CCR2020051-AttachmentMuskego Parks Soil Amendments
Page 1
Green Solutions Funding Agreement G98005P57
Muskego Parks Soil Amendments
1. The Parties
This Agreement is between the Milwaukee Metropolitan Sewerage District (District), 260 West
Seeboth Street, Milwaukee, Wisconsin 53204-1446, and the City of Muskego (Muskego), W182
S8200 Racine Avenue, Muskego, Wisconsin 53150.
2. Basis for this Agreement
A. Wisconsin law authorizes any municipality to establish an intergovernmental cooperation
agreement with another municipality for the furnishing of services (Wis. Stat. sec. 66.0301).
B. The District is responsible for collecting and treating wastewater from locally-owned
sewerage systems in the District’s service area.
C. During wet weather, stormwater enters the sewerage system, increasing the volume of
wastewater the District must collect and treat.
D. During wet weather, stormwater directly enters surface water, increasing pollution levels in
those waterways and increasing the risk of flooding.
E. Green infrastructure, such as constructed wetlands, rain gardens, green roofs, bioswales, and
porous pavement, reduces the volume of stormwater in the sewerage system and the amount
of pollutants discharged to surface waters.
F. The District wants to expedite the amount of green infrastructure installed in its service area.
G. Muskego plans to install green infrastructure that supports the District’s green infrastructure
goals.
3. Date of Agreement
This Agreement becomes effective immediately upon signature by both parties and ends when
Muskego receives final payment from the District or when the parties terminate this Agreement
according to sec. 14 of this Agreement.
4. District Funding
The District will reimburse Muskego for the cost of the project described in the attached project
description (project), up to $295,604. The District will provide funding after the District
receives the Baseline Report and the Conservation Easements.
Muskego Parks Soil Amendments
Page 2
5. Location of Project
The project will amend soil in several parks, as identified in the project description.
6. Baseline Report
After completion of the project, Muskego will provide a Baseline Report using forms provided
or approved by the District. The Baseline Report will include:
A. a site drawing, showing the project as completed;
B. a topographic map of the project site;
C. design specifications for the project, including rainwater capture capacity (maximum per
storm) and other information regarding runoff rate reduction or pollutant capture;
D. a tabulation of the bids received, including bidder name and price;
E. a copy of the executed construction contract;
F. a legal description of the property where the project is located, including parcel identification
numbers;
G. photographs of the completed project;
H. a maintenance plan;
I. an outreach and education strategy, including a description of events or activities completed or
planned;
J. an itemization of all construction costs, with supporting documentation;
K. a W-9 Tax Identification Number form;
L. a Small, Veterans, Women, and Minority Business Enterprise Report; and
M. an Economic Impact Report, showing the total number of people and the estimated number of
hours worked on design and construction of the project by Muskego’s employees, contractors,
consultants, and volunteers.
7. Procedure for Payment
Muskego will submit an invoice to the District for the amount to be reimbursed. The invoice
will document all costs to be reimbursed. Invoices from consultants will provide: their hourly
billing rates, if applicable; the hours worked, by individual; and a summary of the tasks
accomplished.
Muskego will send the Baseline Report and the invoice to:
Andrew Kaminski, Project Manager
Milwaukee Metropolitan Sewerage District
260 West Seeboth Street
Milwaukee, Wisconsin 53204-1446
The District will not provide reimbursement until the project is complete and the District has
received all required deliverables.
Muskego Parks Soil Amendments
Page 3
8. Changes in the Project and Modifications to the Agreement
Any changes to the project must be approved by the District in writing in advance. The District
will not reimburse for work that is not described in the original project description unless
Muskego obtains prior written approval from the District.
9. Modifications to this Agreement
Any modifications to this Agreement will be in writing and signed by both parties.
10. Project Maintenance
Muskego will maintain the project for at least eleven years. If the project fails to perform as
anticipated or if maintaining the project is not feasible, then Muskego will provide a report to the
District explaining the failure of the project or why maintenance is not feasible. Failure to
maintain the project will make Muskego ineligible for future District funding until Muskego
corrects maintenance problems.
11. Permits, Certificates, and Licenses
The Muskego is solely responsible for compliance with all federal, state, and local laws and any
required permits, certificates, or licenses.
12. Procurement
Muskego must select professional service providers according to the ordinances and policies of
Muskego. Muskego must procure all non-professional services, such as construction, sewer
inspection, and post-construction restoration, according to State of Wisconsin statutes and
regulations and the ordinances and policies of Muskego. Whenever work valued over $25,000 is
procured without the use of a public sealed bidding process, the District may request and
Muskego must provide an opinion from a licensed attorney representing Muskego explaining
why the procurement complies with State of Wisconsin law and the ordinances of Muskego.
