PWKA Committee Status Report 051205 Sean E. McMullen, Director W182 S8200 Racine Avenue ENGINEERING/BUILDING Muskego, WI 53150 (262) 679-5686 INSPECTION DEPARTMENT PUBLIC WORKS COMMITTEE STATUS REPORT FOR: MAY 2005  Tess Corners Pond Expansion/Drainage Issues (New Berlin) - The public notice expired and no comments were received. The DNR is completing the paper work for permit which we should receive by our meeting date of March 22, 2004.The environmental issues have been approved and the DNR’s engineer has signed off on the project. The permit application should be going to publication within the next 15-20 days. This has to be in the paper for 30 days and if no one objects, a permit is then issued. Once a permit is issued we will look at land acquisition with the City of New Berlin with a late summer or early Fall 2004 construction start. The public notice is in the paper and it expires on 3-4-04. To date, the DNR has not had any public comments on the project and Sean will be meeting with the City of New Berlin this week for land acquisition. 3/15/04 - The public notification has expired and no comments were received. The DNR is completing the paper work for the permit, which we should, received by our meeting date of March 22, 2004. 4/22/04 - Received DNR and Army Corp of Engineers permit. Relocation order is going to the City of New Berlin’s Common Council agenda for their second meeting in May and will be discussing the project with the DNR and their relocation experts before that meeting. Looking at a late summer, early fall construction date. 5/26/04 - Relocation Order went to the City of New Berlin’s Public Works Committee at the end of May and will be going to their Common Council meeting in June. A meeting has been th scheduled with DNR/City of New Berlin/City of Muskego for June 11 to go over the DNR’s process and timelines for land acquisition. 6/28/04 – The City of New Berlin has approved all relocation orders and they have been sent to the DNR. Still looking at a Fall 2004 construction date. 7-13-04 – Meeting held between City of New Berlin and DNR on 7-12-04 regarding appraisals and acquisition. Another meeting has been scheduled for 7-21-04 at the City of Muskego with City of New Berlin and R&M representatives. 8-12-04 – Appraisals have been ordered. We should receive the appraisals within the next 35 to 45 days. 9-14-04 – Bids were open. Please review the attached email from J. P. Walker, City of New Berlin. 10-13-04 – The City of New Berlin is in the process of land acquisitions for the project. Sean and a representative from the City of New Berlin will be meeting with the DNR on Friday, 4/18/05 MAY COMMITTEE REPORT PAGE 2 October 15 to request approval to continue grant funding for this project until June 2005. A th meeting for Thursday, October 14 is scheduled to meet with the affected City of New Berlin property owners to discuss land acquisition. Re-bid opening date is October 21, 2004 at 10:AM at the City of New Berlin. 11-11-04 – New bids received. Cost came in less than lst bid. New bid is $2,622,000. Will be working with City Attorneys for both communities on inter-municipal agreement for this project. 1-12-05 – The City of New Berlin’s Common Council rejected bids and did not approve the intermunicipal agreement with the City of Muskego so the project has been dropped. This item will be taken off of future agendas. 2-18-05 – We have been contacted by the City of New Berlin inquiring about the 50% payment. We have completed the review of the outstanding invoices and, to date, it appears that there is $68,886.47 outstanding with $4,514.17 that was recently invoiced. 3-17-05 – Revised invoice was sent to the City of New Berlin. Sean and J. P. Walker met to review the invoices. The City of New Berlin will be running the vouchers through on their 3/22/05 common council meeting. 4/15/05 – Nothing has been received to date. 5/12/05 – Nothing has been received to date.  Janesville Road Reconstruction Project - The DNR had objections regarding navigating waterways and the retention pond in back of BioSource Flavors. The City of Muskego requested a meeting with the DNR, on behalf of Waukesha County, and we were able to negotiate minor changes to address the DNR’s concerns. This delay will backup the bid date thst from January 22, 204 to February 17, 2004. The construction start of April 15 thru May 1 will not change. The Utility relocation work scheduled for completion the third week in March. Bids were received on February 18, 2004 and the apparent low bidder is Mann Brothers with an estimated construction cost of $4,360,417.04. The City of Muskego’s portion is under the original estimate. 