PUM20031020r
APPROVED
CITY OF MUSKEGO
PUBLIC UTILITIES COMMITTEE MEETING
Minutes of Meeting Held Monday October 20, 2003
Chairman Eric Schroeder called the meeting to order at 7:12 p.m. Also present
were Committee members Aid. Rick Petfalski, Aid Pat Patterson, Utilities
Superintendent Scott Kloskowski, Engineer and Building Inspection Director
Sean McMullen, Finance Director Dawn Gunderson, Ruekert & Mielke
representative Steve Schultz, and those per attached list.
It was noted that the meeting was posted in accordance with the Open Meeting
Law.
Those present recited the Pledge of Allegiance.
APPROVAL OF MINUTES OF PREVIOUS MEETING
Aid. Petfalski moved to approve minutes of September 15, 2003. Seconded
by Aid. Patterson, motion carried 2-0.
Review Proposed 2004 Sewer & Water Budgets with Finance Director — Finance
Director Gunderson review with the Committee the proposed 2004 sewer and
water budgets. Director Gunderson stated if the Committee approved the budget
it will go to Council on November 11th. Aid. Petfalski moved to approve the
proposed 2004 water budget. Aid. Patterson seconded. Motion carried 3-0.
Aid. Patterson moved to approve the proposed 2004 sewer budget.
Seconded by Aid. Petfalski. Motion carried 3-0.
STATUS OF PROJECTS
Ruekert-Mielke representative Steve Schultz updated the committee on the
attached status of on -going projects as follows:
• Janesville Road Water Main — Punch list completed. Meeting with
environmental specialists on contaminated soils along Tess
Corners.
• Parkland Drive — Construction started October 2, 2003. Main
installed as of October 13th. Changes from the DNR on the testing
and sampling on the main. The City will sample tomorrow.
Well Site Exploration — The well site investigation report is 95%
complete. Specifications were sent to City for review October 3rd
Public Utilities Committee Meeting — October 20, 2003 Page 2
Then sent to the DNR for approval and the bidding process starts.
Geophysics will start within the next few weeks on the other sites.
• Stoneridge Ground Water Remediation — Contacted the Water
Supply Section at the EPA and they will check into the status with
the Landfill contact at EPA and if it is not moving ahead the Water
Supply Section can take it over.
• Lakewood Meadows / Acquisition of Water System - Study has
been submitted. Waiting to hear back from residents.
• Champions Village Water System — Study will be submitted at next
meeting.
• Chamberlain Hill — Curb and gutter installed the week of October 6,
2003. Pavement and sump discharge lines remain to be installed.
• Prairie Meadows — Punch list completed.
SEWER UNFINISHED BUSINESS
Status of Town of Norway Contract - Nothing new to report.
Status of claims from West Lake, Lake Lore and Lake Brittany — Mr. Schultz
contacted Jim Krohelski of the USGS. The study has not been started and the
USGS is still waiting to receive the report from the Homeowners Association.
Mr. Schultz reported the lake levels are still dropping.
Review Invoices for water treatment — West Lake Homeowner's Association -
Deferred until after the City receives the report from the USGS.
SEWER NEW BUSINESS —
Review RCA charges — Hair Maqic — Mr. Peter Jungbluth was present to request
the Committee review the RCA charges for the hair salon. Mr. Jungbluth
explained at the previous location the usage would equal about 1.42 REC's
which includes a duplex. The duplex no longer exists and the hair salon is being
charged 3.25 REC's. Aid. Patterson moved to approve lowering the REC's
to 1.5. Aid. Schroeder seconded. Aid. Schroeder explained he was basing
the 1.5 REC's off of the residential equivalent chart. Aid. Petfalski suggested
lowering to 1.25 REC's based on actual usage and taking into consideration the
duplex no longer exists. Upon voice vote motion was denied 1-2 with Aid.
Petfalski and Aid. Schroeder voting no. Aid. Petfalski moved to approve
lowering to 1.25 REC's. Aid. Schroeder seconded. Motion carried 2-1 with
Aid. Patterson voting no.
Public Utilities Committee Meeting — October 20, 2003 Page 3
Review quarterly payment to MMSD and Town of Norway — The Committee
reviewed charges. Aid. Petfalski moved to approve charges from MMSD and
Town of Norway. Seconded by Aid. Patterson. Motion carried 3-0.
Review amendment to RCA District Boundary-- Director McMullen stated the
Committee discussed in the past to amend the RCA District to mimic the 208
District, which include the Blattner and May properties. Aid. Patterson moved
to approve amendment to the RCA District to include the Blattner and May
properties. Aid. Schroeder seconded. Motion carried 2-0-1. Aid. Petfalski
abstaining.
