PUBLIC UTILITIES COMMITTEE - CITY OF MUSKEGO
MINUTES OF MEETING HELD THURSDAY, AUGUST 19, 1993
The meeting was called to order at 7:03 P.M. by Chairman David
J. Sanders. Also present were Committee Members Woodard and
Schneider, Mayor De Angelis, Rich Eberhardt (Ruekert & Mielke),
Utility Superintendent Scott Kloskowski, Ald. Misko and those
per the attached list.
The Committee reviewed the status of the following projects:
Hillendale-North of Hwy L (Sewer and Water)
Public Works Department will be patching bad spots in the road,
time permitting. Supt. Kloskowski will continue to try to
secure quotes for forced hookup for the Lawrence Schmidt
property.
Southeast Sewer Project
Engineering continuing.
The Committee reviewed status of REC allocations and noted that
there were 1,483 RECS as of January 1, 1993, and 1,385 RECS
left to allocate as of August 1, 1993.
A report from the Sewer Utility Clerk was reviewed listing the
following club houses that are not currently being charged:
Overlook Bay
Freedom Square
American College
Pioneer Center
The Committee directed that the Sewer Utility Clerk follow the
recommendation of MMSD and contact the above clubhouses to
advise that they are required to install a meter, which will be
their responsibility to maintain, and that the meter will be
read on a quarterly basis to estimate a sewer usage charge.
Rich Eberhardt, Ruekert & Mielke, discussed with the Committee
the status of Settler's Creek sewer system, College Square
sewer system and West Park Place sewer system. Ald. Schneider
moved to recommend acceptance of improvements. Seconded by
Ald. Woodard, motion carried.
The Committee deferred further discussion on proposed
amendments to the Sewer and Water Assessment policies until the
September meeting in order to review recommendations that will
• be forthcoming from the meeting with consultants scheduled for
Thursday, August 26, 1993.
Public Utilities Committee - Page 2
August 19, 1993
�1 Skip Brenden from the Muskego-Norway School District, appeared
before the Committee to request hookup for the proposed
District Office to be built west of the High School's current
football field, on Woods Road, off of Jean Drive (Woodcrest
Heights Subdivision). REC charges will be based on employee
count. Ald. Woodard moved to approve connection. Seconded by
Ald. Schneider, motion carried.
Mr. Mort Bailey appeared before the Committee to request sewer
connection for a property on the corner of Racine Avenue and
College Avenue in the City of New Berlin for a convenience
store/gas station/restaurant. Ald. Schneider moved to deny
request due to problems with transferring RECs through MMSD
between the City of Muskego and the City of New Berlin.
Seconded by Ald. Woodard, motion carried.
The Committee reviewed the Subdivider's Procedural Guide.
The Committee reviewed the MMSD Capacity Allocation report and
placed on file.
The Committee reviewed Sewer Utility Clerk's request for
direction on the REC charge for group homes. Ald. Schneider
moved to classify group homes as residential units.
Seconded by Ald. Woodard, motion carried.
• Stan Potrykus and Mr. Belsha appeared before the Committee to
request five sewer connections for a land division adjacent to
Settlers Creek and Durham Drive; three connections off of
Hidden Creek Court (Settlers Creek) and two off of Durham
Drive. Ald. Woodard moved to approve the five connections.
Seconded by Ald. Schneider, motion carried.
No action was taken by the committee on the Seefeld claim
(Kristin Downs) as the party did not appear.
The Committee reviewed revised
Environmental Technologies. A
Attorney for review.
contract from Northern
copy has been sent to the City
There was nothing new to report on the proposed water reservoir
site.
The Committee review bill from Underground Pipeline, Inc. in
the amount of $9,500.00 for additional footage for water loop
connection between Meadow Green West and Kristin Downs
Subdivision. Ald. Woodard moved to approve payment. Seconded
by Ald. Schneider, motion carried. The Committee directs the
City Engineer to research whether the developer of Meadow Green
West installed the correct amount of water main and, if not,
the additional cost will be charged to the developer.
The Committee reviewed the sewer plans for Lakewood Meadows
Addn. #1 and directed the City Engineers to forward the plans
Public Utilities Committee - Page 3
August 19, 1993
to MMSD. They also reviewed the water plans and noted that the
• well information was incomplete and that the water plans have
to be resubmitted to the Committee for approval with all the
required data.
•
The Committee reviewed sewer plans for Foxboro North and
recommend approval. They also discussed the layout for the
connections to properties off of Mystic Drive and determined
that the mains will be installed in the back of the properties.
The Mayor will coordinate a meeting between the affected
property owners and the engineer for the project to discuss
design and cost.
Rich Eberhardt discussed with the Committee several questions
on the recently submitted water plans for Candlewood Creek,
Phase I. The Committee directed that fire hydrants be placed
at the intersections of Woods Road/Kathryn Drive and Woods
Road/Stanwood Blvd. They also require that the water main
extensions at these intersections be clear of the pavement and
the water main in linwood Drive be extended to the limits of
Phase I.
The meeting adjourned at 10:00 P.M.
ca
Respectfully submitted,
Ald. Donna M. Woodard
Secretary