PUM20010219PUBLIC UTILITIES COMMITTEE MEETING - CITY OF MUSKEGO Approved
Minutes of Meeting Held Monday February 19, 2001
Chairman David Sanders called the meeting to order at 7:15 PM. Present were committee members Aid. Mark
Slocomb and Aid. William Le Doux. Also present were Utilities Superintendent Scott Kloskowski, Mayor De
Angelis, and Ruckert - Mielke representative Richard Eberhardt.
It was noted by Chairman David Sanders that the meeting was posted in accordance with the Open Meeting Law.
Approval of Minutes of Previous Meeting
Ald. Le Doux moved to approve the minutes of the January 22, 2001 and February 13, 2001 meetings. Seconded by
Ald. Slocomb, motion carried.
Status of Projects
Richard Eberhardt reviewed the status of projects (as per attached) noting the following updates. EPI lift station
contractor intends to start March 12, 2001, with a final completion date of August 15, 2001, Rausch system passes
testing and restoration will be done in Spring. Quietwood Creek is having some problems with cracked fittings on the
risers.
Status of Town of Norway Contract
Nothing new to report.
Status of Sewer Metering
Scott reported that there had been a problem with the supplier. The meters have been received and should be
installed before the end of this quarter. Since the meters have been delivered, the deadline to install the meters will be
March 31, 2001,
• Status of MMSD Proposed Storm Water Rules
The Technical Committee meeting has been postponed until March. The Committee reviewed the letter sent to
MMSD from Michael Campbell of Ruekert— Mielke.
Review request for sewer capacity — Nature Estates (Boehm)
Mr. Wayne Salentine appeared before the committee at the 11/16/00 meeting, to request sewer capacity for a fifteen
(15)-lot subdivision on the south side of Woods Rd. Director McMullen reported the City is waiting for a further
clarification on the Amended 208 Sewer Service Area from SEWRPC. The Plan Director will be meeting with
SEWRPC this week.
Review Deadline of Sewer Connections
The property owner of S69 W 16643 Martin Dr. (#2171.113) had been given a deadline to connect to the sewer
system of November 24, 2000. The property did supply the committee a copy of their signed contract. The property
owner called on February 14, and reported that she spoke with her contractor and plans to be connected by February
23. Ald. Sanders made a motion to defer until next month. Ald. Le Doux seconded, motion carried.
Further discussion on claim received from Zaharopoulos — Boxhorn-Grovewav-Rvan Sewer Proiect
Mr. Zaharopoulos was invited to attend the meeting and supply cancelled checks for items in claim. Aid. Slocomb
informed the committee he spoke with an Attorney who is working with Mr. Zaharopoulos on gathering information
requested by the committee. Ald Slocomb made a motion to defer in order to review a detailed package to be sent in
before next month's meeting. AId. Le Dour seconded, motion carried.
Status of alternatives for in -line storage at McShane Lift Station
The committee reviewed the preliminary schedule and cost estimates for the McShane Storage Facility provided by
IR Ruekert — Mielke.
North Cape Ryan 500' N of Boxhorn Sewer Project
The committee reviewed the Public Hearing comments. Mr. Dumke was present and had several questions on
connecting to the sewer system and the expense. Mr. Dumke noted he had not been invited to the last meeting. The
foundry owned by Mr. Dumke will be serviced internally by a grinder pump connected to the 2" pressure lateral that
was assessed on the Lorenz property. Mr. Dumke asked if his two houses that set back approximately 1000' would
Public Utilities Committee Minutes — 2/19/2001 — Page 2
be required to connect. Ald. Slocomb indicated the committee would not require the houses to connect at this time
because the distance was over 500' The committee reviews the standby properties on an annual basis. Mr. Dumke
• indicated the foundry would need to update the bathrooms to meet building requirements. Scott directed Mr. Dumke
to check if the plumbing code would require a need for possibly a duplex grinder pump in order to serve all of his
properties in the future. Scott suggested Mr. Dumke get several estimates from contractors for the conversion work.
Ald. Slocomb suggests hiring a contractor that has experience with conversions. Ms. Lorenz was concerned if the
foundry was sold how the connection of her property would be affected. Scott suggested that an agreement regarding
the connection be done in advance between the two properties should a change of ownership take place. Mr. Blattner
and family were there to find out the decision of the committee on the method of assessment. Mr. Blattner questioned
the possibility of servicing future parcels on his property. The committee suggested he meet with the Plan Director.