WATER UNFINISHED BUSINESS
Further discussion possible acquisition of Champions Village community water
system — Director McMullen explained because of the existing golf course the
City would potentially need to create a wellhead protection district due to the
chemicals used. Aid. Patterson moved to direct Ruekert & Mielke to begin a
wellhead protection district for the two potential community well
acquisitions of Champions Village. Aid. Petfalski seconded. Motion
carried 3-0.
WATER NEW BUSINESS
Discuss DNR consent order for radium compliance - Wells 4 & 5 -
Superintendent Kloskowski stated there is no update at this time. There may be
a need to hold a special meeting. Aid. Patterson moved to defer. Seconded by
Aid. Petfalski. Motion carried 3-0.
Review comments from Informational Session on 13th Amended WCA District
and 10.10 Agreement and Recapture Roll- Some comments that were heard
was a strong opposition to an increase on monthly charges and the developers of
Champions Village lack of notification to the residents. Residents along the
watermain route were not opposed to it. Aid. Petfalski moved to recommend
approval to Council of the 13'h Amended WCA District. Aid. Patterson
seconded. Motion carried 3-0.
Aid. Petfalski moved to approve the X21B Agreement. Seconded by Aid.
Patterson. Motion carried 3-0.
Review proposed amendment to the 14th Amended WCA District (MSKC
2171.997.002 & .003 (Brauch Property— Oak Hill Trail) — Director McMullen
explained as part of the Chamberlain Hill subdivision Mr. Paul Brauch requested
the contractor for Chamberlain Hills install two watermain laterals to his property
without prior approval from the City. The two laterals are outside the WCA
District. Mr. Brauch has signed a waiver of special assessment notice and
hearing. The WCA District needs to be amended to include this service. Aid.
Public Utilities Committee Meeting — October 20, 2003 Page 4
Petfaiski moved to approve the 14th Amendment to WCA District. Aid.
Patterson seconded. Motion carried 3-0.
SUBDIVIDER'S EXHIBITS - None.
ACCEPTANCE OF IMPROVEMENTS — Nothing to report.
REVIEW OF DEFERRED ASSESSMENTS/SEWER & WATER — Director
McMullen stated the Committee will review the interest rates for future deferred
assessments on a case by case basis.
ACCEPTANCE OF IMPROVEMENTS — Discussion, update and possible action
may be taken on any or all of the following:
REPORT OF THE UTILITY SUPERINTENDENT — Nothing to report.
REPORT OF ENGINEERING/BUILDING INSPECTION DIRECTOR — Nothing to
report.
COMMUICATIONS AND ANY OTHER BUSINESS AS AUTHORIZED BY LAW
— None.
Aid. Petfalski moved to adjourn at 8:41 PM. Seconded by Aid. Patterson,
motion carried 3-0.
Respectfully submitted,
Kellie Renk, Recording Secretary
Public Utilities Committee Meeting — October 20, 2003 Page 5
CONSULTANTS REPORT FOR:
PUBLIC UTILITIES COMMITTEE
Monday October 20, 2003
Submitted Wednesday October 15, 2003
BOLD ITALICS INDICATE NEW INFORMATION
CITY PROJECTS:
JANESVILLE ROAD BOX CULVERT UTILITY RELOCATES
Design alternate selected August 28, 2002
County does not anticipate box culvert reconstruction prior to Fall 2003
Design to be sent to City for review by May 15, 2003
After City review, plans must be sent to County and State for approvals
Plans sent to County for review June 4, 2003
JANESVILLE ROAD WATER MAIN — JEWEL-OSCO TO COLLEGE AVENUE
City authorized design to College Avenue September 12, 2002
Plans for entire project to be submitted by January 17, 2003
Project revised to be from Kohl's to 1000 feet East of Tess Corners Drive
Potential contaminated soils discovered on site June 6, 2003, BLS Environmental
retained to assist City. Additional contaminated soils encountered week of July 7, 2003
Record drawings to be submitted to City for first review week of September 15
Paving completed September 8, 2003
Restoration has not taken due to dry weather
Contractor called on October 13, 2003punch list completed
Site review scheduled for week of October 13, 2003
Mc Shane Pump Station — Bluhm Drive Storage Facility
Site grading and punch list items in process
Storm sewer and road installation completed
Post construction well level monitoring completed
Restoration by seeding completed Need substantial grass growth
Project close out paper work in process
Request for USGS review of declining groundwater levels sent August 15
Moorland Road Water Main
Sample by City tested safe
Punch list repairs completed
Parkland Drive Freedom Square water main connection
Construction started October 2, 2003
Main installed as of October 13, 2003 no connections are made
DNR required initial safe sample taken October 13, 2003 from 8 inch only
Pressure tests and final safe sample tests tentatively scheduled for later the week
of October 13 or early the week of October 20, 2003
Well Site Exploration
Contract for test borings to Layne Northwest
Test borings completed in Woods Road area
Public Utilities Committee Meeting — October 20, 2003 Page 6
PAGE 2
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday October 20, 2003
Well Site Exploration (continued)
Geophysical surveys conducted at Big Muskego Estates site
Three test borings drilled in Big Muskego Estates area week of March 3, 2003,
Additional resistivity tests completed Quietwood East
Geophysical surveys will be conducted on additional sites after harvest
Well site investigation report and specifications being prepared for DNR submittal and
bidding in Fall
Well site investigation report 95% complete
Specifications were sent to City for review October 3, 2003
DEVELOPMENTS:
Big Muskego Estates
First review letter sent to City March 6, 2003
Second review letter sent to City April 8, 2003
Preconstruction conference held October 2, 2003
CANDLEWOOD (INTERIOR)
Repairs completed, manhole now passed tests.
