Corners Drive
subject to the following conditions:
1. Parking or storages of inoperable employee and customer
vehicles is prohibited. In the event of an inoperable
company vehicle, said vehicle shall be repaired or removed
from the property in a timely manner.
2. An appropriately sized dumpster(s) shall be provided.
3. No storage, dumping, landfilling or burning of twigs,
branches, stumps logs, leafs, grass clippings, discarded
potting vessels on host property.
4. No storage of above or below ground fuel tanks; existing
fuel tanks shall be removed.
5. Site shall be maintained in a neat and orderly fashion.
6. The mixing and storage of any herbicides and pesticides
shall be conducted in compliance with all applicable State
and Federal regulations.
7. Review of this operation shall be on an annual basis
to coincide with the annual review of the extractive
operations.
BE IT FURTHER RESOLVED, That the amended Conditional Use
Grant be recorded within 30 days of the approval by the Plan
Commission.
BE IT FURTHER RESOLVED, That all reference to parking of
trucks is specifically parking and not storage and that the
trailer referenced is an open trailer for equipment hauling.
Plan Commission
City of Muskego
Adopted 09-06-94
Defeated
Deferred
09-01-94