PUM20030421CITY OF MUSKEGO
PUBLIC UTILITIES COMMITTEE MEETING Approved
Minutes of Meeting Held Monday April 21, 2003
Acting -Chairman Rick Petfalski called the meeting to order at 7:04 p.m. Also
present was Committee members Aid. Eric Schroeder, Engineer and Building
Inspection Director Sean McMullen, Ruekert & Mielke representative Steve
Schultz and those per attached list. Chairman Eileen Madden and
Superintendent Scott Kloskowski were excused.
It was noted that the meeting was posted in accordance with the Open Meeting
Law.
Those present recited the Pledge of Allegiance.
APPROVAL OF MINUTES OF PREVIOUS MEETING
Aid. Schroeder moved to approve minutes of March 18 and 25, and April 8,
2003. Seconded by Aid. Petfalski, motion carried 3-0.
STATUS OF PROJECTS
Ruekert & Mielke representative Steve Schultz updated the committee on the
attached status of on -going projects as follows:
• Janesville Road Water Project— Construction began April 15, 2003.
Freedom Square Water System — Plans sent to the DNR April 21,
2003. Water Main plans will be submitted by the end of the week.
Pending the City's review will then be forwarded to the DNR for
review also. Ruekert & Mielke will be working with the City
Attorney to discuss his concerns.
Well Explorations Project — Review of the six possible sites
continues. Field recognizance on potential sites will take place
within the next couple weeks and test borings will be done on the
Carity site.
• McShane Storage Facility —Owner training started last week.
Contractor had to replace bad valves on the flushing gates used to
clean out the tank after the event. Impellors were taken out and
trimmed.
Public Utilities Committee Meeting — April 21, 2003 Page 2
• SEWER UNFINISHED BUSINESS
Status of Town of Norway Contract - Nothing new to report.
Review Accruing Deferred Assessment Interest report from Finance Director —
Deferred to next meeting.
SEWER NEW BUSINESS
Ordinance to Amend Chapter 3 and Chapter 21 Sewer Service Areas (Sewer
Utility) to update service area to include all areas include in the Amended Linnie
Lac Agreement — The old sewer agreement with New Berlin was under Chapter
3. The last agreement, Chapter 21, allowed connection with bordering lots where
capacity was available known as the Linnie Lac Agreement. Aid. Petfalski
moved to recommend to Council approval of amending Chapter 3 and
Chapter 21 Sewer Service Areas. Aid. Schroeder seconded. Motion carried
unanimously.
Discuss deferred assessment — May property - Director McMullen explained that
Towne Realty just purchased the property and were under the assumption that
the assessment did not come due until the property was divided and lots were
sold. Because the tax key had to be split up, the assessment will come due at
. the time the tax key is recorded. Director McMullen referred to the assessment
policy 6 A (1) which states as an alternative, the City, at its sole option may
negotiate with a property owner having an assessment come due. Aid.
Schroeder moved to defer to the next meeting. Aid. Petfalski seconded.
Motion carried unanimously.
Review 1st Qtr MMSD & Town of Norway Charges - After reviewing charges,
Aid. Petfalski moved to approve 1st quarter MMSD and Town of Norway
sewer charges. Aid. Schroeder seconded. Motion carried unanimously.
Review quotes for renovation of Lake Lore Liftstation — Director McMullen
reported the pumps at the Lake Lore Liftstation are 18-22 years old and are due
to be replaced. Aid. Petfalski moved to approve the quote of $31,132.00
from Smith & Loveless for the replacement of pumps for the Lake Lore
Liftstation . Aid. Schroeder seconded. Motion carried unanimously.
WATER UNFINISHED BUSINESS
WATER NEW BUSINESS None.
