Alderman Noah Fiedler called the meeting to order at 6:00 PM. Also present were
Aldermen Dan Soltysiak and Keith Werner, City Engineer David Simpson, and Public
Utilities Superintendent Scott Kloskowski. Public Works Superintendent Wayne Delikat was
absent.
Ald. Fiedler led those present in the Pledge of Allegiance.
The meeting was noticed in accordance with the Open Meeting Law on May 12, 2011.
APPROVAL OF MINUTES OF APRIL 25, 2011
Ald. Werner moved to approve the minutes of April 25, 2011. Seconded by Ald. Soltysiak.
Motion carried 3-0.
STAFF REPORTS
None
STATUS OF PROJECTS
Janesville Road Reconstruction (Moorland to Racine) – City Engineer Simpson stated
nothing big on this yet. Utilities are working on relocate design.
Durham Drive Reconstruction & Sanitary Sewer Project – City Engineer Simpson advised
utility crews are moving forward rapidly. Majority of power poles are relocated, main lines
are moved over, and service switch overs this week. Time Warner cable promised us to be
out there this week. Progress meeting tomorrow morning. As soon as Time Warner is out
of our way we will be able to move forward much faster. Dewatering wells are in place for
sanitary sewers.
McShane Pump Station Upgrade – Bypass pump is in per Public Utilities Superintendent
Kloskowski.
Ryan Road Sanitary Sewer Relay – Public Utilities Superintendent Kloskowski stated it is
completed.
Storm Water Studies (Luehring Drive, Circle Drive, and Catalina Drive) – City Engineer
Simpson gave a status update. Luehring Drive is going well. Circle Drive – still waiting on
district. Catalina Drive 90% design is done.
PPII Reduction & Sanitary Sewer Backup Prevention Programs – City Engineer Simpson
stated going to Finance and Council next week.
UNFINISHED BUSINESS
None
NEW BUSINESS
Discuss mandatory connection to sanitary sewer under 21.05(2)(a) of the City’s Municipal
Code as it relates to S90 W13322 Boxhorn Drive – City Engineer stated the residents of S90
2
W13322 Boxhorn Drive expressed concern regarding the impending requirements that they
will have to connect to public sewer within nine months of said public sewer becoming
available for use. A land division across the street has caused a low pressure force main to
be installed which will be publicly dedicated in the near future. This dedication will trigger
the nine month window for connection to the public sewer for this home. The homeowners
are requesting that they not have to connect their home to the new sewer; however, the
current code does not allow for any variation from the required connection. The home is
currently served by a private treatment system. The current code exists in order to protect
public health by reducing the chance of contamination of ground water or surface waters.
City Engineer Simpson would write a letter to everyone here and the other two homes
stating what occurred here Ald. Werner made a motion that dedication of improvements
would be required upon connection of the first new or existing home along new sanitary
sewers. Ald. Soltysiak seconded. Motion carried 3-0.
Recommendation of purchase of Public Utilities Chevrolet Colorado Pickup Truck – Public
Works Superintendent Kloskowski stated bids had been requested from three dealers and
he would recommend accepting the proposal from Holz Motors Inc. Ald. Soltysiak made a
motion to accept the proposal in the amount of $16,233.00 from Holz Motors Inc. Seconded
by Ald. Werner. Motion carried 3-0.
Recommendation of approval of engineering design services contract for Utility Relocations
required by the reconstruction of Janesville Road – City Engineer Simpson advised as part
of the Janesville Road Reconstruction Project, all utilities located within the right-of-way
must be relocated, where needed, at the expense of each utility. Working with the County
and the design engineer for Janesville Road to establish a scope and cost to complete all
the necessary survey and design work for our utilities. The proposal from Ayres Associates
will provide for the necessary work to be completed for a cost of $16,500.00. Ald. Soltysiak
made a motion to approve pending negotiations with Ayres regarding Limitation of
Professional Liability amount. Ald. Werner seconded. Motion carried 3-0.
NEW BUSINESS PLACED ON FILE
None.
COMMUNICATIONS AND MISCELLANEOUS BUSINESS AS AUTHORIZED BY LAW
City Engineer Simpson asked committee if they would like to go all electronic. Ald. Werner
requested adding a title with New Business topics.
ADJOURNMENT
Ald. Soltysiak moved to adjourn the meeting at 6:40 PM. Ald. Werner seconded. Motion
carried 3-0.