PUM20040216APPROVED
CITY OF MUSKEGO
PUBLIC UTILITIES COMMITTEE MEETING
Minutes of Meeting Held Monday February 16, 2004
Chairman Eric Schroeder called the meeting to order at 7:05 p.m. Also present
were Committee members Aid Pat Patterson, Aid. Rick Petfalski, Utilities
Superintendent Scott Kloskowski, Engineer and Building Inspection Director
Sean McMullen and Ruekert & Mielke representative Steve Schultz.
It was noted that the meeting was posted in accordance with the Open Meeting
Law.
Those present recited the Pledge of Allegiance.
APPROVAL OF MINUTES OF PREVIOUS MEETING
Aid. Patterson moved to approve minutes of January 19, 2004. Seconded
by Aid. Petfalski, motion carried 3-0.
Aid. Patterson moved to approve minutes of January 27, 2004. Seconded
by Aid. Petfalski, motion carried 3-0.
STATUS OF PROJECTS
Steve Schultz updated the committee on the attached status of on -going projects
as follows:
• Big Muskego Estates — Utility construction completed week of
February 1, 2004. Punch list repairs waiting for pavement
installation.
• Well exploration project — Finished geophysics on all sites except
North Cape and Ryan. A different piece of equipment is needed.
Reports for all other sites being done. Borings can be started.
• Northfield Green - Revised construction plans received for review
February 10, 2004. Utility plans recommended for approval
February 11, 2004.
• Stonerige Ground Water Remediation —There was a meeting with
the consultant of Stoneridge. EPA should have the consultants
final work plan. Sampling on Well 7 should be started.
• Lakewood Meadows — Legal documents'are done. Two issues that
remain are the legal description does not match what is actually out
Public Utilities Committee Meeting — February 16, 2004 Page 2
there and trying to finalize who has to sign the agreement, the
water trust or 70% of the members.
• CCV/Stonebridge Watermain Extension — All exeptions have been
taken off the title. Three signatures are needed. Recapture
Agreement will go to Council on February 24, 2004.
• Proposed Development — Valley Sand and Gravel site — New Berlin
Plan Commission will be meeting in March. Ruekert & Mielke will
be doing a ground water remediation presentation.
SEWER UNFINISHED BUSINESS
Status of Town of Norway Contract - Director McMullen explained a contract is
no longer needed. Town of Norway agreed to 16% of planned capacity for
Muskego. Muskego and Town of Norway came to agreement what flow
allocations will be and lift station upgrade cost will be. Item will remain on the
agenda until the City receives the new Resolution.
Status of claims from West Lake, Lake Lore and Lake Brittany — Nothing new to
report.
Review Invoices for water treatment — West Lake Homeowner's Association -
Nothing new to report.
SEWER NEW BUSINESS — Nothing new.
WATER UNFINISHED BUSINESS
Establish policy for Champions Villaae (WCA) connection charae — Director
McMullen explained six of the remaining buildable lots are owned either by the
Developer or a subsidiary of Burke Properties. One of the remaining lots is
owned by Mr. Heidenreich, and possibly the lot is not buildable. Aid. Petfalski
moved to charge WCA charges 60 days after the date of signing the
agreement. Aid. Patterson seconded, motion carried 3-0.
WATER NEW BUSINESS
Review quotes for water tower inspection — Superintendent Kloskowski reviewed
a letter from Ruekert & Mielke explaining the four ways the tank was proposed to
be inspected. Aid. Petfalski moved to approve Dixon Engineering doing a
dry tank inspection at $4015.00. Seconded by Aid. Patterson, motion
carried 3-0.
