The meeting was called to order by Chairman Schaumberg at 8:30 P.M.
Also present were Aldermen Dumke, Wallner, Pienkos and Supt. Bertram.
Supt. Bertram reviewed with the committee the proposed plans submitted
by Ray Gray which could be used to install a storm sewer between Lots
29 and 30 in the Guernsey Meadows Subdivision, said storm sewer to be
extended to the rear lot line of the Dietzler and Mattson properties.
Aid. Schaumberg moved that the proposed plans be approved, seconded
by Ald. Dumke, motion carried.
Supt. Bertram reported that he is still attempting to remove the bog
in'Big Muskego Lake in the vicinity of Caesar's Dam.
The committee discussed the possibility of opening Luehring Drive to
provide more efficient snowplowing and to improve fire department and
rescue service to the homes in the area.
Supt. Bertram to contact First National Bank of Waukesha regarding
a vehicle count on Highway 24 which will be required if their efforts
to have the State construct a shadow lane are to be successful.
The committee received correspondence indicating that the developers
of Lake Lore Subdivision will install a storm sewer to the lake.
The committee received correspondence indicating that Roger Johnson,
developer of Shagbark Subdivision, has agreed to install inverts
along Martin Drive this fall.
The committee discussed the problem of the endwall on the Eugene
Johnson property on Lannon Drive.
Correspondence received from the developers of Lake Lore Subdivision
requesting that a bond be set to insure completion of all improvements.
The matter will be considered at the next meeting.
The committee discussed the matter of the dangerous curve on Martin Drive
in the area of the former Nike Site and reviewed correspondence from
the Waukesha County Highway Commission indicating that it is possible
to receive 75% of the cost of the project from the Safer Off-System
Act of 1977. They also reviewed correspondence from the State of
Wisconsin Department of Transportation indicating the need for re-
designing the project in order to meet design standards of the Off-
System Project. The committee will review the matter at its next
meeting.
Supt. Bertram reported that the ditch problems on Groveway Lane have
been resolved.