The committee also discussed that some of his property is outside of the sewer service area. The committee reviewed
the three ways the assessment roll had been calculated. Since the county determines how many access points the
property has, the committee felt the fair way to assess would be on front foot only verses a unit assessment. Aid.
Slocomb made a motion to determine the assessment method to be on the front foot basis. Ald. Le Doux seconded,
motion carried. Rich discussed the reduction of the alternative bid of $9,730.00 and how this would affect the
assessments. Aid. Slocomb made a motion to reduce the project cost by the $9, 730.00 and to recalculate the front
foot cost to reflect the reduction and to recommend approval with these changes of the final assessment roll to
council. Aid. Sanders seconded, motion carried. Rich indicated he would have the address and tax key
correctionsmade on the assessment roll by Friday. A letter will be sent to the property owners to have them indicate
how many laterals they would like for their property. Ald. Slocomb discussed the interest rate and noted that the
committee had not received input from the Finance Director. The committee would like the method of calculating
interest to be researched and analyzed by the Finance Director prior to Council's final approval. Ald. Slocomb made
a motion to set the interest rate at 8%subject to reviewing the information requestedfrom the Finance Director. Aid.
Le Doux seconded, motion carried.
SEWER NEW BUSINESS
• Review Condo's Sewer Usage Charges
Pioneer Centre has two buildings that have two units each. Due to the fact the meter is installed on the well head the
question is how the two buildings should be charged for sewer usage. Ald. Slocomb made a motion to charge the two
buildings in the Pioneer Centre Condo's that have two units each as part of the complex, based on metered usage
plus a connection charge per building. Ald. Le Doux seconded, motion carried. Pioneer Center and Freedom Square
Condo's have requested that each unit receive an individual bill.
Review Bids for Manhole Rehabilitation Program Continuation
The committee reviewed the following bids for the project:
Contractor
Base Bid
Infratech
$ 245,135.00
United Sewer & Water
$ 320,975.00
Rawson Contractors Inc.
$ 240,604.00
Advanced Sewer & Water
$ 249,456.00
American Sewer Services Inc.
$ 341,530.00
Super Excavators, Inc.
$ 289,965.00
MJ Construction Inc.
$ 254,067.80
Michels Pipeline Constr. Inc.
$ 361,270.00
Underground Pipeline Inc.
$ 227,634.00
Globe Contractors Inc.
$ 393,570.00
Ald. Sanders made a motion to accept the recommendation of the engineers for the low bid, Underground Pipeline,
Inc. in the amount of$ 227,634.00, contingent on receipt of Waukesha County Department of Public Works permit
• for the 2001 Muskego Sanitary Manhole Rehab Program Project. Ald. Slocomb seconded, motion.
TUATVn TTNVT TQL V"
Status of Stoneridge Ground Water Remediation
Nothing new to report.
Public Utilities Committee Minutes — 2/19/2001 — Page 3
Status on proposed electrical power plant — New Berlin
Mayor reported a binder of information had been dropped off in his office for review.
• Status of Repainting of the Water Tower
Mayor reported the City is waiting to hear back from the Bonding Company.
WATER NEW BUSINESS
Review Correspondence from Ruekert — Mielke on Regional Water Supply Issues
The committee discussed the letter from Steven H. Schultz of Ruckert — Mielke, urging the communities to contact
SE WRPC and express support for a regional study. The committee discussed the need to create a model for a
baseline data. The Mayor will be sending a letter in response to the regional study.
Determine meeting Date for Proposed Janesville Rd. Water Project
The Mayor's office will be scheduling a meeting with Rich, and to invite the property owners in to determine interest
in a proposed water project on Janesville Rd.
Mr. Rich Eberhardt was dismissed at 8:36 p.m.
REVIEW OF DEFERRED ASSESSMENTS/SEWER & WATER — Nothing new to report.
REVIEW OF FIVE-YEAR CAPITAL PLAN - Nothing new to report.
ACCEPTANCE OF IMPROVEMENTS
The committee reviewed the memo from Mr. McMullen recommending the committee to approve sewer and water
plans for the Reserve at Champion's Village. Aid. Slocomb made a motion to approve sewer and water plans for the
Reserve at Champion's Village contingent on the completion of the corrections listed in the February 15, 2001 letter
from Ken Ward on the sewer and water main, amd MMSD and DNR approval, also on the receipt ofsatisfactoryfire
40 flow computations for Ruckert — Mielke. Ald. Le Doux, seconded, motion carried.