Discuss possibilities for water service — Kenwood Place — Mr. Kenneth Laschen
and Mr. Wayne Salentine were present to discuss water service to the 37-lot
Public Utilities Committee Meeting — February 16, 2004 Page 3
subdivision. Superintendent Kloskowski explained that subdivision of this size
the City requires a community well. The proposed subdivision is immediately
adjacent to Lakewood Meadows. Mr. Kloskowski recommended they tie into the
Lakewood Meadows system and that would save them from having to provide
storage. Depending on what New Berlin decides, municipal water may be a
possibility in the future. DNR would approve connection to the existing
Lakewood Meadows as a temporary connection until the City takes over the
system. Mr. Kloskowski noted that the City will not be treating the tannins that
are currently in the Lakewood Meadow water system. Mr. Salentine asked if the
City would consider fixing the tannin problem with the money the developer puts
up to the City. The Committee directed Mr. Salentine and Mr. Laschen to design
the water main because it would be needed regardless if they connected to
Lakewood Meadows our drilled their own well. The Committee should know
more about Lakewood Meadows system and also New Berlin's plans for
extending water main by the next meeting. Mr. Salentine will obtain an estimate
from Layne Northwest, and staff or Ruekert & Mielke will review the estimate.
SUBDIVIDER'S EXHIBITS -
Sewer and Water plans for Northfield Green Subdivision — Director McMullen
explained this piece of land is multifamily and commercial part of Carity
Subdivision off Janesville Rd. There is a large retention pond next to connection.
The maximum spacing between hydrants is 400 feet. There will be a hydrant
that is has a 616 foot spacing due to the retention pond. This spacing is within
the DNR requirements of 800 feet. The plans meet all City standards. Ald.
Petfalski moved to approve sewer and water plans for Northfield Green subject to
DNR and MMSD approval. Ald. Patterson seconded, motion carried 3-0.
ACCEPTANCE OF IMPROVEMENTS — Nothing to report.
REVIEW OF DEFERRED ASSESSMENTS/SEWER & WATER — Nothing to
report.
ACCEPTANCE OF IMPROVEMENTS — Discussion, update and possible action
may be taken on any or all of the following:
REPORT OF THE UTILITY SUPERINTENDENT — The Utility Department has
discontinued the sale of water to the directional boring companies. Use during
the cold weather is damaging the hydrants.
REPORT OF ENGINEERING/BUILDING INSPECTION DIRECTOR — Nothing to
report.
COMMUICATIONS AND ANY OTHER BUSINESS AS AUTHORIZED BY LAW
Aid. Petfalski moved to adjourn at 8:04 PM. Seconded by Aid. Patterson,
motion carried 2-0.
Public Utilities Committee Meeting — February 16, 2004 Page 4
Respectfully submitted,
,PC, V
u�—�
Kellie Renk,
Recording Secretary
CONSULTANTS REPORT FOR:
PUBLIC UTILITIES COMMITTEE
Monday February 16, 2004
Submitted Wednesday February 11, 2004
BOLD ITALICS INDICATE NEW INFORMATION
CITY PROJECTS:
JANESVILLE ROAD BOX CULVERT UTILITY RELOCATES
Design alternate selected August 28, 2002
County does not anticipate box culvert reconstruction prior to Fall 2003
Design to be sent to City for review by May 15, 2003
After City review, plans must be sent to County and State for approvals
Plans sent to County for review June 4, 2003
No comments have been received from County or City as of November 1, 2003
JANESVILLE ROAD WATER MAIN — JEWEL-OSCO TO COLLEGE AVENUE
City authorized design to College Avenue September 12, 2002
Plans for entire project to be submitted by January 17, 2003
Project revised to be from Kohl's to 1000 feet East of Tess Corners Drive
Potential contaminated soils discovered on site June 6, 2003, BLS Environmental
retained to assist City. Additional contaminated soils encountered week of July 7, 2003
Record drawings to be submitted to City for first review week of September 15
Contractor called on October 13, 2003 punch list completed
Site review confirmed all restoration completed
Final Payment and Close Out Change Order issued week of December 8, 2003
Mc Shane Pump Station — Bluhm Drive Storage Facility
Project close out paper work in process
Vibration damage to property claims remain unresolved
Moorland Road Water Main (will be removed from status report next month)
Sample by City tested safe
Punch list repairs completed
Parkland Drive Freedom Square water main connection
Construction completed
Safe samples and pressure tests all passed
Road pavement replaced
As Built survey completed, drawings in process
Punch list waiting for valve operation by Utility in spring
Public Utilities Committee Meeting — February 16, 2004 Page 5
Well Number 9 - Big Muskego Estates
Project bid opened November 7, 2003
Recommendation of award sent week of November 10, 2003
DNR approval received January 8, 2004
Preconstruction meeting scheduled for January 16, 2004
PAGE 2
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday February 16, 2004
Well Site Exploration
Contract for test borings to Layne Northwest
Test borings completed in Woods Road area
Geophysical surveys conducted at Big Muskego Estates site
Three test borings drilled in Big Muskego Estates area week of March 3, 2003,
Additional resistivity tests completed Quietwood East
Resistivity and seismic testing completed on two sites, processing data
Report with recommendations to be submitted week of January 19, 2004
DEVELOPMENTS:
Big Muskego Estates
First review letter sent to City March 6, 2003
Second review letter sent to City April 8, 2003
Preconstruction conference held October 2, 2003
Sanitary sewer installed,
Storm sewer west of Durham Drive is installed
Water main under construction east of Durham Drive
Utility construction completed week of February 1, 2004
Punch list repairs waiting for pavement installation.
