PUM20021118• CITY OF MUSKEGO Approved
PUBLIC UTILITIES COMMITTEE MEETING
Minutes of Meeting Held Monday, November 18, 2002
Acting Chairman Rick Petfalski called the meeting to order at 7:03 p.m. Also
present was Committee member Ald. Madden, Engineering/Building Inspection
Director Sean McMullen, Public Utilities Superintendent Scott Kloskowski,
Ruekert & Mielke representative Rich Eberhardt and Mr Jacobus (Indian Trail).
It was noted that the meeting was posted in accordance with the Open Meeting
Law.
APPROVAL OF MINUTES OF PREVIOUS MEETING
Ald. Madden moved to approve minutes of meeting held October 21, 2002.
Seconded by Ald. Petfalski, motion carried 2-0.
STATUS OF PROJECTS
Ruekert & Mielke representative Rich Eberhardt reviewed the status of current
projects, per attached.
• Mr Eberhardt also updated the committee on the following:
• Janesville Road Water Project —The survey crews have completed work
on the extension.
• SEWRPC's 208 Plan Amendments — MMSD should be taking action on
the Blattner request on 11/20/02. Once they process, SEWRPC will begin
the May petition.
• McShane Storage Facilities — Walls are poured and decking is complete.
The contractor started filling the tank with water on Friday. Leakage
testing is being completed.
• Well Explorations Project- Test borings are all showing a lot of sand and
gravel. Well #3 is dry. Community Center site did not test out.
Quietwood Creek East development site looks promising. Ruekert &
Mielke think there may be a potential for two wells on this site.
• Pioneer Drive — The committee determined that they would like to invite
the Pioneer Drive residents to a meeting to discuss possible water
extension. As this will be a considerable number, the committee is looking
to have the informational meeting held on a separate night at the Public
• Library. The suggested date is Tuesday, January 7, 2003, at 7:00 PM.
Public Utilities Committee — November 18, 2002 Page 2
• SEWER UNFINISHED BUSINESS
Status of Town of Norway Contract — There was nothing new to report.
Further Review Request to Have City Purchase Property/Jacobus (Indian
Trail) — Mr Jacobus appeared before the committee and the committee inquired
if he had secured the two requested appraisals. Mr Jacobus claims that no one
is interested in appraising the property. Mr Jacobus now has hired an attorney
and the attorney is securing an appraiser Mr Jacobus requested, at the advice
of attorney, to request that this item be deferred. Aid. Petfalski moved to defer.
Seconded by Aid. Madden, motion carried 2-0.
SEWER NEW BUSINESS
Discuss Stoney Creek Sewer Usage Bill — The committee reviewed
memorandum from Sewer Utility Clerk Renee Kowalik showing the sewer usage
bill for the 3rd quarter for Lutherans Inc. for Elderly (Stoney Creek). The owners
are asking for some relief as the 3rd quarter showed 1,320,000 gallons and this
was due to dry weather and excessive grass watering. Scott explained that they
are metered right off their well and there is no easy way to plumb their outside
hose bib. After considerable discussion, Aid. Petfalski moved to base sewer
• usage charge for the 3rd quarter on water usage from the Ist quarter.
Seconded by Aid. Madden, motion carried 2-0. Aid. Petfalski requested a
copy of the 4ch quarter usage report for this complex when compiled.
Annual Review of Sewer Usage Charges — Hardship Status for 2003 — The
report received from Sewer Utility Clerk Renee Kowalik was reviewed and placed
on file.
WATER UNFINISHED
Status of request to PSC for water rate change — Scott advised that the
auditors were here this week gathering information for what is needed for PSC
application and they anticipate having information ready to submit in January of
2003.