3/15/04 - Preconstruction meeting is scheduled for 3/25/04 and the th construction operations meeting is scheduled for 3/12/04. Construction start of April 15 thru stth May 1 has not changed. 4/22/04 - Construction will start on April 26. All construction details can be seen by linking into the City of Muskego’s website - engineering - links - Janesville Road Reconstruction. 5-26-04 – Construction still in progress and contractor (Mann Bros.) has been requested to supply to the City a monthly report on their schedule. Copies will be given to all aldermen. We have been working with Waukesha County and contractor to keep the access points to all of the subdivisions open as long as possible and to make the closures as minimal as possible. 6/28/04 – City has received a new schedule for road closures and Woodland Place to Tess th Corners will be closed on July 6 for 28 days. 7/13/04 – Moving along. Hit a large area of contaminated soil on the Schaumberg property which may jeopardize the road closures. Will be working with contractor to remove the soil within the timeline and it may necessitate some additional lane closures. 8/12/04 – Working with Waukesha County on acquiring either an easement or some type of other arrangements for a parking lot at the old Prestige Auto next to Country Trader. We are waiting for the DNR to approve plans on box culvert so we can rip out the old culvert. Paving should commence on 8-16-04. Will be switching traffic by the 1st of September. The project is 3 1/ 2 weeks behind schedule. 2 4/18/05 MAY COMMITTEE REPORT PAGE 3 9-14-04 – Sent the legal descriptions to Waukesha County. Their Cooperation Council will review the lease agreements for the parking lot. Should have something from them by the October meeting for committee review. 10-13-04 Waukesha County is still reviewing the City’s request to lease area west of Country Trader for municipal parking. Hoping to have an answer sometime in November. Scott and Sean are working with Waukesha County and DNR to resolve a sewer problem. 11-11-04 – Finance Committee will be reviewing and approving the final lease documents for the area west of Country Trader for municipal parking. 1/12/05 – Waukesha County’s Board of Public Works have approved the lease agreement for the parcel directly west of Country Trader for municipal parking and it is now being taken up by the full County Board. If approved, details on construction and maintenance will have to be determined. 2-18-05 – Janesville Road Reconstruction: a. Lease agreement with Waukesha County for parking lot. Waukesha County Board and our Common Council have both approved the lease agreement. However, prior to any work being done, the parking lot and the fence installation needs to be designed and approved by the County Board of Public Works. Discussion from last year’s COW stipulated that work being done on the Municipal Parking Lot must be approved by the Finance Committee prior to any expenditure. Last year, engineering staff estimated approximately $40,000. - $50,000. for the installation of this parking lot. Those monies were removed from the 2005 Capital Budget. Engineering staff will begin the process in early March for surveying and design of the parking lot. b. Lighting – We have met with Waukesha County on the height and location of the lighting along Janesville Road. We will be bringing the plans for approval to the March meeting. Discussion at COW in 2004 requested that COW review the lighting plan. After Public Works Committee approval, the lighting plan will be submitted to COW for review. c. Plowing – Several complaints have come from residents from Woodland East to Tess Corners Drive. Most of these complaints related to the “benching” of the snow across their driveways. City staff will be working with Waukesha County’s to discuss options to minimize the effects of this “benching” to the individual driveways. d. Final Restoration – Mann Brothers is scheduled to complete the final restoration before June 1, 2005. This includes all of the sodding, permanent surface course, permanent pavement markings, signs, etc. 3-17-05 – Nothing new to report.  4-15-05 Parking Lot – The survey work is finished. Will be submitting parking lot plans to Waukesha County and will be including the parking lot in the 2005 Paving Program. th Lighting – Lighting plans will be distributed at the April 18 meeting for discussion. Restoration – Final restoration project meeting kick-off minutes are attached. 5-12-05 Final road restoration will be completed after installation of light poles. Anticipated date of completion is June lst. 3 4/18/05 MAY COMMITTEE REPORT PAGE 4 - Parking Lot: Sean will bring parking lot plans to Monday’s meeting. Lighting: One-half of the physical conduits have been installed. Light poles should be in within the next five (5) weeks.  