13. Responsibility for Work, Insurance, and Indemnification
Muskego is solely responsible for planning, design, construction, and maintenance of the project,
including the selection of and payment for consultants, contractors, and materials.
Muskego is solely responsible for ensuring compliance with Wisconsin prevailing wage law.
The District will not provide any insurance coverage of any kind for the project or the Muskego.
Muskego will defend, indemnify, and hold harmless the District and its Commissioners,
employees, and agents against all damages, costs, liability, and expenses, including attorney’s
fees and related disbursements, arising from or connected with the planning, design,
construction, operation, or maintenance of the project.
14. Terminating this Agreement
The District may terminate this Agreement at any time before the commencement of
construction. After the commencement of construction, the District may terminate this
Agreement only for good cause, including, but not limited to, breach of this Agreement by
Muskego. Muskego may terminate this Agreement at any time, but Muskego will not receive
any payment from the District if Muskego does not complete the project.
Muskego Parks Soil Amendments
Page 4
15. Conservation Easements
After the completion of construction, the District must receive a Conservation Easements from
Muskego. The Conservation Easements will be limited to the project. The term of the
Conservation Easements will be eleven years. Muskego will cooperate with the District to
prepare the Conservation Easements.
16. Exclusive Agreement
This Agreement is the entire agreement between Muskego and the District for the project.
17. Severability
If a court holds any part of this Agreement unenforceable, then the remainder of the Agreement
will continue in effect.
18. Applicable Law
The laws of the State of Wisconsin apply to this Agreement.
19. Resolving Disputes
If a dispute arises under this Agreement, then the parties will try to resolve the dispute with the
help of a mutually agreed-upon mediator in Milwaukee County. The parties will equally share
the costs and fees associated with the mediation, other than attorney’s fees. If the dispute is not
resolved within 30 days after mediation, then either party may take the matter to court.
20. Notices
All notices and other communications related to this Agreement will be in writing and will be
considered given as follows:
A. when delivered personally to the recipient's address as stated in this Agreement; or
B. three days after being deposited in the United States mail, with postage prepaid to the
recipient's address as stated in this Agreement.
21. Independence of the Parties
This Agreement does not create a partnership. Muskego does not have authority to make
promises binding upon the District or otherwise have authority to contract on the District's
behalf.
22. Assignment
Muskego may not assign any rights or obligations under this Agreement without the District's
prior written approval.
23. Public Records
Muskego will produce any records in the possession of Muskego that are subject to disclosure by
the District pursuant to the State of Wisconsin’s Open Records Law, Wis. Stats. secs. 19.31 to
19.39. Muskego will indemnify the District against all claims, demands, or causes of action
resulting from the failure to comply with this requirement.
Muskego Parks Soil Amendments
Page 5
MILWAUKEE METROPOLITAN
SEWERAGE DISTRICT
CITY OF MUSKEGO
By: ____________________________ By:
Kevin L. Shafer, P.E.
Executive Director
Richard Petfalski, JR.
Mayor
Date: ___________________________ Date: ______________________________
Approved as to Form
By: ___________________________
Attorney for the District
By:
Sharon Mueller
Clerk-Treasurer
Date: _______________________________
Muskego Parks Soil Amendments
Page 6
Green Solutions Funding Agreement G98005P57
Muskego Parks Soil Amendments
Project Description
Muskego will amend soils in parks as shown in the following table. The goal is to improve the
health of the grass in the parks. The soil amendments will promote the development of thick root
systems that help absorb more rain, which will reduce water pollution and the amount of water
that can get into sewers. With thicker root systems, grass will be more drought-tolerant and
more competitive with weeds.
Park Soil Amendment Area
(Square Feet)
Bluhm 654,929.15
Horn 119,463.47
Idle Isle 84,079.49
Jensen 110667.07
Kurth 310,813.42
Lions 57,987.60
Manchester Hill 117726.31
Moreland 187,416.21
Old City Hall 68,107.00
Park Arthur 153,104.15
Sand Hill 312,189.21
Schmidt 88,510.15
Veterans 229,974.95
Total 2,494,968.18
Schedule
Muskego will complete the project by December 31, 2020.
Budget
This project has the following estimated cost:
Low Bidder was Beilfuss Corporation: $142,394.24
Top Dress Material (Waupaca Sand and Solution Quote): $60,710
Construction Contingency for Green Infrastructure: $40,000
Construction inspection time: $20,000
City of Muskego Staff time: $20,000
Consultant time for RFP process: $12,500
Total: $295,604.24
Outreach and Education
Muskego will post educational signage and describe the project and its benefits in a community
newsletter or web page.
Muskego Parks Soil Amendments
Page 7
Educational materials will acknowledge District funding for the Project.
Signage will:
1. be either designed and provided by the District or provided by Muskego and approved by
the District,
2. be at a location approved by the District, and
3. identify the District as funding the green infrastructure by name, logo, or both.