WATER NEW BUSINESS
Review alternatives for radium standard compliance, wells 4, 5 and 6 —
Wells 4, 5 and 6 are above levels of acceptable radium. It appears as if well 4
and 6 should be abandoned. Well #5 is questionable and it was noted that a
considerable amount of money has been put into it. Scott felt there were three
choices for Well #5: a) Abandon, b) Inquire whether or not the DNR would let us
keep it as an emergency well (only to be used if several wells weren't working),
• and c) Add onto the building and put in some softening equipment and then
Public Utilities Committee — November 18, 2002
Page 3
• blend with radium water Scott stated that we might lose those three wells and
gain Freedom Square well. He recommends that the committee move forward
with acquiring well sites and expanding search for new sitings.
REPORT OF UTILITY SUPERINTENDENT — Scott reported that they are getting
quotes from everyone for the truck, but none for the crane. He is looking at a
2002 Lynch Truck for $29,231.00 and a box crane around $19,000.00, which will
be well within budget. The truck will be ordered this year if it comes within
budget.
ADJOURNMENT
Ald. Madden moved to adjourn at 7:41 p.m. Seconded by Ald. Petfalski, motion
carried 2-0.
Respectfully submitted,
Cathie M. Anderson
Recording Secretary
n
LJ
•
// /j/ -4�52 "2 -,
•
•
CONSULTANTS REPORT FOR:
PUBLIC UTILITIES COMMITTEE
• Monday November 18, 2002
Submitted Tuesday November 12, 2002
BOLD ITALICS INDICATE NEW INFORMATION
CITY PROJECTS:
FREEDOM SQUARE WATER SYSTEM
Design plans cannot be located by City or Freedom Square
Easements submitted to City for review and action week of May 131"
DNR has requested another 30-day extension, may need another extension
First floor elevation of pump house has to be more than 2 feet above regional flood
elevation. Working on proposal to modify Freedom Square pond outlet to lower this
elevation.
DNR will allow facilities to be acquired by easement (August 1)
Utility Superintendent forwarded easements to Condo Association to obtain from
Parkland Development Group
Connection approved by DNR October 30, 2002
JANESVILLE ROAD BOX CULVERT UTILITY RELOCATES
Cost estimates to be submitted to City week of February 18
Estimates and design alternatives submitted to City for review February 21, 2002
Design alternate selected August 28, 2002
• JANESVILLE ROAD WATER MAIN — JEWEL-OSCO TO COLLEGE AVENUE
Preliminary field survey completed, Preliminary plans in progress
Preliminary design to 1000 feet east of Tess Comers Drive complete
City authorized design to College Avenue September 12, 2002
Additional survey completed, preliminary plans in drafting
MANHOLE REHABILITATION 2001
Project closeout paperwork and Final Payment Recommendation forwarded to the City
April 1, 2002
Martin Drive Relocation — Utility extensions
On hold pending WDNR Alternatives Analysis to Wetland impacts
Mc Shane Pump Station — Bluhm Drive Storage Facility
Shop drawing submittals from contractor continue
De -watering started June 28"
Contractor graded and paved base course north of Bluhm Court October 9
Wall section pours should be completed week of November Il, 2002
Precast planks should be installed week of November 18, 2002
Tentatively start filling tank for leak test on Monday November 18, 2002
Moorland Road Water Main
Sample by City tested safe
• Punch list repairs in process
PAGE 2
is PUBLIC
report for
PUBLIC UTILITIES COMMITTEE
Monday November 18, 2002
Well Site Exploration
Contract for exploratory wells to Layne Northwest to be executed soon
Four test borings completed
Working with City on planned development issues.
