CCR1995183COMMON COUNCIL - CITY OF MUSKEG0
RESOLUTION #183-95
AWARD OF BID
Bellview Detention Pond and Storm Sewer Project
WHEREAS, the City advertised for bids for the Bellview Detention Pond and
Storm Sewer Project, and the following bids were received:
C. W. Purpero, Inc.
New Berlin Grading, Inc.
Sunny Slope Grading, Inc.
$124,459.00
162,221.50
122,346.00
WHEREAS, the City engineers and the Public Works Committee have
recommended approval of the low bid from Sunny Slope Grading in the
amount of $122,346 for the Bellview Detention Pond and Storm Sewer
Project .
Muskego, upon the recommendation of the City Engineers and the Public
NOW, THEREFORE, BE IT RESOLVED that the Common Council of the City of
Works Committee, does hereby accept the low bid from Sunny Slope
Grading, Inc. for the Bellview Detention Pond and Storm Sewer Project
contingent upon a change order acceptable to the City Engineers being
executed extending the completion date for the storm sewer portion of
the project to commence on February 1, 1996 if all necessary easements
have been obtained and if not, contractor agrees to extend the starting
date of the storm sewer portion of the contract until said easements are
obtained. e IT FURTHER RESOLVED that the Mayor. and Clerk are hereby authorized
to sign the necessary documents in the name of the City, and are
further authorized to sign any change orders at their discretion upon
recommendation of the City Engineers.
DATED THIS 12th DAY OF SEPTEMBER , 1995.
SPONSORED BY:
PUBLIC WORKS COMMITTEE
Ald. Domonic D'Acquisto
Ald. Mark Suhr
Ald. Brian R. Misko
This is to certify that this is a true and accurate copy of Resolution
#183-95 which was adopted by the Common Council of the City of Muskego.
@9/95 jmb