PUM20021216CITY OF MUSKEGO Unapproved
PUBLIC UTILITIES COMMITTEE MEETING
Minutes of Meeting Held Monday, December 16, 2002
Chairman Eileen Madden called the meeting to order at 6:50 p.m. Also present
were Committee members Aid. Rick Petfalski and Aid. Eric Schroeder, Utilities
Superintendent Scott Kloskowski, Engineer Dave Simpson, and Ruekert &
Mielke representative Steve Schultz.
It was noted that the meeting was posted in accordance with the Open Meeting
Law.
Those in attendance recited the Pledge of Allegiance.
APPROVAL OF MINUTES OF PREVIOUS MEETING
Aid. PefFalski moved to accept minutes of meeting held November 18, 2002.
Seconded by Aid. Schroeder, motion carried 3-0.
STATUS OF PROJECTS
Steve Schultz reviewed the status of projects as listed on Consultant's Report
dated December 16, 2002, as attached.
Steve Schultz also reported that the western portion of the Janesville Road
watermain project design is nearly finished with the eastern portion continuing.
Lack of road plans from Waukesha County is delaying design completion of the
plans.
Freedom Square water acquisition is moving ahead. The City is awaiting an
answer from the PSC regarding taking over ownership of the system without
having ownership of all the easements.
Well explorations are continuing with one possible well site identified in the
Quietwood Creek East subdivision and more testing being done on the Big
Muskego Estates site.
The McShane Storage Facility has waterproofing on 65% of the walls and
backfilling has begun. The building walls are complete.
Utilities Superintendent Kloskowski reported that an informational meeting has
been scheduled for the Pioneer Drive water project for January 7, 2003 at 7:00
p.m. at the Library.
Public Utilities Committee Meeting
December 16, 2002 — Page 2
SEWER UNFINISHED BUSINESS
Status of Town of Norway Contract — The Committee reviewed letter from the
PSC indicating that the PSC will not hold a hearing on the City's complaint
against the Town of Norway.
SEWER NEW BUSINESS
Review Sewer Backup Manual — The Committee reviewed packet from the
City's insurance company on sewer backups and policies. Aid. Schroeder
moved to defer Seconded by Aid. Petfalski, motion carried 3-0.
Review Sewer, Water, and Forcemain Plans for Settlement on Woods Road
— Dave Simpson submitted sewer and water plans for the Settlement on Woods
Road subdivision and reported all consultant issues have been addressed. Ald.
Petfalski moved to accept sewer and water plans and to submit to MMSD and
the DNR. Seconded by Aid. Schroeder, motion carried 3-0.
WATER UNFINISHED BUSINESS
Status of Request to PSC for Water Rate Change — Utilities Superintendent
Kloskowski reported that the auditors are compiling the necessary information for
submittal to the PSC.
WATER NEW BUSINESS
Review of Draft CDA Redevelopment District Plan — The Committee reviewed
the CDA Redevelopment District Plan.
Janesville Road Water Project/Possible Durham Drive & Tess Corners Drive
Extension — Utilities Superintendent Kloskowski explained that he would like to
extend water service south from Janesville Road to Cornell Circle on Durham
Drive and south to the Tess Corners Fire Department on Tess Corners Drive as
part of the Janesville Road water project. Aid. Petfalski moved to direct Ruekert
& Mielke to include watermain on Durham Drive south to Cornell Circle and on
Tess Corners Drive far enough south to serve the Tess Corners Fire Department
in the design of Janesville Road watermain. Seconded by Ald. Schroeder,
motion carried 3-0.
Review Agreement with Freedom Square Condominium — The Committee
reviewed draft agreement. Utilities Superintendent Kloskowski stated that some
details need to be completed before approval can be voted on.
Public Utilities Committee Meeting
December 16, 2002 — Page 3
Discuss Boundaries of WCA 10 District and Direct City Engineer to Draft
Map and Legals — Utilities Superintendent Kloskowski explained the WCA map
and proposed amendment provided by the Planning Department. Aid. PetFalski
moved to approve WCA amendment to include Draft'A' and 'B' and to include all
properties with frontage on McShane Road and on Courtland Lane, and to direct
the Engineering Department to draft a map and legal description. Seconded by
Aid. Schroeder. motion carried 3-0.
