Chairman Rick Petfalski called the meeting to order at 7:00 p.m. Also present
was Committee member Aid. Eileen Madden, Engineering/Building Inspection
Director Sean McMullen, Public Utilities Superintendent Scott Kloskowski,
Ruekert & Mielke representative Rich Eberhardt, and those per the attached list.
Aid. Sanders was absent.
It was noted that the meeting was posted in accordance with the Open Meeting
Law.
APPROVAL OF MINUTES OF PREVIOUS MEETING
Aid. Madden moved to approve minutes of meetings held May 20, 2002 and May
28, 2002. Seconded by Ald. Petfalski, motion carried 2-0.
STATUS OF PROJECTS
Rich Eberthardt updated the Committee on the status of projects per report
attached.
• SEWER UNFINISHED BUSINESS
Status of Town of Norway Contract — There was nothing new to report.
Status of Proposed Amendment to SEWRPC's 208 Plan —
Engineering/Building Inspection Director McMullen reported that the plans are at
SEWRPC for review.
Further Review Request to have City Purchase Property/Jacobus (Indian
Trail) — Utilities Superintendent Kloskowski reported that a response has not
been received from Mr Jacobus.
Further Review of Sewer Usage Charts and Compare REC Purchases —
Engineering/Building Inspection Director McMullen and Utilities Superintendent
Kloskowski reported meeting with the engineers from Ruekert & Mielke and the
City Attorney. It has been determined that more research needs to occur before
a recommendation can be made.
Further Review of Deferred Sewer Assessment (Richard Patterson,
#2256.993 — North Cape Road ) — There was nothing new to report.
•
Public Utilities Committee
• June 17, 2002 — Page 2
Review Deadline for Connection (O'Malley) — Ald. Petfalski moved to extend
deadline for O'Malley's connection to sewer to August 31, 2002 with the
contingency that Mr O'Malley cash the check that was issued to him for
reimbursement of the lateral that was not installed as part of the project within the
next fourteen days. There is also a requirement to secure the building and have
the utilities disconnected as soon as possible. There will not be any further
extensions. Seconded by Ald. Madden, motion carried 2-0. Utilities
Superintendent Kloskowski reported that the Utilities' course of action would be a
forced connection of the building with costs charged back to the property owner if
the building is not removed by August 31, 2002.
SEWER NEW BUSINESS
Discuss Sewer Extension/Highway G (Old Loomis Road) —
Engineering/Building Inspection Director McMullen explained the request by
several property owners on Loomis Road. Several residents have failed septic
systems and would like to connect to sewers in the Town of Norway.
Engineering/Building Inspection Director McMullen requests that an area survey
be taken to determine if there is further interest in municipal sewer service in this
area. The Committee agreed that survey should be done for residents on
• Loomis Road from Union Church Road to Muskego Dam Road including
Ludwig's Cabinet Shop.
Discuss 550 Ft. of Proposed Sewer Extension — Bluhm Drive South to
McShane Road — Engineering/Building Inspection Director McMullen explained
the proposal. The question to be answered is whether the Utility should extend
gravity sewermain south of the storage facility to McShane Road now since
Bluhm Drive is being destroyed as part of the current project. The Utilities
Committee looked at this in the early stages of the storage facility and decided
not to extend since there didn't seem to be an immediate need for this main.
Engineering/Building Inspection Director McMullen explained that a developer
was now negotiating with the owner of the property south of McShane from
Bluhm Drive to Mystic Drive. Engineering/Building Inspection Director McMullen
asked the Committee to direct Ruekert & Mielke to study this area to determine
the pipe size and depth needed to service the entire area serviced by this
extension.
Aid. Pettalski moved to direct Ruekert & Mielke to study this basin and determine
size and depth of pipe needed and to formulate a cost estimate for an extension
south to McShane. Seconded by Ald. Madden, motion carried 2-0.
Public Utilities Committee
• June 17, 2002 — Page 3
WATER UNFINISHED BUSINESS
Status on Potential Impacts to Well #7/Status of Stoneridge Groundwater
Remediation — There was nothing new to report.
Status on Proposed Power Plants — Muskego/New Berlin — There was
nothing new to report.
Further Discussion of Water Service — Rosewood Estates, Addn. #1 -
Engineering/Building Inspection Director McMullen asked for deferral of this item
to allow time to discuss further with the developer of the property to the west.
ADJOURNMENT
Aid. Madden moved to adjourn at 7:45 p.m. Seconded by Aid. Petfalski, motion
carried 2-0.