REPORT OF UTILITY SUPERINTENDENT/REPORT OF CITY ENGINEER
Scott reported on the significant rain event and that the system held its own. Scott also reported the North Shore Lift
Station startup had been done, and everything went good. Training will be held next week.
COMMUNICATIONS AND ANY OTHER BUSINESS AS AUTHORIZED BY LAW — None
Ald. Slocomb moved to adjourn at 9: 05 RM Seconded by Ald. Le Doux, motion carried
Respectfully submitted,
Q
Renee IwalikQL(iG2X.t/ �
Recording Secretary
• CONSULTANTS REPORT FOR:
PUBLIC UTILITIES COMMITTEE
MONDAY, FEBRUARY 19, 2001
Submitted Wednesday February 14, 2001
BOLD ITALICS INDICATE NEW INFORMATION
CITY PROJECTS:
BOXHORN, RYAN, GROVEWAY
CLOSEOUT BEING HANDLED BY THE CITY
HIGHVIEW ACRES
WAITING ON CHIMNEY SEAL REINSTALLATION
HILLENDALE DR 1300 FT S TO 3500 FT S OF JANESVILLE RD
PROJECT CLOSE OUT IN PROCESS
LOOMIS DRIVE / NORTH CAPE RD - US45 / MSS- IC-96 -
LETTER SENT WITH FINAL PAPERWORK REQUIREMENTS
PROJECT FINAL PAYMENT ON HOLD PENDING LIEN RESOLUTION
MANHOLE REHABILITATION 2000
CONTRACTOR HAS STARTED CLOSE OUT PAPERWORK
PUNCH LIST TO BE REPAIRED IN SPRING
• MANHOLE REHABILITATION 2001
BIDS OPENED FEBRUARY 15, 2001
NORTH SHORE LIFT STATION GENERATOR
STARTUP TEST FEBRUARY 13, 2001
SWITCH OVER ON FEBRUARY I4, 2001
NORTH CAPE ROAD / RYAN RD TO 500 FT N. OF BOXHORN DR.
COUNTY HAS INQUIRED ABOUT SCHEDULE - THEY PAVE IN 2001
MMSD/DNR APPROVAL PACKAGE SUBMITTED NOVEMBER 29
MMSD WAS WAITING ON DNR APPROVAL
RECEIVED DNR APPROVAL
CONTRACTOR STATED: WEPCO STARTED RELOCATING POLE
ASSESSMENT HEARING HELD FEBRUARY 13, 2001
WOODS ROAD - KURTZE LANE TO BAY LANE PROJECT MW-26-99
PROJECT CLOSE OUT PAPER WORK STARTED
WOODS ROAD - BROOKE LANE TO EAST OF RACINE AVENUE
CONTRACTOR REQUESTING FINAL PAYMENT
DEVELOPMENTS:
AVION ESTATES
PUNCHLIST REMAINS
• CANDLEWOOD (INTERIOR)
PHASE ONE NOT SUBMITTED
PAGE
PUBLIC UTILITIES COMMITTEE
MONDAY FEBRUARY 19, 2001
CANDLEWOOD - WOODS ROAD WATER MAIN
STARTED FEBRVARYI2, 2001
MUST BE COMPLETED BY MARCH 20, 2001
CHAMPIONS VILLAGES - ADDITION 3 (PHASE FOUR)
PUNCH LIST SENT TO CONTRACTOR DECEMBER 1, 2000
CONTRACTOR WORKED ONPUNCHLIST
MANHOLE FRAME RESET SEAL REINSTALLED
DEER CREEK TWO
PUNCH LIST SENT TO CONTRACTOR
RESTORATION, WAS DONE ADJACENT TO LAKE RIDGE
DYER EASEMENT - HILLENDALE DRIVE
PUNCHLIST COMPLETED EXCEPT FOR RESTORATION
RECORD DRAWING SUBMITTED TO CITY FEBRUARY 2
•
EPI LIFT STATION / FORCE MAIN
EASEMENT ACQUISTION IN PROCESS
RESUBMITTED TO MMSD/DNR FOR REAPPROVAL NOVEMBER 29,
MMSD WAITING ONDNR FORMAL APR0VAL
WDNR AND WDOT APPROVALS RECEIVED •
CONTRACTOR IS CONSIDERING ALTERNATE CONSTRUCTION
METHODOLOGY
JEWEL - OSCO FORCE MAIN AND LIFT STATION
PLANS AND SPECIFICATIONS ARE COMPLETE
JEWEL - OSCO REVIEW OF LOCATIONAND EXTERIOR OF
GENERATOR BUILDING REQUIRED
LAKEWOOD MEADOWS ADD NO 2
NOTHING NEW
LAKEWOOD CONDOMINIUMS (OVERLOOK BAY)
SAFE SAMPLE RECEIVED
WET CONNECTION OF WATER MAIN WAS COMPLETED
LOUGHNEY/NETTESHIEM (KELSEY DRIVE)/SALENTINE
RESTORATION REMAIN
RECORD DRAWINGS SUBMITTED TO CITY AND TOWN OF NOR WAY
MUSKEGO CENTER/BERG
AS BUILTS COMPLETED
PUNCH LIST SENT TO CONTRACTOR
is
• PAGE
PUBLIC UTILITIES COMMITTEE
MONDAY, FEBRUARY 19, 2001
MUSKEGO MOTOR CAR CO
PUNCH LIST RESENT TO CONTRACTOR
MMSD REVIEWED AS BUILTS FEBRUARY 2, 2000
CONTRACTOR TOLD R/M THEY WILL NOT COMPLETE DUE TO PAYMENTS NOT
RECEIVED
QUIETWOOD CREEK (CARITY)
INTERNAL CONSTRUCTION CONTINUES
WOODS ROAD WATER MAIN WET CONNECTION MADE NOVEMBER 16
RECORD DRAWINGS STAR TEDON PORTIONS ALREADY PAVED.
