CCR2018007-Improvements-Edgewater
COMMON COUNCIL – CITY OF MUSKEGO
RESOLUTION #007-2018
DEDICATION OF PUBLIC IMPROVEMENTS
FOR EDGEWATER HEIGHTS (Phase II) SUBDIVISION
WHEREAS, Edgewater Heights, LLC, hereafter called “DEVELOPER” has constructed public
improvements in and around Racine Ave and Edgewater Heights Way including all water distribution,
sanitary sewers, storm sewers, and paving including any and all equipment and appurtenances which may
in any way be a part thereof or pertain to, in and for the Edgewater Heights (Phase II) Subdivision; and
WHEREAS, the DEVELOPER has completed the construction and installation of the following
improvements:
Sanitary Sewer
305 LF at $23.00/LF of 2” HDPE Sanitary Force Main
711 LF at $24.00/LF 3” HDPE Sanitary Force Main
775 LF at $48.00/LF 1 ½” HDPE Sanitary Lateral
1 Each at $1,100/Each 3” Valve and Box
2 Each at $1,200/Each Flushing Station
1 Each at $3,900 Connection to Ex. Force Main
Total – Sanitary Sewer/Force Main $69,714.00
Water Main
32 LF at $74.00/LF of 6” C900 Water Main
1,125 LF at $$68.00/LF of 8” C900 Water Main
125 LF at $150.00/LF of Directionally Drill 8” Water Main
687 LF at $50.00/LF of 1 ¼” HDPE Water Service
3 Each at $1250.00/Each of 6” Valve and Box
2 Each at $1500.00/Each of 8” Valve and Box
3 Each at $3600.00/Each of Hydrant
1 Each at $4,400.00/Each of Connection to Ex. Water Main
Total – Water Main $153,918.00
Storm Sewer
864 LF at $37.00/LF of 6” PVC Storm Sewer
991 LF at $$42.00/LF of 12” RCP Storm Sewer
447 LF at $45.00/LF of 15” RCP Storm Sewer
305 LF at $54.00/LF of 18” RCP Storm Sewer
6 Each at $900.00/Each of 12” End Section
11 Each at $2,000.00/Each of 24”x36” Inlet
9 Each at $2,300.00/Each of 48” Storm MH
2 Each at $2,200.00/Each of Pond Outlet Structure
6 Each at $840.00/Each of Rip Rap at End Sections
Total – Storm Sewer $167,715.00
Paving
2,900 LF at $10.15/LF of 30” Mountable Curb and Gutter
4,600 SY of 8” Stone and 3.5” Binder
170 SY 3’ Stone Shoulder
Total - Paving $124,885.00
and appurtenances (collectively called “IMPROVEMENTS”) in accordance with the provision of Chapter
18 of the Municipal Code of the City of Muskego, hereafter called the “CITY”, and the City Engineer has
certified the systems’ acceptability; and
WHEREAS, it is the Developer’s intent to, without charge to the CITY, unconditionally give,
grant, convey and fully dedicate the IMPROVEMENTS to the CITY, free and clear of all encumbrances,
and together with mains, conduits, pipes, plants, machinery, equipment and appurtenances which relate
directly to the utilization of such IMPROVEMENTS; and
WHEREAS, the DEVELOPER shall guarantee the public improvements to be dedicated against
any defects due to faulty materials or workmanship which appear within a period of one (1) year from the
date of dedication and shall pay for any damages resulting therefrom to the CITY property and shall
indemnify the CITY against any claims, suits, or liabilities brought against the CITY at any time arising
out of the alleged defects or other failure of this guarantee; and
WHEREAS, the DEVELOPER must complete the installation of the final lift of asphalt on all
roadways per subdivider’s agreement and said work will be considered dedicated and accepted upon
written notification by the City Engineer; and
NOW, THEREFORE, BE IT RESOLVED That the Common Council of the City of Muskego,
upon the recommendation of the Finance Committee, does hereby accept dedication and acceptance of the
public improvements in and for the Edgewater Heights (Phase II) Subdivision.
DATED THIS 23rd DAY OF JANUARY, 2018
SPONORED BY:
FINANCE COMMITTEE
This is to certify that this is a true and accurate copy of Resolution #007-2018 which was adopted by the
Common Council of the City of Muskego.
_____________________________
Clerk-Treasurer