Mayor Petfalski called the meeting to order at 5:39 pm.
ROLL CALL
\ 1 ue, cxy of
SKEGO
APPROVED
Present: Mayor Petfalski, Alderperson Wolfe, Alderperson Hammel, Alderperson Decker, Alderperson
Schwer, Alderperson Kubacki
Absent: Alderperson Schroeder, Alderperson Madden
Also present: City Attorney Warchol, Public Works & Development Director Kroeger, and City Clerk
Roller
STATEMENT OF PUBLIC NOTICE
City Clerk Roller stated that the meeting was noticed in accordance with the open meeting law.
APPROVAL OF AGENDA
Moved by Alderperson Kubacki; seconded by Alderperson Hammel to Approve.
Motion Passed: 5 - 0
Voting For: Alderperson Wolfe, Alderperson Hammel, Alderperson Decker, Alderperson Schwer,
Alderperson Kubacki
Voting Against: None
APPROVAL OF MINUTES
Committee of the Whole Meeting Minutes - January 23, 2024
COWM24.01.23.docx
Moved by Alderperson Hammel; seconded by Alderperson Wolfe to Approve.
Motion Passed: 5 - 0
Voting For: Alderperson Wolfe, Alderperson Hammel, Alderperson Decker, Alderperson Schwer,
Alderperson Kubacki
Voting Against: None
NEW BUSINESS
Alderperson Schroeder arrived at 5:40 pm.
Topics for Discussion
-- Direct Connections to the City of Muskego Sanitary Sewer System
-- Update on Per- and Polyfluoroalkyl Substances (PFAS)
-- Water Capacity Assessment District
(1) Mr. Kroeger mentioned the storm which hit Muskego in April. The sanitary sewer system is
about 1.9 million gallons and we were 6" away from having to start the bypass and dump in the
creek. Levels were monitored by cameras and a lot of clear water was observed in the system.
Residents are probably unaware they are dumping clear water into the sanitary sewer. The City
would like to educate them to get sump pumps to drain water their front yards or drainage
easements. Another option is to put in a skeleton sewer which flows into the storm sewer. It took
48 hours to drain out the sanitary sewer system.
(2) PFAS, the "forever chemical". The EPA came out with their new standards. The DNR standard
was 70 parts per trillion and now the APA rule just adopted by the DNR is 4 parts per trillion. We
have been testing for PFAS for the last year. The City of Muskego is under DNR and EPA.
There are no communities that meet the new standards. We are making sure we are following
all of the rules of the DNR and that we test everything.
Committee of the Whole Meeting Minutes — 5/14/24
Page 12
(3) After Mr. Kroeger explained the Water Capacity Assessment District and what needs to be
done, he asked how we want to handle them going forward. For now, we are going to do one
specific quadrant from Janesville at Kwik Trip to the north to the city limits and Racine west to
the city limits. This topic will go on a future Committee of the Whole for more discussion.
COMMUNICATIONS AND MISCELLANEOUS BUSINESS AS AUTHORIZED BY LAW
None.
ADJOURNMENT
Moved by Alderperson Kubacki; seconded by Alderperson Schroeder to Adjourn at 6:33 pm.
Motion Passed: 6 - 0
Voting For: Alderperson Wolfe, Alderperson Hammel, Alderperson Decker, Alderperson Schwer,
Alderperson Schroeder, Alderperson Kubacki
Voting Against: None
Minutes recorded by City Clerk Roller and transcribed by Assistant Deputy Clerk -Treasurer Crisp.