PSM19900607. PUBLIC SAFETY COMMITTEE - CITY OF MUSKEGO
MINUTES OF MEETING HELD JUNE 7, 1990
The meeting was called to order at 8:00 P.M. by Chairman Taube.
Also present were Committee Members Simmons and Patterson, G. P.
Lee, Assistant Fire Chief Zahn (Tess Corners Volunteer Fire
Dept.) and Carl Mack (Muskego Volunteer Fire Company).
The Committee further reviewed the revisions to the Sprinkler
Ordinance with G. P. Lee. After complete review, Ald. Patterson
moved to recommend adoption of the revised Sprinkler Ordinance.
Seconded by Ald. Simmons, motion carried.
G. P. Lee reported on the following condemnations:
1. Kurer (W142 S8028 Durham Drive) - Kurer to
appear at the Plan Commission on June 19, 1990
to discuss original intent and clarification of
Resolution 39-89. Court date of June 30, 1990.
2. Lobel (W181 S9134 Parker) - Judge will be setting
new court date. New citation to be issued for
June 27, 1990.
• 3. Benke (S110 W20544 So. Denoon) - Call made to Mrs.
Benke on June 6, 1990. Mrs. Benke is checking into
her insurance and stated that A. Guhr will take
down building as soon as possible.
4. Fischer (W172 S7513 Center Drive) - Duplex will
be down sometime between July 1 and August 1, 1990.
G. P. Lee reviewed with the Committee a revised form for Erosion
Control for new construction (attached). This new procedure will
incorporate a fee of $1.00 per 1,000 sq. ft. because of more
inspections to be made to assure compliance.
The meeting adjourned at 9:20 P.M.
Respectfully submitted,
Ald. William T. Simmons
Secretary
ca
Attachment: Soil Erosion Exhibit
• For: Erosion Control Chapter 29 of the Municipal Code
Dear Owner -------------------------------------------------------
This letter is to inform you of the new policy for enforcing the
Erosion Control Ordinance. The ordinance was adopted at the end
of 1986. The purpose of that ordinance was to minimize the
amount of sediment and other pollutants carried by run off from
some contruction sites into the lakes and streams or drainage
facilities and a Jacent lands.
When the ordinance was passed we had adopted an agreement that
stated step by step what should be done during the course of
construction. This agreement was used to gain compliance. It
has become apparent that many of the owners were unaware of the
requirements and the builders would install silt barriers, charge
the owner and then remove them prior to the final grading on the
lot. This generally left the entire lot subject to erosion.
inis new policy will incorporate a fee because of more
inspections to be made to assure compliance.
CITY OF MUSKEGO
EROSION CONTROL ORDINANCE
(or 1/2 acre or less disturbance)
retain soil on lot sites during construction, the following control devices
d techniques shall be used:
1. Before Excavation, Foundation and Basement Construction.
a. TO minimize erosion trom the site, preserve existing
vegetation or provide and maintain a solid wall of
hay or straw bales as necessary or until stabilization of
the lot as per 3.b.
b. The stockpile of excavated soil shall be protected
from eroding from the site.
C. Use only minimum routes over the curb and sidewalk for
truck and heavy equipment.
d. Backfill basement walls, rough grade the lot and
remove excess soil from the lot as soon as possible.
e. Provide for streeet cleaning.
2. Before Framing, Roofing, and Siding Construction.
a. or construction access, provideavel surfaced driveway.
b. Provide for street cleaning.
3. Before Finishing Phases
a. F-InIsHea grade of lot shall conform to
approve drainage patterns as shown on the plat,
unless change approved by the Building Inspector, in
writing.
b. Stabilize lot by temporary or permanent seeding
and mulching, or sodding after fine grading.
C. Where eaves and downspouts are used, provide extenders
and diffusers to spread out and direct water to
vegetation areas.
d. Provide for street cleaning.
Devices or Techniques Submitted by the Owner as Attached.
I agree to install all the control devices and implement all the control
techniques which are indicated on this check list for the parcel listed below.
Hay Bales
Sediment Trap
OWNER: Date:
Owner'sAddress:
Address of Parcel:
Parcel Description:Lot: Block: Subdivision
Silt Fence
I, as Agent for above Owner, certify that I am acting under the authority of
the Owner and that the Owner and I both understand all the conditions of this
permit and agree to abide by them.
AGENT:
Address:
pPhone:
ignature:
Fee $ 25.00 Min. Paid
1.00 Der 1000 sq. ft.