Big Muskego Estates II
First construction plan review completed week of December 1, 2003
Second construction plan review completed January 13, 2004
Remaining items are storm water related
Utility plans recommended for approval
CANDLEWOOD (INTERIOR) (will be removed from status report next month)
Repairs completed, manhole now passed tests.
City authorized GIS updates on September 9, 2003
Chamberlain Hill
A portion of this project was determined to be in the boosted pressure area on
April 2, 2003
Contractor has not submitted shop drawings or condition report for existing booster
station.
Pavement and sump discharge lines installed
Field survey started for As Builts week of December 8, 2003
City televised sanitary sewer lines and found broken pipe
Public Utilities Committee Meeting — February 16, 2004 Page 6
Contractor working on punch list repairs
Water booster station not operational as of January 14, 2004
First start up test February 4, 2004 with USEMCO, City, and Contractor
Items to complete were identified
PAGE 3
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday February 16, 2004
LAKEWOOD CONDOMINIUMS (OVERLOOK BAY) (will be removed from status report
next month)
Punch list repairs completed
Record drawings for sanitary sewer submitted to MMSD November 14, 2002
Storm water system record drawings submitted to City, pending location of pond outfall
south of building number 4
Northfield Green
First construction plan review completed December 15, 2003
Revised construction plans received for review February 10, 2004
Utility plans recommended for approval February 11, 2004
Quietwood Creek East
First design review letter submitted on August 22, 2002
Second design review letter submitted on December 3, 2002
Final design review letter submitted January 09, 2003
Utility installation on hold pending final plat
Underground utility construction began July 7, 2003
Utility construction nearing completion September 9, 2003
Field survey for as builts drawings started week of December 1, 2003
Punch list repairs completed
Sanitary sewer lines televised by the City
Quietwood Creek South
Construction complete as of November 10, 2003
Waiting for contractor to finish inverts before punch list and as constructed survey
Roads paved week of November 17, 2003
Punch list repairs have been completed
Prairie Meadows Estates
Sanitary sewer installed, storm sewers installed
Road construction completed August 1, 2003
Sump discharge line installation completed August 21, 2003
Punch list repairs completed
City waiting for sanitary sewers to be cleaned before City televises lines
Two laterals repaired
System re -televised by City
Reserve at Champions Village (will be removed from status report next month)
Public Utilities Committee Meeting — February 16, 2004 Page 7
Sanitary and Storm sewer main and water mains installed
Resubmitted sanitary sewer and water main record drawings to City August 1
Storm sewer record drawings submitted to City August 1, 2002
Punch list repairs completed.
PAGE 4
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday February 16, 2004
Riverview Court (will be removed from status report next month)
Utility installation completed and tested as of October 7, 2002 except for vacuum test on
sanitary manhole number 8
Water main locator wire continuity test completed
Final record drawings submitted to City March 10, 2003
Manhole repaired and past test, late May 2003
Rosewood Estates Addition Number 1 (will be removed from status report next month)
Utility construction completed February 21, 2003
Road paved week of July 7, 2003
Sump lines installed
Completion letter sent August 6, 2003
SAL FERRITO SEWER (PRIVATE SANITARY SEWER)
DEWATERING WELL NOT REMOVED
LATERALS NOT CONNECTED YET
SARAH ESTATES (WOODS ROAD) (will be removed from status report next month)
Record drawings for Sanitary Sewer submitted to MMSD November 14, 2002
Storm Sewer record drawings on hold until adjustments before surface course paving
Punch lists are completed.
