Public Works Committee- MINUTES - 2/18/2013CITY OF MUSKEGO Approved
PUBLIC WORKS COMMITTEE
MINUTES OF MEETING HELD MONDAY, FEBRUARY 18, 2013
Ald. Neil Borgman called the meeting to order at 6:00 PM. Also present were Ald. Robert
Wolfe, Ald. Eileen Madden, Public Works Director David Simpson and Public Utilities
Superintendent Scott Kloskowski.
Ald. Borgman led those present in the Pledge of Allegiance.
The meeting was noticed in accordance with the Open Meeting Laws on February 15, 2013.
APPROVAL OF MINUTES OF DECEMBER 17, 2012
Ald. Madden moved to approve the minutes of December 17, 2012. Seconded by Ald.
Wolfe. Motion carried 3-0.
STAFF REPORTS
None
STATUS OF PROJECTS
Director Simpson gave updates on the following projects:
Janesville Road Reconstruction – County still plans on a mid-June start for Phase II.
Working on utility relocations. Trees have been removed. Everything on track.
Tess Corners Reconstruction – Complete. Repair sink hole. Contractor will be back in
Spring.
Racine Avenue Recreational Trail – 95% plans right now. Have one change to make near
the wetland area. DNR wants us to go around wetlands instead of across.
UNFINISHED BUSINESS
None
NEW BUSINESS
Moorland Dental Center Request for Refund of Sanitary Sewer Charges – Director
Simpson stated he received a request from Moorland Dental Center for a refund for
their sanitary sewer bill for the third quarter of 2012. Moorland Dental Center is
billed for their sanitary usage based on actual water consumption (as all commercial
properties), which is determined by utilizing the water meter which tells the City how
much water was utilized. Moorland Dental Center did not elect to install a deduct
meter, which basically is a meter that would go on your hose bibs or irrigation
systems, anything that would guarantee water would go outside and not down the
drain. Because of that there third quarter bill for sewer usage in 2013 was
approximately $3,900, which is substantially more than their normal quarterly bill of
around $100. A portion of the $3,900 goes to MMSD. In this case it’s about $800.
If we were to consider a refund, we would have to recognize that any commercial
business without a deduct meter would have the same right to come forward and
request a refund. After discussion with Committee and Jason Thompson, DDS,SC,
2
of Moorland Dental Center, as to going back to the contractor that did the plumbing
or a policy change, it was decided to put this on hold and look into it further and
bring it back to the next meeting.
Belle Chasse Phase II- Discussion of Mystic Drive Realignment at Woods Road –
Director Simpson advised Belle Chasse Phase II is scheduled to come forward this
Spring. As part of any new development we look at impacts to the City infrastructure
whether it be sewer, water, storm water, traffic outlets, and miscellaneous items. As
part of this development, Phase II connects the entire subdivision Phase I and
Phase II to Mystic Drive. Mystic Drive is currently aligned with Woods Road but not
at a 90 degree angle. Some point in the past when the land was subdivided at the
corner of Mystic and Woods, whoever was here at the time had the landowner
dedicate the proper right-of-way we would need to realign Mystic at Woods Road.
This has been on the staff’s radar for quite some time to look at the possibility to
make it a safer intersection. When the subdivision discussions occurred in the last
month with this Phase coming through I thought it would be a good time to discuss
the realignment and the impact the subdivision would have on that intersection. I
ran the numbers and came up with Belle Chasse adding about 22% more traffic. I
have estimated the cost of intersection realignment at $60,000, therefore, the
developer’s share would be $13,200. Ald. Madden made a motion to approve a
provision for a lump sum payment of $13,200 to the City. Seconded by Ald. Wolfe.
Motion carried 3-0.
Approval of Belle Chasse Phase II Construction Plans – Phase I plans were
approved back in 2008 per Director Simpson. It is unclear in the minutes if Phase II
was approved at that time. Minutes just say Belle Chasse plans. I’m bringing the
plans back to you for Phase II approval. The plans have not changed from the
original 2008 date. The only changes I would ask the developer to make would be
some grading change in the central portion of Phase II for drainage safety issues.
Other than that everything is the same. The developer has agreed to make the
change. Ald. Madden made a motion to approve Belle Chasse Phase II construction
plans contingent upon technical corrections. Seconded by Ald. Wolfe. Motion
carried 3-0.
Approval of Conveyance of Rights in Valley Drive to Waukesha County – Director
Simpson stated as part of the Janesville Road reconstruction project Waukesha
County does a transportation plat that shows all the strips of land the County has
taken along the right-of-way existing and proposed. The Valley Drive right-of-way
has come into question as to its official dedication during the title search process.
Because of this, the County has decided to purchase the Valley Drive right -of-way
as if it were existing private land. As the County purchases this land, the assumed
easement rights that we own on these lands need to be released so that the new
right-of-way does not have easement encumbrances. City owned water main and
sanitary sewer are within this newly purchased area. As this is a mutually beneficial
project, the County if requesting a no cost conveyance. Ald. Wolfe made a motion to
approve conveyance of rights in land for the Janesville Road reconstruction project
within Valley Drive. Ald. Madden seconded. Motion carried 3-0.
3
Discuss Potential Intersection Analysis- Woods Road & Moorland Road – Per
Director Simpson the intersection of Woods and Moorland is currently a four way
stop. During morning and especially afternoon peak hours the intersection is
experiencing pretty heavy delays. Alderman Wolfe asked me to look at exploring
some alternatives for this intersection. I called some consultants and got some
baseline pricing what it would take to do a full intersection analysis. They were
telling me anywhere from $12K-$15K depending what work we really wanted from
them. That would depend on which alternative we could see as an option. If we
wanted more detail it could be more than $15K or if less under $12K. For this price,
the following scope could be accomplished:
Data Collection -
12-hour intersection count
Crash data, 5-years
Intersection geometrics
20-year traffic projections
Signal warrant analysis
Comparative analysis of stop signs, signal and roundabout for the following elements –
Traffic operations
Safety
Very rough impacts (relatively generic, but will id potential red flags)
Ped/bike accommodations
Written tech memo summary
Conceptual level designs could be created for three design alternatives
The designs could be used to refine the right-of-way impacts and costs for the three alternatives
Should the Committee wish to move ahead with this project, I can utilize funds from
the 2013 Road Program and proceed with enlisting the assistance of a consultant to
complete the project as described in the scope above or as modified by the
Committee. Ald. Borgman made a motion to go ahead with project at the cost of $12K-
$15K necessary to discuss the warrants of the study and direct staff to proceed. Ald.
Madden seconded. Motion carried 3-0.
NEW BUSINESS PLACED ON FILE
None
COMMUNICATIONS AND MISCELLANEOUS BUSINESS AS AUTHORIZED BY LAW
ADJOURNMENT
Ald. Madden moved to adjourn the meeting 6:59 PM. Ald. Wolfe seconded. Motion carried
3 -0.
Jeanne Struck
Recording Secretary