City authorized GIS updates on September 9, 2003
Chamberlain Hill
Design engineer picked up print of sanitary system map August 6 for design use
Initial plan review completed January 28, 2003
A portion of this project was determined to be in the boosted pressure area on April 2,
2003
Site grading has begun
Underground utility construction to begin the week July 15, 2003
DNR approval received August 1, 2003
Underground utilities 75% complete
Contractor has not excavated nor evaluated existing booster station, has not submitted
shop drawings or condition report
Curb and gutter installe week of October 6, 2003
Pavement and sump discharge lines remain to be installed
LAKEWOOD CONDOMINIUMS (OVERLOOK BAY)
Punch list repairs completed
Record drawings for sanitary sewer submitted to MMSD November 14, 2002
Storm water system record drawings submitted to City, pending location of pond outfall
south of building number 4
PAGE 3
Public Utilities Committee Meeting — October 20, 2003 Page 7
�-- Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday October 20, 2003
Quietwood Creek East
First design review letter submitted on August 22, 2002
Second design review letter submitted on December 3, 2002
Final design review letter submitted January 09, 2003
Utility installation on hold pending final plat
Underground utility construction began July 7, 2003
Utility construction nearing completion September 9, 2003
Prairie Meadows Estates
Construction continues.
Sanitary sewer installed, storm sewers installed, road installation required prior to sump
discharge line installation and final adjustments to the sewers
Road construction completed August 1, 2003
Sump discharge line installation completed August 21, 2003
Punch list repairs completed
City waiting for sanitary sewers to be cleaned before City televises lines
Reserve at Champions Village
Sanitary and Storm sewer main and water mains installed
Resubmitted sanitary sewer and water main record drawings to City August 1
Storm sewer record drawings submitted to City August 1, 2002
Punch list repairs completed.
Riverview Court
Utility installation completed and tested as of October 7, 2002 except for vacuum test on
sanitary manhole number 8
Water main locator wire continuity test completed
Final record drawings submitted to City March 10, 2003
Manhole repaired and past test, late May 2003
Rosewood Estates Addition Number 1
Utility construction completed February 21, 2003
Road paved week of July 7, 2003
Sump lines installed
Completion letter sent August 6, 2003
SAL FERRITO SEWER (PRIVATE SANITARY SEWER)
DEWATERING WELL NOT REMOVED
LATERALS NOT CONNECTED YET
SARAH ESTATES (WOODS ROAD
Record drawings for Sanitary Sewer submitted to MMSD November 14, 2002
Storm Sewer record drawings on hold until adjustments before surface course paving
Punch lists are completed.
PAGE 4
Consultant's report for
Public Utilities Committee Meeting — October 20, 2003 Page 8
PUBLIC UTILITIES COMMITTEE
Monday October 20, 2003
Stonebridge subdivision
Second plan review completed August 8, 2003
Third plan review completed October 9, 2003
13-00000.010
SIGN IN SHEET
Champion's Village Off -Site Water Main Extension
INFORMATIONAL MEETING
MONDAY, OCTOBER 20, 2003
NAME (PLEASE PRINT)
ADDRESS
S�hf� /
i&3JUevy 6D- 1.., r3tcr6
00-`( SCM OLTs G--s.1 Z 5 S. g&Os k/. ar"' Ago >
41 SPAR-AcWo 59Sw13023 rJ v tier NR5e.n D,r � S315'v
TI/P M I- A/ M a nN W, ;t S_ I C 7 a IV • C A PF R v
OU
Spa u #1 owl flu.. Iq 6-3.2
es
S�7z
5,ctS w.12�CI Ukkf k
We FgS`n-)S K rr