CCR19990433/99jmb
COMMON COUNCIL - CITY OF MUSKEG0
RESOLUTION #43-99
APPROVAL OF EXTRACTIVE PERMIT
SUPERIOR EMERALD PARK LANDFILL
WHEREAS, Superior Emerald Park Landfill submitted an application for an extractive
permit; and
WHEREAS, The necessary public hearing has been held; and
WHEREAS, The Plan Commission has recommended approval to the Common
Council contingent upon an interim construction agreement being approved by the
Siting Committee and the Common Council, receipt of restoration bond in the amount
of $32,180.70, and the other conditions outlined in #P.C. 190-98. as amended.
NOW, THEREFORE, BE IT RESOLVED That the Common Council of the City of
Muskego, upon the recommendation of the Plan Commission, does hereby approve of
an Extractive Permit for Superior Emerald Park Landfill subject to the conditions
outlined by the Plan Commission.
DATED THIS 23rd DAY OF MARCH, 1999
SPONSORED BY:
Ald. Nancy Salentine
This is to certify that this is a true and accurate copy of Resolution #43-99 which was
adoDted bv the Common Council of the City of Muskego.
AMENDED *** (03-16-99)
AMENDED ** (03-02-99)
AMENDED (12-01-98)
RESOLUTION #P.C. 190-98
APPROVAL OF A CONDITIONAL USE PERMIT FOR
AN EXTRACTIVE PERMIT FOR SUPERIOR EMERALD PARK LANDFILL
AT THE PROPERTY LOCATED AT W124 SI0629 124 STREET
WHEREAS, Conceptual plans were submitted on October 12, 1998, November 3, 1998
and November 6, 1998 by Superior Emerald Park for an Extractive Permit at W124 S10629 124
Street (U.S. HWY 45) and
WHEREAS, Said property is currently zoned 1-2 General Industrial and A Agricultural,
and the proposed use is a permitted use by conditional grant in both districts, and
WHEREAS, The proposed extractive operation would be as follows: activity from 7:OO
a.m. and close down at 4:30 p.m. on weekdays *with no Saturday, Sunday or Holiday
operation; there will be up to 10 trucks carrying, on average, 20 tons of material at two loads per
hour for a total of up to 190 trips in a 9 112 hour day; the removal of an estimated ***377,000
cubic yards of clay, and
WHEREAS, The extractive operation. would begin approximately 560 feet west of U.S.
HWY 45, extend hrther west approximately another 650 feet, have a north-south dimension of
approximately 920 feet, and result in a "25 foot deep pit being approximately **22 feet below the
elevation of U.S. HWY 45, and
WHEREAS, The intent is to utilize the pit to create a pond area if a currently proposed
landfill expansion for the same location is not permitted by approving authorities.
THEREFORE BE IT RESOLVED, That the Plan Commission approves a conditional use
for an extractive permit in compliance with the site and operation plans submitted October 12,
1998, November 3, 1998, November 6, 1998, and ***March 5,1999 by Superior Emerald park
for the Superior Emerald Park property located at W124 SI0629 124 Street (US HWY 45).
**THEREFORE BE IT FURTHER.RESOLVED, That approval is contingent upon
interim construction agreement being approved by Siting Committee and Common
Council. That the road surfaces to maintain a dirt-free and dust-free environment within
one hour of the presence of said condition. Plan Commission approves Restoration Plan
Alternative A ***with a Restoration Bond in the amount of %32,180.70.
Plan Commission
City of Muskego
Approved 03-02-99 03-16-99
Deferred 11-17-98 12- 1-98
12- 15-98 01-05-99
01-19-99 02-02-99
02-1 6-99
03-09-99