PUM20020916• CITY OF MUSKEGO Approved
PUBLIC UTILITIES COMMITTEE MEETING
Minutes of Meeting Held Monday, September 16, 2002
Chairman Dave Sanders called the meeting to order at 7:05 p.m. Also present
were Committee members Aid. Rick Petfalski and Aid. Eileen Madden,
Engineering/Building Inspection Director Sean McMullen, Public Utilities
Superintendent Scott Kloskowski, Ruekert & Mielke representatives Mike
Campbell and Rich Eberhardt, as those per attached list.
It was noted that the meeting was posted in accordance with the Open Meeting
Law.
APPROVAL OF MINUTES OF PREVIOUS MEETING
Aid. Petfalski moved to approve minutes of meeting held September 6, 2002.
Seconded by Aid. Madden, motion carried 3-0.
STATUS OF PROJECTS
Rich Eberhardt updated the Committee on the status of projects dated
• September 16, 2002, as attached.
SEWER UNFINISHED BUSINESS
Status of Town of Norway Contract — There was nothing new to report.
Further Review Request to Have City Purchase Property/Jacobus (Indian
Trail) — There was nothing new to report.
Review Deadline for Connection/O'Malley — Mr Jack Henry appeared before
the Committee representing the O'Malley property on North Cape Road.
Engineering/Building Inspection Director McMullen has talked to Attorney Molter
regarding this matter Attorney Molter's office is reviewing the sewer ordinance
and will have a recommendation for the Committee by the next meeting. No
action was taken.
Further Discussion of Purchase of Utility Vehicle — There was nothing new to
report.
Further Review Quarterly Charge Set for Sewer Meters & Deduct Meters (Ord.
#1113) — Aid. Petfalski moved to set quarterly charge on sewer meters at
$6.00/quarter, the same cost as deduct meters. Aid. Madden seconded, motion
• carried 3-0.
SEWER NEW BUSINESS
Review Request for Amendment to SEWRPC 208 Plan (May Property) —
Engineering/Building Inspection Director McMullen explained that this proposal to
transfer sewer service area between parcels was previously approved. The
developer is now ready to send the request to SEWRPC. Engineering/Building
Inspection Director McMullen brought the item back to the Committee for review
to see if there were any further questions. The Committee had no further
questions. Aid. Madden moved to approve. Seconded by Aid. Petfalski, motion
carried 3-0.
Review Commercial Properties That Have Not Complied with Meter
Installation Requirements — Public Utilities Superintendent Kloskowski reported
on businesses that have not installed meters on their water supplies as required.
Amann's and DeMarini's are the two remaining businesses which have not
complied. Utilities Superintendent Kloskowski reported that further action may
need to be taken to obtain compliance.
WATER UNFINISHED BUSINESS
Status on Potential Impacts to Well #7/Status of Stoneridge Groundwater
Remediation — There was nothing new to report.
• Further Discussion on Installation of Water on Pioneer Drive — Utilities
Superintendent Kloskowski reported on well log research being done on Pioneer
Drive. As the web site for the Department of Natural Resources only allows a
search by well driller or by date, Nancy Payne from the DNR is assisting using
DNR software that allows a search by quarter section.
WATER NEW BUSINESS
Discuss Water Service for Weatherwood Courts (Laimon Property) —
Engineering/Building Inspection Director McMullen explained that developments
of five lots or more need to come before the Public Utilities Committee to
determine what their water source will be. Since is a great distance from the
municipal water system, Engineering/Building Inspection Director McMullen does
not recommend requiring connection to the municipal system. The other
alternatives are private wells and a community well. Engineering/Building
Inspection Director McMullen and Public Utilities Superintendent Kloskowski
recommend that private wells be allowed. Aid. Petfalski moved to allow private
wells in this development. Seconded by Aid. Madden, motion carried 3-0.
REVIEW OF PRELIMINARY SEWER AND WATER BUDGETS FOR 2003
• Public Utilities Superintendent Kloskowski distributed 2003 sewer and water
budgets for preliminary review.
• REVIEW OF DEFERRED ASSESSMENTS/SEWER & WATER
The Committee reviewed a letter from Kathy & Dick Patterson dated September
11, 2002 expressing their objection to the deferred assessment plus interest on
their property. Aid. Petfalski moved to deny request for removal of the
assessment plus interest from the Patterson property. Seconded by Aid.
Sanders, motion carried 3-0.
ADJOURNMENT
Aid. Petfalski moved to adjourn at 8:00 p.m. Seconded by Aid. Madden, motion
carried 3-0.
Respectfully submitted,
Scott Kloskowski
Public Utilities Superintendent
jZ
•
•
C c. ry , W ,
CONSULTANTS REPORT FOR.
PUBLIC UTILITIES COMMITTEE
• Monday September 16, 2002
Submitted Wednesday September 11, 2002
BOLD ITALICS INDICATE NEW INFORMATION
CITY PROJECTS:
FREEDOM SQUARE WATER SYSTEM
Design plans cannot be located by City or Freedom Square
Easements submitted to City for review and action week of May 13'n
DNR has requested another 30-day extension, may need another extension
First floor elevation of pump house has to be more than 2 feet above regional flood
elevation. Working on proposal to modify Freedom Square pond outlet to lower this
elevation.