Stonebridge subdivision
Second plan review completed August 8, 2003
Third plan review completed October 9, 2003
Fourth plan review completed January 13, 2004
Remaining items related to storm water
Utility plans recommended for approval
13-00000.010
Ac�(J(L U}; li hes
Cbmmi qee
+e�vuc�2�p l �O, ��� U
kyCPle�s� n
1,4
APPROVED
CITY OF MUSKEGO
PUBLIC UTILITIES COMMITTEE MEETING
Minutes of Meeting Held Monday February 16, 2004
Chairman Eric Schroeder called the meeting to order at 7:05 p.m. Also present
were Committee members Aid Pat Patterson, Aid. Rick Petfalski, Utilities
Superintendent Scott Kloskowski, Engineer and Building Inspection Director
Sean McMullen and Ruekert & Mielke representative Steve Schultz.
It was noted that the meeting was posted in accordance with the Open Meeting
Law.
Those present recited the Pledge of Allegiance.
APPROVAL OF MINUTES OF PREVIOUS MEETING
Aid. Patterson moved to approve minutes of January 19, 2004. Seconded
by Aid. Petfalski, motion carried 3-0.
Aid. Patterson moved to approve minutes of January 27, 2004. Seconded
by Aid. Petfalski, motion carried 3-0.
STATUS OF PROJECTS
Steve Schultz updated the committee on the attached status of on -going projects
as follows:
• Big Muskego Estates — Utility construction completed week of
February 1, 2004. Punch list repairs waiting for pavement
installation.
• Well exploration project — Finished geophysics on all sites except
North Cape and Ryan. A different piece of equipment is needed.
Reports for all other sites being done. Borings can be started.
• Northfield Green - Revised construction plans received for review
February 10, 2004. Utility plans recommended for approval
February 11, 2004.
• Stonerige Ground Water Remediation —There was a meeting with
the consultant of Stoneridge. EPA should have the consultants
final work plan. Sampling on Well 7 should be started.
• Lakewood Meadows — Legal documents'are done. Two issues that
remain are the legal description does not match what is actually out
Public Utilities Committee Meeting — February 16, 2004 Page 2
there and trying to finalize who has to sign the agreement, the
water trust or 70% of the members.
• CCV/Stonebridge Watermain Extension — All exeptions have been
taken off the title. Three signatures are needed. Recapture
Agreement will go to Council on February 24, 2004.
• Proposed Development — Valley Sand and Gravel site — New Berlin
Plan Commission will be meeting in March. Ruekert & Mielke will
be doing a ground water remediation presentation.
SEWER UNFINISHED BUSINESS
Status of Town of Norway Contract - Director McMullen explained a contract is
no longer needed. Town of Norway agreed to 16% of planned capacity for
Muskego. Muskego and Town of Norway came to agreement what flow
allocations will be and lift station upgrade cost will be. Item will remain on the
agenda until the City receives the new Resolution.
Status of claims from West Lake, Lake Lore and Lake Brittany — Nothing new to
report.
Review Invoices for water treatment — West Lake Homeowner's Association -
Nothing new to report.
SEWER NEW BUSINESS — Nothing new.
WATER UNFINISHED BUSINESS
Establish policy for Champions Villaae (WCA) connection charae — Director
McMullen explained six of the remaining buildable lots are owned either by the
Developer or a subsidiary of Burke Properties. One of the remaining lots is
owned by Mr. Heidenreich, and possibly the lot is not buildable. Aid. Petfalski
moved to charge WCA charges 60 days after the date of signing the
agreement. Aid. Patterson seconded, motion carried 3-0.
WATER NEW BUSINESS
Review quotes for water tower inspection — Superintendent Kloskowski reviewed
a letter from Ruekert & Mielke explaining the four ways the tank was proposed to
be inspected. Aid. Petfalski moved to approve Dixon Engineering doing a
dry tank inspection at $4015.00. Seconded by Aid. Patterson, motion
carried 3-0.
Discuss possibilities for water service — Kenwood Place — Mr. Kenneth Laschen
and Mr. Wayne Salentine were present to discuss water service to the 37-lot