PUM19891005• PUBLIC UTILITIES COMMITTEE - CITY OF MUSKEGO
MINUTES OF MEETING HELD OCTOBER 5, 1989
The meeting was called to order at 7:05 P.M. by Chairman H.
Sanders. Also present were Committee Member D. Sanders, Mayor
Salentine, Utility Superintendent Kloskowski, Ald. Dumke, Ald.
Hilt and those per the attached list.
City Engineer Ken Ward and Financial Consultant Seegar Swanson
appeared before the Committee to review the amended Facilities
Plan for the extension of sewer service in the Area Southeast of
Big Muskego Lake. Ken Ward explained that there are a number of
alternatives available with Alternative #6 being the least cost
alternative at 2.2 million. An estimated 400 to 700 connections
would be available with this alternative. Properties along the
force main would not be assessed because an individual home could
not be connected to the system. All affected property owners
will be invited to a Public Hearing scheduled for November 1,
1989, at 7:00 P.M. to discuss the Facilities Plan.
The Committee discussed the 1990 Reserve Capacity Assessment and
the 1990 Water Capacity Assessment and noted that the dollars for
funding the infrastructure for the Area Southeast of Big Muskego
Lake is calculated on an 8% escalation of the original
• assessment. The front foot assessment will be reviewed for water
projects at the November meeting.
Mayor Salentine updated the Committee on the status of FLOW.
The Committee discussed the status of the Highway L Sewer
Project. City Engineer Ken Ward reported that the bids will be
let within the week and anticipate that the City will be awarding
bid in early January. The Committee reviewed the revised
Agreement between City of Muskego and Waste Management and
recommended Council approval.
The Utility Superintendent reported on Sewer Restorations and
noted that Woods Road is just about completed with the exception
of some ditching to be done on the north side of the road.
The Utility Superintendent advised the Commitee that the Odor
Control equipment for the Woods Road Lift Station has been
installed and he is waiting for the electrician to provide
service.
The Committee reviewed the status of the Lake/Park/Richards Water
Project. The City Engineers are drawing up the plans. The
Utility Superintendent alerted the Committee that four homes on
Lannon Drive, north of Highway L, have received bad well samples,
and the Committee should consider possibly including Lannon Drive
in this project and creating a loop on Highway L.
Public Utilities Committee - Page 2
October 5, 1989
The Utility Superintendent reported on the status of the Woods
Road -Lannon West Water Project. The contractor is finishing with
some ditching work still to be completed.
Mr. Joe Beatka, W192 S6685 Hillendale, appeared before the
Committee to request that the City look into the feasibility of
sewering this property and G & W Pattern, S66 W19444 Tans
Drive. The Committee moved to direct the City Engineers to
determine if these properties can be served.
Mayor Salentine updated the Committee on his meeting with the
City of New Berlin in regards to the MMSD contract. The City of
New Berlin's Committee of the Whole recommended approval, subject
to staff review, of continuing to include the entire service
valuation in Muskego's contract with the cost of the unconnected
valuation to be paid by New Berlin.
The meeting adjourned at 9:45 P.M.
•
ca
a
Respectfully submitted,
Ald. David J. Sanders
Secretary