Loading...
CCR1968011RESOLUTION {Ill-68 GRANTING C & C CONSTRUCTION CO. AN EXTENSION OF THE CONTRACT COMPLETION TIME ON THE SEWER STABILIZATION PROJECT WHEREAS C & C Construction Company has requested a 6-week extension 8 of the contract completion time on the sewer stabilization project, and WHEREAS the request for additional time is required because of the additionlbeat incurred and delays due to the wet weather in October, and, WHEREAS the Sewer Committee has recommended granting the request, THEREFORE BE IT RESOLVED that the Common Council of the City of Muskego does hereby grant to C & C Construction Company a 6-week extension of their contract completion time on the sewerage stabilization contract. PUBLIC SEVER COMMITTEE aq5cHL Walter Wollman Edmund Budish I Roland PL4LJ Linck \ 0 ATTEST: _. n /L” I City Clerk je 1/68