WOODS ROAD — BROOKE LANE TO EAST OF RACINE AVENUE
Project close out paper work sent to City July 25, 2002
DEVELOPMENTS:
CANDLEWOOD (INTERIOR)
Construction started July 26
Sanitary completed but not fully tested, water installed and tested
Storm sewer should be completed week of September I I
Water main locator wire continuity test not completed
Sample test reports safe, wet connections completed
Punch list review after sump drains installed week of November 25, 1002
Chamberlain Hill
• Design engineer picked up print of sanitary system map August 6 for design use
JEWEL — OSCO / KOHLS ONSITE UTILITIES AND LIFT STATION
Field change for the Lift Station relocation design changes completed and submitted to
City and Developer
Onsite construction completed and tested except for lift station
Punch list reviews to begin the week of September 12, 2002
Record Survey scheduled
All punch list items completed as of October 11, 2002
Water main and force main locator wire continuity tests not completed
Field survey for record drawings started
JEWEL — OSCO / KOHLS Offsite water main
Record drawings submitted August 1, 2002 for City Staff review
Recheck of punch list items week of November 18, 2002
LAKEWOOD CONDOMINIUMS (OVERLOOK BAY)
Punch list repairs completed
Final record drawings for sanitary sewer and water main submitted to City
Storm water system record drawings submitted to City, pending location of pond outfall
south of building number 4
MUSKEGO CENTER/BERG
AS BUB_TS COMPLETED
• PUNCH LIST SENT TO CONTRACTOR
PAGE 3
• Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday November 18, 2002
MUSKEGO MOTOR CAR CO
PUNCH LIST RESENT TO CONTRACTOR
MMSD REVIEWED AS BUILTS FEBRUARY 2, 2000
CONTRACTOR TOLD R/M THEY WILL NOT COMPLETE DUE TO PAYMENTS
NOT RECEIVED
Nature Estates (Boehm — Woods Road)
Second plan review completed November 20, 2001
Revised plans received r/m January 16 for review
QUIETWOOD CREEK (CARITY)
Water and Sanitary Sewer Record Drawings resubmitted to City August 1, 2002
Storm Sewer record drawings resubmitted to City August 1, 2002
Quietwood Creek East
Design engineer picked up print of sanitary system map August 6, 2002 for design use
First design review letter submitted on August 22, 2002
Prairie Meadows Estates
First plan review completed May 31, 2002
• Second plan review completed June 2, 2002
RAUSCH SANITARY PRESSURE SEWER — WOODS ROAD
COMPLETED WEEK OF FEBRUARY 19r"
Restoration is only remaining item.
Record drawings submitted to MMSD and City April 6, 2001
Reserve at Champions Village
Sanitary and Storm sewer main and water mains installed
Resubmitted sanitary sewer and water main record drawings to City August I
Storm sewer record drawings submitted to City August 1, 2002
Punch list repairs completed.
Riverview Court
Sanitary Sewer System map submitted to MMSD July 24, 2002
Construction started week of August 27
Sanitary installed but not tested, water main installed working on laterals
Utility installation completed and tested as of October 7, 2002 except for vacuum test on
sanitary manhole number 8 and water main locator wire continuity test
Punch list review week of November 18, 2002
Rosewood Estates Addition Number 1
Construction plans received for review August 5, 2002
• City picked up Sanitary Sewer System Map September 23, 2002
PAGE 4
Consultant's report for
is PUBLIC UTILITIES COMMITTEE
Monday November 18, 2002
Saint Leonard's water main (East Tower Drive)
Construction completed
Punch list repairs in process
Locator wire tested Monday September 9, 2002
All punch list items completed
Record drawing sent to City for first review September 27, 2002
SAL FERRITO SEWER (PRIVATE SANITARY SEWER)
DEWATERING WELL NOT REMOVED
LATERALS NOT CONNECTED YET
SARAH ESTATES (WOODS ROAD
Record drawings for Sanitary Sewer, Water Main and Storm Sewer submitted to City
Storm Sewer record drawings on hold until adjustments before surface course paving
Punch lists are completed.
VICTORIAN VILLAS
VIDEO OF SEWER NOT YET RECEIVED
City has hired Visu-Sewer
• COMPLETED PROJECTS ONLY AWAITING MMSD APPROVAL OF RECORD
DRAWINGS (AS BUILTS):
CHAMPIONS VILLAGES — ADDITION 2 (PHASE THREE)
HOLTZ - ARROWOOD
KNUDSON FORCE MAIN
NORTH CAPE FARM
WISA FORCE MAIN — HILLENDALE DRIVE
13-00000.010