Review Water Extension Agreement with Towne Realty - The Committee
reviewed agreement with Towne Realty regarding watermain extension. The
Engineering Department will continue to finalize plans.
REPORT OF UTILITY SUPERINTENDENT
Utilities Superintendent Kloskowski discussed radium issue with the Committee
in an effort to update new Committee member Aid. Schroeder The City is
required to report to the DNR by the end of January, 2003 the remedies that will
be implemented in order to come into compliance with the DNR radium standard.
ADJOURNMENT
Aid. Petfalski moved to adjourn at 7:52 p.m. Seconded by Aid. Schroeder,
motion carried 3-0.
Respectfully submitted,
)Wtt
Scott Kloskowski
Public Utilities Superintendent
jz
CONSULTANTS REPORT FOR:
PUBLIC UTILITIES COMMITTEE
Monday December 16, 2002
Submitted Tuesday December 10, 2002
BOLD ITALICS INDICATE NEW INFORMATION
CITY PROJECTS:
FREEDOM SQUARE WATER SYSTEM
Design plans cannot be located by City or Freedom Square
Easements submitted to City for review and action week of May 13"
First floor elevation of pump house has to be more than 2 feet above regional flood
elevation. Working on proposal to modify Freedom Square pond outlet to lower this
elevation.
DNR will allow facilities to be acquired by easement (August 1)
Utility Superintendent forwarded easements to Condo Association to obtain from
Parkland Development Group
Connection approved by DNR October 30, 2002
JANESVILLE ROAD BOX CULVERT UTILITY RELOCATES
Cost estimates to be submitted to City week of February 18
Estimates and design alternatives submitted to City for review February 21, 2002
Design alternate selected August 28, 2002
JANESVILLE ROAD WATER MAIN —JEWEL-OSCO TO COLLEGE AVENUE
Preliminary field survey completed, Preliminary plans in progress
Preliminary design to 1000 feet east of Tess Comers Drive complete
City authorized design to College Avenue September 12, 2002
Additional survey completed, preliminary plans in drafting
West segment 95% complete
East segment to be submitted week of December 15, 2002
MANHOLE REHABILITATION 2001
Project closeout paperwork and Final Payment Recommendation forwarded to the City
April 1, 2002
Martin Drive Relocation — Utility extensions
On hold pending WDNR Alternatives Analysis to Wetland impacts
DNR approvals received late November 2002
Mc Shane Pump Station — Bluhm Drive Storage Facility
Shop drawing submittals from contractor continue
De -watering started June 28 h
Contractor graded and paved base course north of Bluhm Court October 9
Precast planks installed week of November 18, 2002
Visible seepage leaks repaired, leak test completion Week of December 9, 2002
Discharge chamber walls poured, deck is being formed for casting
PAGE 2
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday December 16, 2002
Moorland Road Water Main
Sample by City tested safe
Punch list repairs in process
Well Site Exploration
Contract for exploratory wells to Layne Northwest to be executed soon
Four test borings completed
Working with City on planned development issues.
