PCR2014022RESOLUTION #P.C. 022-2014
APPROVAL OF A BUILDING SITE AND OPERATION PLAN AMENDEMENT
FOR KLAM CONSTUCTION/REALTY LOCATED IN THE NE ¼ OF SECTION 17
(MERCURY DRIVE & JANESVILLE ROAD / TAX KEY NO. 2225.999.012)
WHEREAS, On January 29, 2014 plans were submitted by Gerry Klamrowski for a Building, Site and
Operation Plan Amendment for the property located in the NE ¼ of Section 17 (S81 W19255 Janesville
Road / Tax Key No. 2225.999.012), and
WHEREAS, Said property is currently zoned B-2 Local Service Center District and said use is a permitted
use with Building, Site, and Operation Plan approval, and
WHEREAS, The existing building and site layout were originally approved by the Plan Commission under
#P.C. 113-2007, and
WHEREAS, The original approval for this site/building were for use by the Milwaukee Journal Sentinel as
a distribution facility, and
WHEREAS, The original approval had a stipulation in it stating that any change of use or user would need
to be reviewed by the Plan Commission, and
WHEREAS, There are now three real estate/construction/property maintenance based businesses, all
owned and operated by the same person, that wish to occupy the building/site, and
WHEREAS, The new site users will not have any outdoor parking or storage of any equipment, trucks,
trailers, or materials on site, and
WHEREAS, The businesses will typically have regular office hours of 8 AM – 5 PM, with some possible
limited operations occurring on weekends, and
WHEREAS, There would be no large scale deliveries occurring since deliveries are received via FedEx, or
similar, and
WHEREAS, The only exterior change being thought about is the widening of an existing exterior garage
door to the rear of the building, and
WHEREAS, No signage details have been provided at this time, but the petitioner plans on submitting for
sign permits at a later date and all signage will require permits and approval through the Planning
Department and/or the Plan Commission.
THEREFORE BE IT RESOLVED, That the Plan Commission approves of the Building, Site and Operation
Plan amendment submitted by Gerry Klamrowski for the property located in the NE ¼ of Section 17.
BE IT FURTHER RESOLVED, That any proposed change of use or user for this building must first receive
approvals from the Plan Commission and/or Planning Department through a BSO amendment.
BE IT FURTHER RESOLVED, That all signage will require Plan Department and/or Plan Commission
approval and permits.
BE IT FURTHER RESOLVED, That no outdoor parking or storage of any type is allowed on the site
including, but not limited to, dumpsters, pallets, supplies, materials, racking, trailers, trucks, equipment,
etc.
BE IT FURTHER RESOLVED, That a copy of said plans be kept on file in the Community Development
Department and that all aspects of this plan shall be maintained in perpetuity unless otherwise authorized
by the Plan Commission.
BE IT FURTHER RESOLVED, That failure to comply with the approval contained in this resolution shall
result in the imposition of fines of $100 per day, the initiation of legal action, or both.
Plan Commission
City of Muskego
Adopted: March 4, 2014
Defeated:
Deferred:
Introduced: March 4, 2014
ATTEST: Kellie McMullen, Recording Secretary