DNR will allow facilities to be acquired by easement (August 1)
Utility Superintendent forwarded easements to Condo Association to obtain from
Parkland Development Group
JANESVILLE ROAD BOX CULVERT UTILITY RELOCATES
Cost estimates to be submitted to City week of February 18
Estimates and design alternatives submitted to City for review February 21, 2002
Design alternate selected August 28, 2001
JANESVILLE ROAD WATER MAIN — JEWEL-OSCO TO ST PAULS CHURCH
• Preliminary field survey completed, Preliminary plans in progress
MANHOLE REHABILITATION 2001
Project closeout paperwork and Final Payment Recommendation forwarded to the City
April I, 2002
Martin Drive Relocation — Utility extensions
On hold pending WDNR Alternatives Analysis to Wetland impacts
Mc Shane Pump Station — Bluhm Drive Storage Facility
Shop drawing submittals from contractor continue
De -watering started June 28 s
Gravity sewer completed, Force Main by pass piping installed
Concrete poured for wet well area
Main floor slab graded, stone base installed and steel installation started
One residential well failed. System replaced
Moorland Road Water Main
Water main installed, filled and tested.
Waiting for Safe Sample report
Well Site Exploration
Contract for exploratory wells to Layne Northwest to be executed soon
n
U
PAGE 2
Consultant's report for
• PUBLIC UTILITIES COMMITTEE
Monday September 16, 2002
WOODS ROAD — BROOKE LANE TO EAST OF RACINE AVENUE
Project close out paper work sent to City July 25, 2002
DEVELOPMENTS:
CANDLEWOOD (INTERIOR)
Pre -construction conference held
Construction started July 26
Sanitary completed but not fully tested, water installed and tested waiting for
safe sample report, storm sewer should be completed week of September 11
Chamberlain Hill
Design engineer picked up print of sanitary system map August 6 for design use
JEWEL — OSCO / KOHLS ONSITE UTILITIES AND LIFT STATION
Field change for the Lift Station relocation design changes completed and submitted to
City and Developer
Onsite construction completed and tested except for lift station
Punch list reviews to begin the week of September 12, 2002
Record Survey scheduled
• JEWEL — OSCO / KOHLS Offsite water main
Record drawings submitted August I, 2002 for City Staff review
LAKEWOOD CONDOMINIUMS (OVERLOOK BAY)
Punch list repairs completed
Final record drawings for sanitary sewer and water main submitted to City
Storm water system record drawings submitted to City, pending location of pond outfall
south of building number 4
MUSKEGO CENTER/BERG
AS BUILTS COMPLETED
PUNCH LIST SENT TO CONTRACTOR
MUSKEGO MOTOR CAR CO
PUNCH LIST RESENT TO CONTRACTOR
MMSD REVIEWED AS BUILTS FEBRUARY 2, 2000
CONTRACTOR TOLD R/M THEY WILL NOT COMPLETE DUE TO PAYMENTS
NOT RECEIVED
Nature Estates (Boehm — Woods Road)
Second plan review completed November 20, 2001
Revised plans received r/m January 16 for review
•
PAGE
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday September 16, 2002
QUIETWOOD CREEK (CARITY)
Water and Sanitary Sewer Record Drawings resubmitted to City August 1, 2002
Storm Sewer record drawings resubmitted to City August 1, 2002
Quietwood Creek East
Design engineer picked up print of sanitary system map August 6, 2002 for design use
First design review letter submitted on August 22, 2002
Prairie Meadows Estates
First plan review completed May 31, 2002
Second plan review completed June 2, 2002
RAUSCH SANITARY PRESSURE SEWER — WOODS ROAD
COMPLETED WEEK OF FEBRUARY 19Tn
Restoration is only remaining item.
Record drawings submitted to MMSD and City April 6, 2001
Reserve at Champions Village
Sanitary and Storm sewer main and water mains installed
Resubmitted sanitary sewer and water main record drawings to CityAugust I
• Storm sewer record drawings submitted to City August 1, 2002
Punch list repairs completed except for one internal seal.
Riverview Court
Sanitary Sewer System map submitted to MMSD July 24, 2002
Construction started week of August 27,"
Sanitary installed but not tested, water main installed working on laterals
Rosewood Estates Addition Number I
Construction plans received for review August 5, 2002
Saint Leonard's water main (East Tower Drive)
Construction completed
Punch list repairs in process
Record survey and drawing scheduled
Locator wire tested Monday September 9, 2002
SAL FERRITO SEWER (PRIVATE SANITARY SEWER)
DEWATERING WELL NOT REMOVED
LATERALS NOT CONNECTED YET
40
PAGE 4
Consultant's report for
• PUBLIC UTILITIES COMMITTEE
Monday September 16, 2002
SARAH ESTATES (WOODS ROAD
Record drawings for Sanitary Sewer, Water Main and Storm Sewer submitted to City
Storm Sewer record drawings on hold until adjustments before surface course paving
Punch lists arc completed.
VICTORIAN VILLAS
VIDEO OF SEWER NOT YET RECEIVED
City has hired Visu-Sewer
COMPLETED PROJECTS ONLY AWAITING MMSD APPROVAL OF RECORD
DRAWINGS (AS BUILTS):
CHAMPIONS VILLAGES — ADDITION 2 (PHASE THREE)
HOLTZ-ARROWOOD
KNUDSON FORCE MAIN
NORTH CAPE FARM
WISA FORCE MAIN — HILLENDALE DRIVE