WOODS ROAD — BROOKE LANE TO EAST OF RACINE AVENUE
Project close out paper work sent to City July 25, 2002
DEVELOPMENTS:
CANDLEWOOD (INTERIOR)
Construction started July 26
Sanitary completed but not fully tested, water installed and tested
Storm sewer should be completed week of September I 1
Sample test reports safe, wet connections completed
Punch list review after sump drains installed week of November 25, 2002
Punch list issued December 10, 2002 to Contractor for sanitary and water
Punch list for Storm sewer is pending cleaning of inlets by Contractor
Water and force main locator wire continuity tests completed
Chamberlain Hill
Design engineer picked up print of sanitary system map August 6 for design use
JEWEL — OSCO / KOHLS ONSITE UTILITIES AND LIFT STATION
Field change for the Lift Station relocation design changes completed and submitted to
City and Developer
Onsite construction completed and tested except for lift station
Punch list reviews to begin the week of September 12, 2002
Record Survey scheduled
All punch list items completed as of October 11, 2002
Water main locator wire continuity test not completed
Record drawings to be submitted week of December 11, 2002
Force main locator wire continuity test completed
JEWEL — OSCO / KOHLS Offsite water main
Record drawings submitted August 1, 2002 for City Staff review
Recheck of punch list items week of November 18, 2002
PAGE
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday December 16, 2002
LAKEWOOD CONDOMINIUMS (OVERLOOK BAY)
Punch list repairs completed
Record drawings for sanitary sewer submitted to MMSD November 14, 2002
Storm water system record drawings submitted to City, pending location of pond outfall
south of building number 4
MUSKEGO CENTER/BERG
AS BUILTS COMPLETED
PUNCH LIST SENT TO CONTRACTOR
MUSKEGO MOTOR CAR CO
PUNCH LIST RESENT TO CONTRACTOR
MMSD REVIEWED AS BUILTS FEBRUARY 2, 2000
CONTRACTOR TOLD R/M THEY WILL NOT COMPLETE DUE TO PAYMENTS
NOT RECEIVED
Nature Estates (Boehm — Woods Road)
Second plan review completed November 20, 2001
Revised plans received r/m January 16 for review
QUIETWOOD CREEK (CARITY)
Sanitary Sewer Record Drawings submitted to MMSD November 14, 2002
Storm Sewer record drawings resubmitted to City August I, 2002
Quietwood Creek East
Design engineer picked up print of sanitary system map August 6, 2002 for design use
First design review letter submitted on August 22, 2002
Second design review letter submitted on December 3, 2002
Prairie Meadows Estates
First plan review completed May 31, 2002
Second plan review completed June 2, 2002
RAUSCH SANITARY PRESSURE SEWER— WOODS ROAD
COMPLETED WEEK OF FEBRUARY 19T"
Restoration is only remaining item.
Record drawings submitted to MMSD and City April 6, 2001
Reserve at Champions Village
Sanitary and Storm sewer main and water mains installed
Resubmitted sanitary sewer and water main record drawings to City August
Storm sewer record drawings submitted to City August 1, 2002
Punch list repairs completed.
PAGE 4
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday December 16, 2002
Riverview Court
Sanitary Sewer System map submitted to MMSD July 24, 2002
Construction started week of August 27`h
Sanitary installed but not tested, water main installed working on laterals
Utility installation completed and tested as of October 7, 2002 except for vacuum test on
sanitary manhole number 8 and
Second punch list sent to contractor on November 19, 2002
Field survey for record drawings completed December 3, 2002
Water main locator wire continuity test completed
Rosewood Estates Addition Number 1
Construction plans received for review August 5, 2002
City picked up Sanitary Sewer System Map September 23, 2002
Saint Leonard's water main (East Tower Drive)
Construction completed
Punch list repairs in process
Locator wire tested Monday September 9, 2002
All punch list items completed
Record drawing sent to City for first review September 27, 2002
SAL FERRITO SEWER (PRIVATE SANITARY SEWER)
DEWATERING WELL NOT REMOVED
LATERALS NOT CONNECTED YET
SARAH ESTATES (WOODS ROAD
Record drawings for Sanitary Sewer submitted to MMSD November 14, 2002
Storm Sewer record drawings on hold until adjustments before surface course paving
Punch lists are completed.
VICTORIAN VILLAS
VIDEO OF SEWER NOT YET RECEIVED
City has hired Visu-Sewer
COMPLETED PROJECTS ONLY AWAITING MMSD APPROVAL OF RECORD
DRAWINGS (AS BUILTS):
CHAMPIONS VILLAGES — ADDITION 2 (PHASE THREE)
HOLTZ-ARROWOOD
KNUDSON FORCE MAIN
NORTH CAPE FARM
WISA FORCE MAIN — HILLENDALE DRIVE
13-00000.010