RAUSCH SANITARY PRESSURE SEWER- WOODS ROAD
UNDER CONSTRUCTION
MAYBE COMPLETED WEEK OF FEBRUARY 19TH
ROSEWOOD ESTATES (FORMERLY WOODGATE ESTATES)
POST PAVING PUNCHLIST (UNDERGROUND) COMPLETED
SAL FERRITO SEWER (PRIVATE SANITARY SEWER)
DEWATERING WELL NOT REMOVED
LATERALS NOT CONNECTED YET
• SARAH ESTATES (WOODS ROAD)
PLANS RECEIVED FOR REVIEW FEBRUARY 12, 2001
VICTORIAN VILLAS
VIDEO OF SEWER NOT YET RECEIVED
COMPLETED PROJECTS ONLY AWAITING MMSD APPROVAL OF RECORD DRAWINGS (AS
BUILTS):
CHAMPIONS VILLAGES - ADDITION 2 (PHASE THREE)
HOLTZ-ARROWOOD
KNUDSON FORCE MAIN
NORTH CAPE FARM
WISA FORCE MAIN - HILLENDALE DRIVE
`T c� e 2cA
GENERAL OFFICE (414) 272-5100 1-�31 �L
ACCOUNTING DEPT (414) 225-2047
Milwaukee Metropolitan Sewerage District
260 West Seeboth Street
P.O. Box 3049
Milwaukee, Wisconsin 53201-3049
(414) 272-5100 DATE 08/24/99
TO City of Muskego CREDIT NO.
W182 S8200 Racine Avenue
P.O. Box 903
Muskego, WI
CREDITED
Your Account This Date Is:
Make checks payable to:
Milwaukee Metropolitan Sewerage District
P.O. Box 689854
Milwaukee, WI 53268-9854
DEBIT NO.
CC9-99
DEBITED
I
• 1999 capital charges for the City Of Muskego
2000 Capital Charge $361,519
1998 Adjustment 0
Add: Properties located in New Berlin but serviced by Muskego
Real Property $6,778,040 x $.66128 = $4,482
Personal Property $ 887,351 x $.66128 = $587
Total Due 36$ 6,588
ig
Pursuant to MMSD Resolution No. 84-162-8, passed September 6, 1984, Resolution No. 97-195-11(02),
passed November 17, 1997, and Resolution No. 99-179-11, dated November 15, 1999 and the
provisions of applicable Wisconsin statutes, your capital charge billing is $366,588.
This capital charge is payable April 1, 2000. Payments not received by April 1, 2000 shall be subject to
a late charge determined at the rate of interest established in Resolution No. 84-162-8, as amended by
Resolution No. 96-155-11(02), ADOPTED November 18, 1996. The current applicable rate of interest on
late payments is12% on the amount due the District.
2MS: DUE WITHIN 30 DAYS OF THE DATE OF THE INVOICE
Your account has been CREDITED or DEBITED as above
MUSKEGOCC99.XLS12/10/99 4. 1
Jones Island Wastewater Treatment Plant South Shore Wastewater Treatment Plant
700 East Jones Street, Milwaukee 53207-1091 482-2040 8500 South 5th Ave., Oak Creek 53154-3506 764-1045