Martin Drive Realignment - All of the works has been completed and final payments have been held due to sewer trench settlement at the Basse driveway. Once the paving plants open in spring, this will be corrected, at no cost to the City, and the funds will be released. At the request of the Public Services Committee, Waukesha County has reopened the request for traffic signals at this intersection. They are approximately 20% completed with the study review and once I receive this information, I will forward on to the committee. Nothing new to report. Nothing new to report. 3/15/04 - Nothing new to report. 4/22/04 - Met with the th contractor on May 4 to take care of the road damage caused by sewer settling. 5-26-04 – Met with contractor and we are working on methods to repair the roadways and those repairs will be done this summer. 6/28/04 – Sean will check with Vivian Kuss from WE Energies on the status of the relocation of streetlight. Contractors for Chamberlain Hills Subdivision are doing replacement on segments going into subdivision as well as ditch replacements. 7/13/04 – Discussed with WEPCO the need for a street light at intersection of Martin and Janesville. It was agreed that the most cost-effective way is to delay the project until the Lindemann property on the corner is developed and distribution is installed. City has also requested that the existing light be taken down to avoid further accidents. 8/12/04 - Nothing new to report. 9/14/04 – Nothing new to report. 10/13/04 – Areas are still settling. Will be discussing with Committee the option of wedging the area and then do a replacement in spring of 2005. 11-11-04 – Payne & Dolan is installing a wedge over the damaged areas. This will stay on the agenda until permanent repairs are completed by Super Excavators in spring of 2005. 1/12/05 – Permanent repairs will be completed by Super Excavators in spring of 2005. 2/18/05 – Nothing new to report. 3/17/05 – Nothing new to report. 4/15/05 – Nothing new to report. 5/12/05 – Nothing new to report.  Durham Drive Realignment - Waiting to find out if CMAQ funding has been approved. Once we get final word from the State, the committee will be notified. Still waiting word from the DNR. 3/15/04 - Nothing new to report. 4/22/04 - Nothing new to report. 5/26/04 – Nothing new to report. 6/28/04 – Nothing new to report 7/13/04 – There is a Department of Transportation meeting on 7/14/04 regarding status of funding. Sean will report at the 7/19/04 meeting. 4 4/18/05 MAY COMMITTEE REPORT PAGE 5 8/12/04 – We will be receiving a formal letter from the DOT that we are not receiving the funding for Durham Drive for this budget cycle and we will be reapplying for the next budget in November. 9/14/04 – Nothing new to report. 10-13-04 – Sean is working with DNR on filling of wetland issues. The DNR has approved the final alignment and wetland impacts. Storm sewer design must be submitted for approval prior to a permit being issued. 11-11-04 – Nothing new to report. 1/12/05 – Nothing new to report. 2/18/05 – McShane south to “OO”. The City received word from the Department of Transportation that the STP-D funding for the 2005-2006 biennium has been cut and no funding will be available until the 2007-2008 biennium. Should the City wish to construct this road prior to that timeframe, ii will need to be locally funded or we will need to look at other federal funding opportunities. A copy of the Southwest Wisconsin Local Transportation Funding Handbook will be made available for the committee’s review. 3-17-05 – Nothing new to report. 4/15/05 Nothing new to report. 5/12/05 Nothing new to report. Idle Isle Bridge – 5/26/04 – Met with Suzie Link (Chairman of the Little Muskego Lake District Commissioners) today to discuss construction schedule which will be from September 1, 2004 to November 1, 2004. Will be doing the boat launch at the same time. However, the th boat launch will need to be down until around the 15 of November, 2004. th 6-28-04 – The work on Idle Isle Bridge is scheduled to commence on September 12 through st November 1. The bridge will be closed most of that time because it is a complete deck replacement. Wayne Delikat, Public Works Superintendent, suggested that a sign be posted s th soon as possible advising of closing. A sign will be posted by July 9 to inform the public on the closures of the parks and launch. 7/13/04 – This project will be bid at the end of this month. 8/12/04 – Bi opening is scheduled for August 19, 2004 at 11:00 AM and will go to common council on August 24, 2004 for approval. A copy of the plans and specifications are on the desk in the Alderman’s office for review prior to meeting. 