Loading...
PCR1975020RESOLUTION #P. C. 20-75 ESTABLISHING GUIDELINES FOR THE DEVELOPMENT OF WILDFLOWER PLANNED UNIT DEVELOPMENT 0 WHEREAS the developers of the proposed Wildflower planned unit development have appeared several times before the Commission with presentations for the Commission to consider, and WHEREAS at the Commission meeting held on March 4th, 1975, Aldrian dated February 7, 1973, and the developers presented a proposal drafted by Shephard, Legan & resolved problems and the developer has requested that the Commission advise them what is needed to have the project given furher consid- eration by the Commission which would result in a favorable recommen- dation to the Sewer Committee and the Common Council, and WHEREAS following the presentation there remained several un- WHEREAS the Plan Commission of the City of Muskego wishes to indicate its willingness to give a favorable recommendation to the can be resolved. Sewer Committee and the Common Council if the few remaining problems THEREFORE BE IT RESOLVED that the Plan Cmission of the City of Muskego does hereby indicate its willingness to consider a to the Sewer Committee and the Common Council subject to the following: favorable recommendation of the Wildflower planned unit development 1. A relocation of the parkway in such a way as to provide sufficient room on the north side of the parkway to incorporate the zero lot line patio homes which are presently located on the south side which will provide better access to the open space of the planned unit development by both the residents of the development and the public. It is the wish of the Plan Commission to create an open lineal parkway. 2. The developer shall provide sufficient evidence that the proposed water impoundment ponds- will, in fact, sufficiently reduce the flooding problems presently occurring on Richdorf Drive or in lieu of that, a proposal to storm sewer the water to the lake. 3. Assurances that the road leading from Hillendale which will eventually become a parkway will be completely constructed to its termination at the south lot line of the project in the first phase or in lieu of that? provide a cash bond in a sufficient amount to assure its completlon at a later date. 4. A presentation to the Commission which would show how the smaller parcel (3 to 5 acres) adjacent to Sunny Hill Drive will be removed from this project and developed or the inclusion of the smaller parcel in the overall project. 0 Page 2 Resolution #P. C. 20-75 will 2 e provided for the planned unit development. , A commitment that some form of recreational facilities 6. A comitment that curb and gutter (and storm sewer) will be provided where deemed necessary by the city's engineers. 7. A statement showing the different phases of development and how they conform to Resolution #40-75 As Amended. BE IT FURTHER RESOLVED that any subsequent approval by the Cmission will be subject to the understanding that all requirements of Section 6.02 of the Muskego Zoning Ordinance shall be met which shall include, but is not limited to, engineering, financial ability, open space maintenance agreement, developer's agreement, etc. City of Muskego Plan Cmission Adopted MAR1 8 1975 0 ~~ Defeated Deferred bj s 3-18-75