CCR2016002-Improvements-Aster Hills
COMMON COUNCIL - CITY OF MUSKEGO
RESOLUTION #002-2016
DEDICATION OF PUBLIC IMPROVEMENTS
FOR ASTER HILLS ESTATES SUBDIVISION
WHEREAS, HBT of Aster Hills Estates LLC, hereafter called “DEVELOPER” has constructed public
improvements in and around Boxhorn Reserve Drive, Bonningale Court, Aster Hills Court, Ballard Court,
Lindley Court, Upland Lane and Harrington Court including all water distribution, sanitary sewer facilities,
storm sewers, and paving including any and all equipment and appurtenances which may in any way be a
part thereof or pertain to, in and for the Aster Hills Estates Subdivision; and
WHEREAS, the DEVELOPER has completed the construction and installation of the following
improvements:
Sanitary Sewer
4,078 LF at $76.00 /LF of 8” Sanitary Sewer Pipe with granular backfill
548 LF at $83.00 /LF of 8” Sanitary Sewer Pipe with restrained joints with granular backfill
2,444 LF at $59.00 /LF of 6” Sanitary Laterals with granular backfill
756 LF at $ 27.00 /LF of 2” Force main pipe – directional bore
274 LF at $31.00 /LF of 2” Force main pipe with spoil backfill
15 LF at $37.00 /LF of 2” Force main pipe with granular backfill
141 LF at $30.00 /LF of 1-1/2” Pressure pipe with spoil backfill
68 LF at $36.00 /LF of 1-1/2” Pressure pipe with granular backfill
2 EACH at $ 2,000 /EACH Force main cleanout manholes
1 EACH at $ 500 /EACH Sanitary service valve
30 EACH at $ 3,000 /EACH Sanitary standard manhole
1 EACH at $ 6,000 /EACH Connection to existing manhole and adjust rim elevation
Total – Sanitary Sewer/Force main $636,247.00
Water Main
4,308 LF at $64.00 /LF of 8” water main pipe with granular backfill and tracer wire
194 LF at $48.00 /LF of 8” water main pipe with spoil backfill and tracer wire
523 LF at $66.00 /LF of 8” water main pipe with restrained joints with granular backfill and tracer wire
240 LF at $95.00 /LF of 6” Hydrant leads with granular backfill and tracer wire
26 LF at $110.00 /LF of 6” Hydrant leads with restrained joints with granular backfill and tracer wire
15 EACH at $4,000 /EACH of Hydrants, aux. valve with box, extensions, and tracer wire with location box
12 EACH at $1,200 /EACH of 8” Butterfly valve with box
2498 LF at $45.00 /LF 1-1/4” Water service with granular backfill
2 EACH at $6,000/EACH Connection to existing water main
Total – Water Main $544,012.00
2
Resolution #002-2016
Storm Sewer
535 LF at $57.00 /LF of 12” Storm sewer with granular backfill
1,123 LF at $52.00 /LF of 12” Storm sewer with spoil backfill
205 LF at $58.00 /LF of 15” Storm sewer with granular backfill
805 LF at $47.00 /LF of 15” Storm sewer with spoil backfill
33 LF at $61.00 /LF of 18” Storm sewer with granular backfill
301 LF at $57.00 /LF of 18” Storm sewer with spoil backfill
39 LF at $74.00 /LF of 24” Storm sewer with granular backfill
946 LF at $67.00 /LF of 24” Storm sewer with spoil backfill
4,642 LF at $31.50 /LF of 6” Storm sewer with granular backfill
27 EACH at $750 /EACH of Storm cleanouts
2 EACH at $700 /EACH of 12” End section with gate
3 EACH at $750 /EACH of 15” End section with gate
2 EACH at $1000 /EACH of 24” End section with gate
44 EACH at $1,500 /EACH of 2’ x 3’ Inlets
18 EACH at $1,600 /EACH of 48” Storm sewer manholes
5 EACH at $1,300 /EACH of 48” Storm sewer field inlets
5 EACH at $1,900 /EACH of 60” Storm sewer manholes
1 EACH at $3,000 /EACH of Rip rap and fabric
Total – Storm Sewer $509,977.00
Paving
15,596 SY at $3.90/SY of 4” base course (3/4” crushed limestone T.B. state gradation #2)
18,933 SY at $2.95/SY of 4” base course (1-1/4” crushed limestone T.B. state gradation #1)
170 LF at $23.00/LF of 30” standard vertical face concrete curb and gutter
10,056 LF at $9.50/LF of 30” mountable curb and gutter
101 LF at $9.50/LF of 30” mountable curb and gutter reverse pan (traffic circle)
60 LF at $28.00/LF of 6” barrier curb (traffic circle)
44 SY at $67.00/SY of 8” concrete pavement over 6” base aggregate dense 1-1/4” (traffic circle)
15,596 SY at $13.00/SY of 4” Asphaltic concrete binder course (two 2” base lifts E-0.3, 12.5mm) with tack coat
between all lifts
1,076 SY at $21.50/SY of Asphalt recreational trail (3” surface course, state gradation No. 3 bituminous concrete (E-
0.3, 9.5mm) over 6-3/4” crushed limestone T.B.)
3 EACH at $775/EACH Concrete recreational trail ramps with detectable warning field
1 at $2,500/Lump Sum of Permanent signing and striping
190 LF at $1,996.90/Lump Sum of Wood split rail fencing along portion of recreational trail on CTH OO
Total – Paving (Not including Final Lift of Asphalt) $454,410.15
and appurtenances (collectively called “IMPROVEMENTS”) in accordance with the provision of Chapter 18
of the Municipal Code of the City of Muskego, hereafter called the “CITY”, and the City Engineer has
certified the systems’ acceptability; and
WHEREAS, it is the Developer’s intent to, without charge to the CITY, unconditionally give, grant,
convey and fully dedicate the IMPROVEMENTS to the CITY, free and clear of all encumbrances, and
3
Resolution #002-2016
together with mains, conduits, pipes, plants, machinery, equipment and appurtenances which relate directly
to the utilization of such IMPROVEMENTS; and
WHEREAS, the DEVELOPER shall guarantee the public improvements to be dedicated against any
defects due to faulty materials or workmanship which appear within a period of one (1) year from the date of
dedication and shall pay for any damages resulting therefrom to the CITY property and shall indemnify the
CITY against any claims, suits, or liabilities brought against the CITY at any time arising out of the alleged
defects or other failure of this guarantee; and
WHEREAS, the DEVELOPER must complete the installation of the final lift of asphalt on all
roadways per the subdivider’s agreement and said work will be considered dedicated and accepted upon
written notification by the City Engineer; and
NOW, THEREFORE, BE IT RESOLVED That the Common Council of the City of Muskego, upon
the recommendation of the Finance Committee, does hereby accept dedication and acceptance of the public
improvements in and for the Aster Hills Estates Subdivision.
th
DATED THIS 12 DAY OF JANUARY, 2015
SPONSORED BY:
FINANCE COMMITTEE
This is to certify that this is a true and accurate copy of Resolution #002-2016 which was adopted by the
Common Council of the City of Muskego.
_____________________________
Sharon Mueller, City Clerk-Treasurer