Discuss_ proposed water main extension / Freedom Square — Director McMullen
explained the City Attorney sent out a letter of concerns that he would like met
. before the final closing date. Director McMullen is requesting the Committee
approve the acquisition and extension and recommend to Council. The water
Public Utilities Committee Meeting — April 21, 2003 Page 3
• main extension is being reviewed by City of Muskego Engineering Department
and designed by Ruekert & Mielke. The plans must go to the DNR for approval
and once approved the project can be bid out and the results brought back to the
Committee. In the meantime staff can be working on the final closing and
converting the residents over to City water. Aid. Petfalski moved to
recommend to Council approval of the acquisition and extension of water
main for Freedom Square. Aid. Schroeder seconded. Motion carried
unanimously.
Sal Corrao — Lakewood Meadows Subdivision — City to take over communitv well
system — Lori Eilers, Michael Ligocki and Sal Carro of Lakewood Meadows
Subdivision were present to discuss the possibility of the City taking over the
community well. Lori Eilers presented to the Committee the attached partial list
of the subdivision's well maintenance and repair records. The well had also been
televised and information was given to Superintendent Kloskowski. After
discussing the issue it was staffs recommendation that it would be in the City's
best interest to take over the system providing there are no major problems. Aid.
Peffalski stated he is concerned with having an island utility and also the water
may not have the same quality as City water. Aid. Schroeder moved to
proceed with the system exploration by Ruekert & Mielke, not to exceed
$10,000.00. Aid. Petfalski seconded. Motion carried unanimously.
. Discuss writing of specific policies relating to water assessments — This item was
brought about from the Big Muskego Estates WCA Public Hearing. Residents
were concerned the City would be charging them a recapture if a developer
comes in and decides to run the 12" water main down McShane Dr. Director
McMullen explained to the Committee that it would not be possible to write a
policy relating to water assessments. He further explained that the PSC rules
change so it would not be possible to write a specific policy because the City
takes each on a case -by -case basis. The existing policy allows the City to make
exceptions and recommendations on assessments prior to the assessment roll
being sent out.
Discuss Chamberlain Hill Water Booster Pump Station — Chamberlain Hills
Subdivision has five lots where the base elevation of the property is higher than
860 feet. These five properties will need to be in a separate boosted zone. A
booster station will need to be installed to provide pressurized water similar to
Lake Forest. A booster station was purchased and installed by the City for Lake
Forest Subdivision. Since then the booster station has been abandoned and
obsolete for its intended use in its current location. Chamberlain Hills
Subdivision needs a booster station and staff is recommending the City allow
Cedar Mill Homes to remove the station, do all restoration and install it in an
easement granted to the City Water Utility in Chamberlain Hills. Cedar Mill
Homes will also be responsible for any corrections and repairs, and under the
• direction of Ruekert & Mielke to put the pump station on line. Once the station is
on line Cedar Mill Homes would then turn it back over the City Utility Department.
Public Utilities Committee Meeting — April 21, 2003 Page 4
In the future if the Borchardt or Sonnentag property develops they would also
make use of the booster station. There would be no additional cost to the
Borchardt's, Sonnentag's or the City because the water capacity assessment has
already been paid. Cedar Mill Homes drafted an agreement that will be sent to
the City Attorney for review. The agreement will include Cedar Mill Homes will
hold the City harmless as they remove and install the station. Aid. Schroeder
moved to allow Cedar Mill Homes to remove the booster station, do all
restoration and install it in an easement granted to the City Water Utility in
Chamberlain Hills, after review of the City Attorney. Seconded by Aid.
Schroeder. Motion carried unanimously.
SUBDIVIDER'S EXHIBITS - Big Muskego Estates Sewer and Water Extension -
Director McMullen stated the plans are for sewer and water only for the sanitary
sewer extension to Big Muskego Estates Phase 1. Plans include the 16" water
main through the development to tie into Big Muskego Estates Addition 1, which
could then service North Cape Farms. Director McMullen noted there has been
concern of the wells drying up along Schaeffer Drive. Because of this, the City is
requiring the developer to run 16" municipal main underneath Hwy "00" to south
side of Hwy "00". Plans will be sent to MMSD and DNR for approval and will be
brought back next month. Deferred to next month.
ACCEPTANCE OF IMPROVEMENTS — Nothing to report.
