CCR2009113-Bonestroo-Streambank
(Removed at 7/28/2009 Common Council Meeting)
COMMON COUNCIL - CITY OF MUSKEGO
RESOLUTION #113-2009
APPROVAL OF AGREEMENTS FOR ENGINEERING SERVICES AND PERMITTING
FOR THE RYAN ROAD-BOXHORN DRIVE CHANNEL RESTORATION PROJECT
WHEREAS, In 2006, the City entered into the attached “Supplemental Agreement” with
Bonestroo, Rosene, Anderlik and Associates, Inc. for preliminary engineering services
related to the Ryan Road-Boxhorn Drive Channel Restoration Project; and
WHEREAS, The original contract cost was $72,359. The costs spent to date total
$55,200; and
WHEREAS, The City Engineer requests that the attached “Supplemental
Services/Agreement No. 1” be approved so the project can continue to move forward.
The Agreement reflects that the City will pay the remaining contract amount of $17,150
plus an additional $12,850, which does not include Reimbursable Expenses or Permit
Fees estimated to be $1,500; and
WHEREAS, The Finance Committee reviewed the initial “Supplemental Agreement”
and “Supplemental Services/Agreement No. 1” with Bonestroo and recommended
approval to the Common Council.
NOW, THEREFORE, BE IT RESOLVED That the Common Council of the City of
Muskego, upon the recommendation of the Finance Committee, does hereby approve
the initial “Supplemental Agreement” and “Supplemental Services/Agreement No.1”
with Bonestroo for the Ryan Road-Boxhorn Drive Channel Restoration Project.
BE IT FURTHER RESOLVED That the Mayor is authorized to execute the necessary
documentation in the name of the City.
DATED THIS DAY OF , 2009.
SPONSORED BY:
FINANCE COMMITTEE
Ald. Noah Fiedler
Ald. Keith Werner
Ald. Tracy Snead
This is to certify that this is a true and accurate copy of Resolution #113-2009 which
was adopted by the Common Council of the City of Muskego.
______________________________
Clerk-Treasurer