PSEM19730205PUBLIC SEWER COMMITTEE - CITY OF MUSKEGO
MINUTES OF MEETING HELD ON FEBRUARY 5, 1973
• The meeting was called to order by Chairman Schaumberg at 10:30 A.M. Also
present were Aldermen Knudsen and Dumke and Mayor Gottfried.
Mr. Mike Belam of Relocation Realty and Mr. Al Butenhoff of Mutual Builders
• appeared at the meeting to request sewer service to approximately five acres
of land which they own west of Valley Drive and adjacent to the Kelly property.
Mr. Ray Wallner, Agent for Muskego Industrial Park, Inc. appeared to request
that they be allowed to connect into the city's municipal sewer system to
serve their 98 acres west of Racine Avenue under the present zoning.
Mr. Herbert C. Puetzer, representing M.C. Development Co., Inc. appeared
to request to be connected into the municipal sewer system to serve the
former Lazynski-Beck property. His request was based on the present zoning
of R-3 which would allow 99 single family homes and using the 65% limit
would add 22,522 gallons per day of sewage to the system. He further stated
that the entire deferred sewer assessment of approximately $52,000.00
would be paid in full.
Ald. Schaumberg moved, as seconded by Ald. Knudsen, to grant the request
of Superior Excavators an extension of time on their sewer project in
Hi-Y Ranches Subdivision area. Motion carried. Mayor Gottfried will
send a letter along with the notice of extension of time suggesting that
the roads in their project which are in deplorable condition need grading.
The following correspondence was reviewed:
From Mayor Gottfried directed to Michels Pipeline Construction Co., dated
1/26/73, advising them that the City of Muskego would retain $200.00
plus $105.40 to cover revenues lost to the city because of late completion
of their project.
From Mayor Gottfried, directed to United Sewer & Water, Inc., dated 1/30/73,
regarding an agreement between the city and their representative wherein
it was determined that $1,000.00 plus $1,485.20 will be paid to the city
covering revenue lost as a result of late completion date of their project
and the city is releasing all but $5,000.00 plus the settlement amount.
From Mayor Gottfried directed to Rock Contractors, dated 1/26/73, con-
firming an agreement between the city and their representative regarding
• therein it was determined that the $1,000.00 plus $1,169.60 will be paid
to the city to cover revenues lost as a result of late completion date
of their projects and that the city is releasing all but $5,000.00 plus
• the settlement amount.
From Mayor Gottfried directed to the Parker Co. regarding restoration, etc.
of their sewer project in the northeast district.
United Sewer & Water's request for additional payment which would reduce the
amount held back from $5,000.00 to $1,500.00 and $2,000.00 respectively,
was deferred pending review of the area by the committee.
Ald. Schaumberg moved, as seconded by Ald. Dumke,to establish the following
calendar quarters for sewer billing for the northeast district and Hillendale
and Hi-Y Ranches Subdivision area:
Public Sewer Committee
2/5/73
•
G-7 - Northeast District
• Calendar Quarters Payment Date
December 1 to February 28 March 1
March 1 to May 31 June 1
June 1 to August 31 September 1
September 1 to November 30 December 1
H-8 - Northwest District
Hillendale Heights & Hi-Y Ranches Subdivision Area
Calendar Quarters
• February 1 to April 30
May 1 to July 31
•
August 1 to October 31
November 1 to January 31
Motion carried.
Payment Date
May 1
August 1
November 1
February 1
Action on the requests of Relocation Realty, Ray Wallner and Herbert
Puetzer (M.C. Development Co.) was deferred until the next meeting.
Ald. Knudsen moved to adjourn, seconded by Ald. Schaumberg, motion
carried. The meeting adjourned at 12:43 P.M.
Public Sewer Committee