0 REVIEW OF DEFERRED ASSESSMENTS/SEWER & WATER — None.
ACCEPTANCE OF IMPROVEMENTS — Discussion, update and possible action
may be taken on any or all of the following:
REPORT OF THE UTILITY SUPERINTENDENT — Nothing to report.
REPORT OF ENGINEERING/BUILDING INSPECTION DIRECTOR — Nothing to
report.
COMMUICATIONS AND ANY OTHER BUSINESS AS AUTHORIZED BY LAW
— None.
Aid. Schroeder moved to adjourn at 8:30 PM. Seconded by Aid. Petfalski,
motion carried 3-0.
Res ectfully submitted,
7
Kellie Renk
Recording Secretary
0
Public Utilities Committee Meeting — April 21, 2003
Page 5
0
CONSULTANTS REPORT FOR:
PUBLIC UTILITIES COMMITTEE
Monday April 21, 2003
Submitted Tuesday April 15, 2003
BOLD ITALICS INDICATE NEW INFORMATION
CITY PROJECTS:
FREEDOM SQUARE WATER SYSTEM
Easements submitted to City for review and action week of May 13"'
First floor elevation of pump house has to be more than 2 feet above regional flood.
Working on proposal to modify Freedom Square pond outlet to lower this elevation.
DNR will allow facilities to be acquired by easement (August 1, 2002)
Utility Superintendent forwarded easements to Condo Association to obtain from
Parkland Development Group
Connection approved by DNR October 30, 2002
Revised easements submitted to City April 10, 2003 for connections to Parkland
Drive
Parkland Drive water main plan submitted to City and DNR concurrently for
review week of April 14, 2003
JANESVILLE ROAD BOX CULVERT UTILITY RELOCATES
Cost estimates to be submitted to City week of February 18
Estimates and design alternatives submitted to City for review February 21, 2002
Design alternate selected August 28, 2002
Design to be sent to City for review by April 1, 2003
County does not anticipate box culvert reconstruction prior to Fall 2003
Project revised to be from Kohl's to 1000 feet East of Tess Corners Drive
Construction began April15, 2003
JANESVILLE ROAD WATER MAIN — JEWEL-OSCO TO COLLEGE AVENUE
City authorized design to College Avenue September 12, 2002
Additional survey completed
Plans for entire project to be submitted by January 17, 2003
First advertisement January 30, 2003
Bid opening February 13, 2003
WCA public hearing 8s' Amended area scheduled for March 25, 2003
MANHOLE REHABILITATION 2001
Project closeout paperwork and Final Payment Recommendation forwarded to the City
April 1, 2002
Martin Drive Relocation — Utility extensions
On hold pending WDNR Alternatives Analysis to Wetland impacts
DNR approvals received late November 2002
• To be bid as part of the road relocation project.
Pending DNR permit for road, City to set bid date
Public Utilities Committee Meeting — April 21, 2003
Page 6
• PAGE 2
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday April 21, 2003
Mc Shane Pump Station — Bluhm Drive Storage Facility
Start up tentatively scheduled week of April 14, 2003
Gravity system leak repaired week of March 3, 2003
Training scheduled for April 16, 2003
Moorland Road Water Main
Sample by City tested safe
Punch list repairs in process
Well Site Exploration
Contract for exploratory wells to Layne Northwest
Test borings completed in Woods Road area
Geophysical surveys conducted at Big Muskego Estates site
Preparing map showing recommended boring location and letter report on geophysical
survey results and recommendations
Three exploratory wells drilled in Big Muskego Estates area week of March 3, 2003, data
to be reviewed and report filed by April 1, 2003
40 WOODS ROAD — BROOKE LANE TO EAST OF RACINE AVENUE
Project close out paper work sent to City July 25, 2002
DEVELOPMENTS:
Big Muskego Estates
First review letter sent to City March 6, 2003
Second review letter sent to City April 8, 2003
CANDLEWOOD (INTERIOR)
Sanitary completed but not fully tested, water installed and tested
Storm sewer should be completed week of September 11
Sample test reports safe, wet connections completed
Punch list review after sump drains installed week of November 25, 2002
Punch list issued December 10, 2002 to Contractor for sanitary and water
Punch list for Storm sewer is pending cleaning of inlets by Contractor
Water and force main locator wire continuity tests completed
Manhole 6leaks repaired, still failed tests.