9-14-04 – Contracts are being signed today. 10-13-04 – Delay in start of project due to cars and boat trailers in the immediate area. Contractor started last week. 11-11-04 – Bridge deck is completed. The railings are up. Contractor will be out within the next seven to ten days to install the beam guard. Once beam guard is installed, the bridge will be permanently opened. 1/12/05 – Guardrail scheduled to be installed this week. 5 4/18/05 MAY COMMITTEE REPORT PAGE 6 3/17/05 – Contractor couldn’t install the guardrail due to thickness of the frost. Guardrail will be installed in early Spring. 4/15/05 – Nothing new to report. 5/12/05 – Guardrail will be installed this week.  Freedom Square Ponds – 7/13/04 – Waiting for letter from the DNR approving dump site. 8/12/04 – Received letter from the DNR approving dump site. We will finalize documents and will be bidding shortly. 9/14/04 – Work began on the storm sewer Thursday, 9-9-04. Making final changes to the bidding documents. Bid date of the pond project will be October 12, 2004. thth. 10/13/04 – Bid was awarded on October 12. Work is scheduled to begin on November 20 11-11-04 – Contracts were mailed to contractor. Engineering/Building Inspection Director working with alderman of the District and Condo Association to resolve questions and concerns brought up by the Condo Association and as issues are discussed, correspondence will be sent to the committee for information. 1/12/05 – On site preconstruction meeting is scheduled for this week with work starting at the end of next week. Concrete invert between pond 1 and pond 2 will be replaced with a 4’ wide invert. Material going to Johnson Sand & Gravel. 2/18/05 – Pond #1 is approximately 70% completed. The contractor has requested approval from the City and the DNR to excavate deeper, approximately 18” deeper, than the approved excavation. The reason for this additional depth is due to scans of thicker clay, which, if allowed to be excavated out, will expose the granular base of the pond improving the water quality. Pond #2 is approaching 20% - 25% completion. Contractor will be back onsite at the end of this week and next week to finalize dredging. We have discussed the replacement of the invert between the two ponds with the contractor. The contractor is willing to trade the allowance of the additional excavation for the replacement of the concrete invert. The financial impact of this additional dredging and the concrete invert is “0”. 3/17/05 – Pond #1 and Pond #2 have been completely dredged. Contractor installed temporary seed, fertilizer and much for erosion control purposes. Contractor will be coming back to complete the final restoration for both Pond #1 and Pond #2, including the invert installation in spring. Complaint was received about sedimentation into the newly constructed storm sewer. Terra Enterprises will be out to remove the sedimentation from the pipe and discharge point. 4/15/05 – Contractor was out to begin restoration. Numerous complaints were received from residents and contractor to resolve restoration issue. 5/12/05 – City received claim from property owner claiming cracking in basement walls. Quietwood Creek Diverting Structure – Plan were approved at the Plan Commission for the Bay Lane parking lot. The diverting structure will be installed in early 2005. 3/17/05 – Nothing new to report. 5/12/05 – Nothing new to report. Field Drive Repaving – S74 W21052 Field Drive – 3/17/05 Nothing new. 6 4/18/05 MAY COMMITTEE REPORT PAGE 7 4/15/05 -Nothing new. 5/12/05 -Nothing new. Candlewood Village, Candlewood Creek, Quietwood East and Quietwood Creek – Engineering staff will be creating new tables and/or flow charts describing the steps that developments are in the approval process. This chart will be submitted for committee review beginning in March and will be updated monthly. 3/17/05 – Monthly flow chart attached. 4/15/05 – Monthly flow chart attached. 5/12/05 – Monthly flow chart attached. Settlement Center – Old Town Hall – City reviewed the inspection reports from Independent Inspections, LLC. A copy is in your packet. A timeline of events from inception of this project to date will be handed out at the meeting. 3/17/05 – Engineering staff working with several contractors and Bonestroo on the architectural requirements for the State. 4/15/05 – Signed contract for the design of Town Hall with Bonestroo. Project kick-off meeting held today, Friday, 4/15/05, and the project is getting back on track for final completion. 5/12/05 – All buildings were inspected by Mayor, Sean, Maintenance personnel and Craig which resulted in all locks being changed because of safety concerns. 7