Respectfully submitted,
• Scott Kloskowski
Public Utilities Superintendent
jZ
•
06/25/2002
•
•
•
10:21 262-679-4151
)`,1-4 1? -�D
MUSKEGO DPW & UTIL
PAGE 01
06/25/2002 09:59 262-679-4151
MUSKEGO DPW,& UTIL -
PAGE 02
• CONSULTANTS REPORT FOR:
PUBLIC UTILITIES COMMITTEE
MONDAY, June 17, 2002
Submitted Wednesday June 12, 2002
BOLD ITALICS INDICATE NEW INFORMATION
CITY PROJECTS:
FREEDOM SQUARE WATER SYSTEM
Design plans can not be located by City or Freedom Square
Easements submitted to City for review and action week of May 13°i
DNR has requested another 30-day extension,
Letter was sent with extension
HIGHVIEW ACRES
Contractor tested and reset all seals except one manhole which was paved over
MANHOLE REHABMITATION 2001
Project closeout paperwork and Final Payment Recommendation forwarded to the City
April 1, 2002
Martin Drive Relocation —Utility extensions
On holdpending WDNR Alternatives Analysis to Wetland impacts
• Mc Shane Pump Station — Bluhm Drive Storage Facility
All first round well measurements and testing have been completed
Shop drawing submittals from contractor continue
Preconstruction conference held Thursday May 360
Public informational meeting held Thursday May 16
Contracts forwarded to City for signatures June 6'h
Mobilization for de -watering started
Access road construction started, should be paved Monday or Tuesday
Moorland Road Water Main
Contractor delayed by rain
Tentative schedule Mid June through mid July
Design changes in process due to new development adjacent to project
WOODS ROAD — BROOKE LANE TO EAST OF RACINE AVENUE
Project close out paper work sent to contractor
DEVELOPMENTS:
CANDLEWOOD (INTERIOR)
Phase one plans have been reviewed.
Met with Developer's engineer and City on February 7 to clarify design issues
New plan submittal reccived March 12, 2002 for review
0
06/25/2002 09:59 262-679-4151
MUSKEGO DPW & UTIL
PAGE 03
• PAGE
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday June 12, 2002
JANESVILLE ROAD BOX CULVERT UTILITY RELOCATES
Cost estimates to be submitted to City week of February 18
Estimates and design alternatives submitted to City for review
JANESVILLE ROAD WATER MAIN— JEWEL-OSCO TO ST PAULS CHURCH
Preliminary field survey completed
Preliminary plans in progress
JEWEL — OSCO / KOHLS ONSITE UTILITIES AND LIFT STATION
On site construction on hold until week of June 17th
Water main connection to Janesville Road from Kohl's not installed
Field change for the Lift Station relocation design changes completed and submitted to
City and Developer
JEWEL — OSCO / KOHLS Offsite water main
Eastern 300 feet completed
Safe water sample reports have been received
Field work for record drawings completed
• LAKEWOOD CONDOMINIUMS (OVERLOOK BAY)
Punch list repairs completed
Final record drawings for sanitary sewer and water main submitted to City
Storm water system record drawings submitted to City, pending location of pond outfall
south of building number 4
MUSKEGO CENTER/BERG
AS BUILTS COMPLETED
PUNCH LIST SENT TO CONTRACTOR
MUSKEGO MOTOR CAR CO
PUNCH LIST RESENT TO CONTRACTOR
MMSD REVIEWED AS BUILT$ FEBRUARY 2, 2000
CONTRACTOR TOLD R/M THEY WILL NOT COMPLETE DUE TO PAYMENTS
NOT RECEIVED
Nature Estates (Boehm — Woods Road)
Second plan review completed November 20, 2001
Revised plans received r/m January 16 for review
QUIETWOOD CREEK (CARITY)
Punch list repairs completed for Sanitary Sewer and Water main
Water and Sanitary Sewer Record Drawings resubmitted to City May 10, 2002
• Storm Sewer record drawings submitted to City for first review May 10, 2002
06/25/2002 09:58 262-679-4151
PAGE
Consultant's report for
PUBLIC UTILITIES COMMITTEE
Monday June 12, 2002
Prairie Meadows .Estates
MUSKEGO DPW & UTIL
PAGE 04
First plan review completed May 31, 2002
RAUSCH SANITARY PRESSURE SEWER — WOODS ROAD
COMPLETED WEEK OF FEBRUARY 19TH
Restoration is only remaining item.
Record drawings submitted to MMSD and City April 6, 2001
Reserve at Champions Village
Sanitary and Storm sewer main and water mains installed
Preliminary sanitary sewer and water train record drawings submitted to City for review
April 1, 2002
Underground utilities completed, punch list being sent to contractor this week
Riverview Court
Saint Leonard's water main (East Tower Drive)
Revised design plans and DNR forms submitted to City
DNR approval letter received
Preconstruction conference held June S, tentative start Monday June 17
SAL FERRITO SEWER (PRIVATE SANITARY SEWER)
DEWATERING WELL NOT REMOVED
LATERALS NOT CONNECTED YET
SARAH ESTATES (WOODS ROAD
Record drawings for Sanitary Sewer, Water Main and Storm Sewer submitted to City
Storm Sewer record drawings on hold until inlet frames are set to final grade and final
surface paving
Punch lists are completed.
VICTORIAN VILLAS
VIDEO OF SEWER NOT YET RECEIVED
City has hired Visu-Sewer
COMPLETED PROJECTS ONLY AWAITING MMSD APPROVAL OF RECORD
DRAWINGS (AS BUILTS):
CHAMPIONS VILLAGES — ADDITION 2 (PHASE THREE)
HOLTZ-ARROWOOD
KNUDSON FORCE MAIN
NORTH CAPE FARM
• WLSA FORCE MAIN — HILLENDALE DRIVE