Chamberlain Hill
Design engineer picked up print of sanitary system map August 6 for design use
Initial plan review completed January 28, 2003
A portion of this project was determined to be in the boosted pressure area on
April2, 2003
Public Utilities Committee Meeting — April 21, 2003
Page 7
• PAGE
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday April 21, 2003
A%
JEWEL — OSCO / KOHLS ONSITE UTILITIES AND LIFT STATION
Onsite construction completed and tested except for lift station
Punch list reviews to began the week of September 12, 2002
All punch list items completed as of October 11, 2002
Water main locator wire continuity test not completed
Record drawings submitted week of December 11, 2002
Force main locator wire continuity test completed
JEWEL — OSCO / KOHLS Offsite water main
Record drawings submitted August 1, 2002 for City Staff review
Recheck of punch list items week of November 18, 2002
All punch list items completed as of December 20, 2002
Project can be closed if acceptable to City.
LAKEWOOD CONDOMINIUMS (OVERLOOK BAY)
Punch list repairs completed
Record drawings for sanitary sewer submitted to MMSD November 14, 2002
Storm water system record drawings submitted to City, pending location of pond outfall
south of building number 4
MUSKEGO CENTER/BERG
AS BUILTS COMPLETED
PUNCH LIST SENT TO CONTRACTOR
MUSKEGO MOTOR CAR CO
PUNCH LIST RESENT TO CONTRACTOR
MMSD REVIEWED AS BUILTS FEBRUARY 2, 2000
CONTRACTOR TOLD R/M THEY WILL NOT COMPLETE DUE TO PAYMENTS
NOT RECEIVED
Nature Estates (Boehm — Woods Road)
Second plan review completed November 20, 2001
Revised plans received r/m January 16 for review
QUIETWOOD CREEK (CARITY)
Sanitary Sewer Record Drawings submitted to MMSD November 14, 2002
Storm Sewer record drawings resubmitted to City August 1, 2002
Quietwood Creek East
First design review letter submitted on August 22, 2002
Second design review letter submitted on December 3, 2002
Final design review letter submitted January 09, 2003
PAGE 4
Public Utilities Committee Meeting — April 21, 2003
�0M
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday April 21, 2003
Prairie Meadows Estates
Construction started March 31, 2003, delayed due to rain.
RAUSCH SANITARY PRESSURE SEWER — WOODS ROAD
COMPLETED WEEK OF FEBRUARY 19T11
Restoration is only remaining item.
Record drawings submitted to MMSD and City April 6, 2001
Reserve at Champions Village
Sanitary and Storm sewer main and water mains installed
Resubmitted sanitary sewer and water main record drawings to City August 1
Storm sewer record drawings submitted to City August 1, 2002
Punch list repairs completed.
Riverview Court
Utility installation completed and tested as of October 7, 2002 except for vacuum test on
sanitary manhole number 8
Second punch list sent to contractor on November 19, 2002
Field survey for record drawings completed December 3, 2002
Water main locator wire continuity test completed
Sanitary manhole 8 still has not passed vacuum test
Final record drawings submitted to City March 10, 2003
Rosewood Estates Addition Number 1
Utility construction completed February2l, 2003
Road construction to begin in Spring, 2003
Saint Leonard's water main (East Tower Drive)
All punch list items completed
Record drawing sent to City for first review September 27, 2002
SAL FERRITO SEWER (PRIVATE SANITARY SEWER)
DEWATERING WELL NOT REMOVED
LATERALS NOT CONNECTED YET
SARAH ESTATES (WOODS ROAD
Record drawings for Sanitary Sewer submitted to MMSD November 14, 2002
Storm Sewer record drawings on hold until adjustments before surface course paving
Punch lists are completed.
VICTORIAN VILLAS
VIDEO OF SEWER NOT YET RECEIVED
City has hired Visu-Sewer
13-00000.010