CCR2008214-Dedication-Big Muskego II
COMMON COUNCIL - CITY OF MUSKEGO
RESOLUTION # 214-2008
DEDICATION AND ACCEPTANCE OF PUBLIC IMPROVEMENTS IN AND FOR
BIG MUSKEGO ESTATES II SUBDIVISION AND
REDUCTION IN LETTER OF CREDIT
WHEREAS, Homes By Towne of Big Muskego Estates LLC, hereafter called
“DEVELOPER” has constructed public improvements which include public street improvements
on Blue Heron Lane and Schaefer Drive and all sanitary sewer, water main and storm sewer
facilities in and for the Big Muskego Estates II Subdivision; and
WHEREAS, the DEVELOPER has completed the construction and installation of the
following improvements:
Sanitary Sewer
2,323 LF at $ 52 /LF of 8” Sanitary Sewer Pipe with granular backfill
340 LF at $ 29 /LF of 6” Sanitary Laterals with spoil backfill
785 LF at $ 36 /LF of 6” Sanitary Laterals with granular backfill
18 VF at $ 60 /Riser of 6” Sanitary Lateral Risers
14 EACH at $ 2,275 /EACH Standard Manholes
1 EACH at $ 3,800/EACH Construct New Manhole/Existing Sanitary Sewer
3 EACH at $ 500/EACH Adjust Existing Manhole Rim Grade
1 EACH at $ 1,500/EACH Connection to Existing Manhole
Watermain
1,831 LF at $ 46 /LF of 12” watermain with granular backfill and tracer wire
932 LF at $ 37 /LF of 8” watermain with granular backfill and tracer wire
4 EACH at $ 1,075/EACH of 12” Butterfly Valve with box
2 EACH at $ 750/EACH of 8” Butterfly Valve with box
9 EACH at $ 2,500 /EACH of hydrants, box, extensions, tracer wire
1,275 LF at $ 27 /LF 1-1/4” Water Service
1 EACH at $ 3,000/EACH Connection to existing watermain
Storm Sewer
59 LF at $ 38 /LF of 21” Storm Sewer with spoil backfill
6 LF at $ 42 /LF of 21” Storm Sewer with granular backfill
244 LF at $ 35 /LF of 18” Storm Sewer with spoil backfill
52 LF at $ 38 /LF of 18” Storm Sewer with granular backfill
41 LF at $ 31 /LF of 15” Storm Sewer with spoil backfill
1 EACH at $ 1,000/EACH CMP including connection to existing culvert
33 LF at $ 62/LF of 19” x 30” Storm Sewer with granular backfill
148 LF at $ 57/LF of 19” x 30” Storm Sewer with spoil backfill
5 EACH at $ 525 /EACH of 12” End Section
1 EACH at $ 650 /EACH of 18” End Section
Reso. #214-2008 Page 2
1 EACH at $ 775 /EACH of 21” End Section
1 EACH at $ 1,100 /EACH of 19” x 30” End Section
1,443 LF at $ 20/LF of 6” PVC Sump Pump with cleanouts and insulation
497 LF at $ 21/LF of 6” PVC Storm Laterals including insulation and granular backfill
18 EACH at $ 1,300/EACH Storm Sewer inlets
11 EACH at $ 1,400/EACH 48” Storm Sewer Manholes and Round Inlets
2 EACH at $ 2,300/EACH 60” Storm Sewer Manholes
Paving
2,774 C/L LF of roadway including 8” of gravel base course,
30” and 36” curb and gutter,
4” of Asphaltic Concrete Binder Course,
1 ½” Asphaltic Concrete Surface Course
at a lump sum of $ 220,398
and appurtenances (collectively called “IMPROVEMENTS”) in accordance with the provision
of Chapter 18 of the Municipal Code of the City of Muskego, hereafter called the “CITY”, and
the City Engineer has certified the systems’ acceptability; and
WHEREAS, it is the Developer’s intent to, without charge to the CITY, unconditionally
give, grant, convey and fully dedicate the IMPROVEMENTS to the CITY, free and clear of all
encumbrances, and together with mains, conduits, pipes, plants, machinery, equipment and
appurtenances which relate directly to the utilization of such IMPROVEMENTS; and
WHEREAS, the DEVELOPER shall guarantee the public improvements to be dedicated
against any defects due to faulty materials or workmanship which appear within a period of one
(1) year from the date of dedication and shall pay for any damages resulting therefrom to the
CITY property and shall indemnify the CITY against any claims, suits, or liabilities brought
against the CITY at any time arising out of the alleged defects or other failure of this guarantee;
and
WHEREAS, the DEVELOPER has already created the appropriate segregated Storm
Water Maintenance fund in the amount of $2,500.00 as required by the Big Muskego Estates II
Retention Pond Maintenance Agreement; and
WHEREAS, any remaining Developer’s Deposit will be returned to the DEVELOPER
after all invoices from Ruekert-Mielke and/or City staff have been paid; and
WHEREAS, Ruekert-Mielke and the City Engineer have recommended a full release of
the letter of credit for the Big Muskego Estates II Subdivision from its current balance of
$49,000.00 which will bring the remaining amount to $0.00; and
NOW, THEREFORE, BE IT RESOLVED That the Common Council of the City of
Muskego, upon the recommendation of the Finance Committee, does hereby accept dedication
and acceptance of the public improvements within the Big Muskego Estates II Subdivision and
authorize full release of the remaining letter of credit for said Subdivision.
Reso. #214-2008 Page 3
TH
DATED THIS 9 DAY of DECEMBER , 2008
SPONSORED BY:
FINANCE COMMITTEE
Ald. Tracy Snead
Ald. Keith Werner
Ald. Tina Schaefer
This is to certify that this is a true and accurate copy of Resolution #214-2008 which was
adopted by the Common Council of the City of Muskego.
_____________________________
Janice Moyer, Clerk-Treasurer